Decision Maker: Assistant Director for Housing
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
That the Assistant Director for Housing
retrospectively approves the additional contract cost and fees as
follows: -
1. A variation of the contract with Engie Regeneration Limited to
increase the value of the contract sum by £220,000.
2. The additional consultants’ fees of £16,610
resulting in a total additional cost of £236,610.
3. That £117,869 of the cost of these works will not be
recharged to the leaseholders of properties at 1-24 Wall Court N4,
included in their scope.
That the Assistant Director for Housing notes the revised total
cost of this project is now £409,238.
Approval of the additional works costs
to
carry out essential fire safety works, replacement of vinyl
flooring, external repairs and making good of soffits identified
during the construction phase. These additional works were
identified at 1-24 Wall Court N4.
The option of not doing the work was
considered but rejected, because the landlord, Haringey Council
must comply with current fire and Building Regulations as well as
the Decent Homes Standard. It is also more cost effective to
include the works as part of the existing contract, while on site.
This is less disruptive for residents.
Publication date: 28/07/2020
Date of decision: 28/07/2020
Accompanying Documents: