Decision Maker: Assistant Director for Shared Services
Decision published: 21/12/2017
Effective from: 30/07/2017
Decision:
Appoint Meritec Limited to provide benefits
processing service for a period of 8 months as allowed under
Contract Standing Order 10.01.2b)
Lead officer: Mark Rudd
Decision Maker: Director for Adult Social Services
Decision published: 21/12/2017
Effective from: 04/08/2017
Decision:
To approve the award contract to Somerset
Gardens Family health Care Centre for the provision of GP Support
to clients at Protheroe House under CSO10.01.1b
Lead officer: John Everson
Decision Maker: Director for Adult Social Services
Decision published: 21/12/2017
Effective from: 31/07/2017
Decision:
For the Director of Adult Services to approve
the implementation of Contract Standing Order 10.01 and waive the
requirement to tender the contract with Ameo Ltd, Gatenby Sanderson
and Hays Ltd for two interim project managers and one interim
business analyst for a period of 5 months from 2 August 2017 to 29
December 2017 at a maximum total cost of £165,440 + VAT
Lead officer: Beverley Tarka
Decision Maker: Director for Adult Social Services
Decision published: 21/12/2017
Effective from: 24/07/2017
Decision:
To approve the extension of contract to
Wealden Rehab to provide specialist bathing equipment at Osborne
Grove Nursing Home following CQC Inspection.
Lead officer: Beverley Tarka
Decision Maker: Head of Operations
Decision published: 20/09/2017
Effective from: 26/07/2017
Decision:
To approve officers' recommendations as set
out in item 9 of the attached report
Lead officer: Ann Cunningham
Decision Maker: Director for Regeneration
Decision published: 01/09/2017
Effective from: 26/07/2017
Decision:
This report was approved under delegated
authority for the award of a loan agreement to The High Cross
London Ltd for the value of £72,000 subject to the approval
of license, lease and planning permission.
The business will use the loan in order to refurbish the property
to operational standards and to purchase new equipment. Works
include the installation of essential services, seating, new
windows, bar/coldroom, kitchen, toilet and interior and exterior
lighting and signage
Lead officer: Helen Fisher
Decision Maker: Head of Operations
Decision published: 17/08/2017
Effective from: 26/07/2017
Decision:
To approve officers’ recommendations as
set out in item 9 of the attached report
Lead officer: Ann Cunningham
Decision Maker: Interim Director Commercial & Operations
Decision published: 16/08/2017
Effective from: 03/08/2017
Decision:
Haringey, Client & Commissioning Manager
seeks authorisation to appoint a consultant for the delivery of the
Phase 1 works package of repairs and maintenance at Bruce Castle
Museum and Haringey Archives.
Lead officer: Stephen McDonnell
Decision Maker: Director for Housing and Growth
Decision published: 09/08/2017
Effective from: 29/07/2017
Decision:
That the Director of Housing & Growth in
accordance with Contract Standing Orders (CSO) 10.01.1(b) and
10.01.2(d)(ii) agrees to waive the requirement to obtain 3
competitive quotations as required under CSO 9.01 and in accordance
with CSO 9.07.1(c) to award a contract to Sanctuary Supported
Living (SSL), for an initial term of 2 years with an option to
extend for a further period of 1 year. The total price over the
proposed life of the contract is £165,570.93.
Lead officer: Dan Hawthorn
Decision Maker: Interim Director Commercial & Operations
Decision published: 03/08/2017
Effective from: 21/06/2017
Decision:
That the Interim Director - Commercial and
Operations:
1) grants final approval to the event promoters, to hire Finsbury
Park to hold a one-day concert on 1 July 2017 and the Wireless
festival on 7, 8 & 9 July
2017, subject to the signing of the Council’s commercial park
hire
contract.
2) notes that the final hire fee, as detailed in paragraph 8.1.1 of
the report, is an increase since the Cabinet Member decision made
in Feb. 2017 which authorised conditional in principle approval for
the hire.
Lead officer: Stephen McDonnell
Decision Maker: Interim Director Commercial & Operations
Decision published: 02/08/2017
Effective from: 20/06/2017
Decision:
Contract Variation under 10.02.1(a) to the
Cycle Training Contract to vary the contract by a further
£20,000.
Lead officer: Stephen McDonnell
Decision Maker: Director for Housing and Growth
Decision published: 31/07/2017
Effective from: 20/07/2017
Decision:
For the Director of Housing and Growth to
waive the requirement of CSO 9.01 as permitted under Contract
Standing Order 10.01.02 (d)(ii) and (iii) and award the Home Sweet
Home Contract as permitted under CSO 10.01.1(b) to Metropolitan
with a maximum value of £158,080 with an option to extend the
contract for a period of 12 months.
The term of the contract shall be from 1st August 2017 to 31st July
2018. The total value of the contract including the extension is
£316,160.
Lead officer: Dan Hawthorn
Decision Maker: Assistant Director for Corporate Property and Major Projects
Decision published: 28/07/2017
Effective from: 09/05/2017
Decision:
To approve the implementation of Contract
Standing Order 10.02.1b and vary and in crease the value of the
Contract Sum in line with the anticipated construction Final
Account value
Lead officer: David Moore
Decision Maker: Assistant Director for Corporate Property and Major Projects
Decision published: 28/07/2017
Effective from: 06/06/2017
Decision:
Approval to vary an existing award of contract
by the amount of £4,084.93 under Contract Standing Order
(CSO) 10.02.1(a)
Lead officer: David Moore