Issue - decisions

To report on the feedback of statutory consultation carried out from 27 November 2024 to 18 December 2024 on the proposal to introduce cycle hangars at various locations in the borough

27/03/2025 - To report on the feedback of statutory consultation carried out from 27 November 2024 to 18 December 2024 on the proposal to introduce cycle hangars at various locations in the borough

Having considered the proposals, the responses to the statutory consultation and officer comments,
• approved to proceed with Implementation of 24 new cycle storage (cycle hangar) facilities at the proposed locations detailed in Table 1 of section 6.
• approved not to proceed with the installations of Bike hangars at the proposed location for Farrer Road N8, 50 Oakfield Road N4,106 The Avenue, 210 Middle Lane, 159 Mount View Road N4 and 52 Winchelsea Road for the reasons set out in section 4.6 of this report.
• approve the total estimated implementation cost of £108,072.00 which includes consultation, inventory survey, design, traffic management orders, supply, and installation of the cycle hangars. This is from the £487k approved budget for the implementation of the Cycle Parking Programme for year 2024/2025