Issue details
North Hill Retaining Wall Works
Decision type: Key
Decision status: For Determination
Notice of proposed decision first published: 06/09/2019
Anticipated restriction: Part exempt - View reasons
Decision due: 12 Nov 2019 by Cabinet
Agreement to award of Contract for North Hill Retaining Wall scheme following a competitive procurement process. The scheme forms part of the Council's Sustainable Transport Works Plan (STWP) for 2019/20. The scheme is currently at tender stage (estimated value of works around £1 million).
Lead member: Deputy Leader of the Council and Cabinet Member for Neighbourhoods
Lead director: Director of Environment and Resident Experience
Contact: Director of Environment and Resident Experience.
Agenda items
- 12/11/2019 - Cabinet North Hill Retaining Wall Works 12/11/2019