Decision type: Key
Decision status: For Determination
Notice of proposed decision first published: 09/10/2026
Anticipated restriction: Part exempt - View reasons
Decision due: Between 9 Nov 2026 and 31 Jan 2027 by Cabinet Member Signing
Variation of >£500k to the contract value approved by Cabinet in September 2025. The variation is to install Air Source Heat Pumps and is contained within the Contract contingency which is contained within the approved total scheme cost. Approval is needed to issue a variation under the JCT Contract by the Employer's Agent.
Lead member: Cabinet Member for Housing
Lead director: Corporate Director of Finance and Resources (S151 Officer)
Contact: Corporate Director of Finance and Resources (S151 Officer).