Issue details

To award a contract for the delivery of Energiesprong energy efficiency retrofit

Decision type: Key

Decision status: For Determination

Notice of proposed decision first published: 12/04/2021

Anticipated restriction: Part exempt  - View reasons

Decision due: Between 12 May 2021 and 24 May 2021 by Cabinet Member Signing

In line with recommendation 3.4 set out in the Energiespronge Cabinet paper of the 16th March 2021. To seek approval for the appointment of the successful contractor to undertake Energiesprong energy efficiency retrofits in council-owned housing stock. The procurement process is expected to be completed on 11 May 2021 by the GLA. The Council is then required to confirm this appointment by 14 May 2021.

Lead member: Leader of the Council

Lead director: Assistant Director for Planning, Building Standards and Sustainability

Contact: Director for Housing, Regeneration and Planning.