To report on the feedback of statutory consultation carried out from 27 November 2024 to 18 December 2024 on the proposal to introduce cycle hangars at various locations in the borough.

27/03/2025 - To report on the feedback of statutory consultation carried out from 27 November 2024 to 18 December 2024 on the proposal to introduce cycle hangars at various locations in the borough.

Having considered the proposals, the responses to the statutory consultation and officer comments, and having due regard to the needs set out in Section 149 (public sector equality duty) of the Equality Act 2010, approve:

1.1 the implementation of 21 new cycle storage (cycle hangar) facilities at the proposed locations detailed in Table 1 of section 6.
1.2 the total estimated implementation cost of £94k which includes consultation, inventory survey, design, traffic management orders, supply, and installation of the cycle hangars. This is from the £487k approved budget for the implementation of the Cycle Parking Programme for year 2024/2025.