Issue - decisions

To report on the feedback of statutory consultation carried out from 4 Septmber 2024 to 25 September 2024 on the proposal to introduce cycle hangars at various locations in the borough

03/12/2024 - To report on the feedback of statutory consultation carried out from 4 Septmber 2024 to 25 September 2024 on the proposal to introduce cycle hangars at various locations in the borough

Having considered the proposals, the responses to the statutory consultation and officer comments,
• approved to proceed with Implementation of 32 new cycle storage (cycle hangar) facilities at the proposed locations detailed in Table 1 of section 6.
• approved not to proceed with the installations of Bike hangars at the proposed location for 29/31 Alexandra Park Road N10, Ashfield Road, N4, Elsden Road, N17, Ferme Park road N4, Gladwell Road, N8, Grasmere Road N10, Harold Road N8 and 107 Hewitt Road, N8, for the reasons set out in section 4.6 of this report.
• approve the total estimated implementation cost of £154,46.00 which includes consultation, inventory survey, design, traffic management orders, supply, and installation of the cycle hangars. This is from the £487k approved budget for the implementation of the Cycle Parking Programme for year 2024/2025.