That the Assistant Director for Housing
retrospectively approves the additional contract cost and fees as
follows: -
1. A variation of the contract with Engie Regeneration Limited to
increase the value of the contract sum by £220,000.
2. The additional consultants’ fees of £16,610
resulting in a total additional cost of £236,610.
3. That £117,869 of the cost of these works will not be
recharged to the leaseholders of properties at 1-24 Wall Court N4,
included in their scope.
That the Assistant Director for Housing notes the revised total
cost of this project is now £409,238.