The Panel received a report which provided an update on housing voids performance and progress against the Council’s voids improvement programme. The report outlined the findings of the review of voids management undertaken during 2026, the nature of the challenge facing the service, progress made to date and priorities for the remainder of 2026/27. The report was included in the agenda pack at pages 165 to 177. The Corporate Director of Adults, Housing & Health was present for this item, along with; the Director of Housing, the Assistant Director (AD) of Repairs and Compliance, the AD for Asset Management, and the AD for Housing Management. The Cabinet Member for Housing and Co-Deputy Leader was also present for this item. The following arose in discussion of the report:
a. The Panel questioned whether, when someone left a property and gave notice of doing so, the Council undertook an inspection whilst they were still there in order to schedule works as soon as it became vacant. In response, officers advised that the Council did not always get notice of someone ending their tenancy, and that that where they did receive notice, the Council did not necessarily prioritise works according to when they became vacant. Instead, the Council was currently prioritising turning around larger void properties.
b. The Panel sought clarification about who was responsible for the management of voids. In response, the Panel was advised that the end-to-end process for the management of voids and tenancy management sat within Housing Management, who had oversight of the whole void process. The Repairs and Compliance team were responsible for the bit in the middle of the process i.e. scheduling the repair works. Within the Housing Management service, there was a Voids Strategic Coordinator.
c. In response to a follow-up question, officers advised that the Voids Coordinator was familiar with every single void in the pipeline and that they would flag up to senior management when there was a delay, as well as seek resolutions to any delays that occurred. The AD for Repairs and Compliance advised that once his team had received notification from Housing Management that they could enter a particular property, then he was responsible for the time it took to turn those repairs around. This was based on the priorities set by the service, and with a view to the wider voids that needed to be turned around. Officers gave assurances that there was heavy internal scrutiny of voids within the Housing Service. The Heads of Service within the operational teams met every two weeks to review the total number of voids, the number of outstanding voids, priorities and allocation of voids. There was also a weekly dashboard produced on voids to show what was progressing and what was not.
d. The Chair commented that he appreciated the level of focus on voids within the service, but that ultimately the voids numbers were up and had been for a number of years. The Chair sought clarification about where the process of turning around an empty property was breaking down. In response, officers advised that there were a lot of void properties within HRS and that the service had identified that it would never be able to clear the backlog with current resources. A significant number of these voids had, therefore, been batched into a programme of major works to be delivered, and that the service would return to managing the day-to-day turnover of voids. This day-to-day turnover of voids was affected by the development pipeline, for example, as there was a local lettings policy. It was also impacted by regeneration schemes. The AD for Repairs and Compliance advised that he was looking to increase capacity within the team to turnaround empty homes over the next couple of years, in recognition of the fact that the number of voids was increasing. Officers advised that there had been a net reduction of voids of 53 in the current financial year, and that this figure included 330 new voids. It was expected that there would be another 1000 new voids between now and September 2027. Officers set out that they had mapped out what was coming down the pipeline in terms of voids and that they had made a commitment to halve the net number of voids between now and September 2027. The Chair commented that a halving of the net number of voids would still result in the overall number of voids increasing significantly.
e. The Panel queried the extent to which there was a voids strategy in place and questioned why there wasn’t a level of forward planning, with the organisation having a rough idea of which residents might be in a care home in the next 5 years, and an understanding that certain age groups were likely to have children. The Panel sought reassurance that there was a structure in place and that the process was being managed strategically, rather than just reacting to fluctuating numbers of empty homes. In response, officers acknowledged that over the course of a year they would expect a certain number of voids to come up and that there were opportunities for forward planning. It was commented that part of this involved linking it with residents who were in unsuitable homes that didn’t meet their needs and looking at what other options there might be. The Director of Housing agreed to take this away and give some consideration about forward projection and how to look at what demand might be in the future. (Action: Kristian).
f. The Panel commented on Broad Water Farm and the fact that the reason that residents had to be moved was because of the problems with the buildings themselves, with leaks, damp and mould etcetera. Residents being decanted from this site were a result of a failure to rectify repairs over period of months and years, it was questioned therefore, how a repairs person could be expected to turn these properties around in 30 days, given the fact that the repairs issues were the reason that the resident was moved out in the first place. It was suggested that cases where the primary driver was the condition of the property itself should be measured differently. Officers responded with an estimation that around 12% of empty homes were more complex cases and it was acknowledged that these should be a focus for the service. Officers acknowledged that having some kind of target for these seemed appropriate. It was suggested that officers needed to provide assurances to the Panel that there was a plan in place, that it was properly resourced, and that it was being properly tracked within the organisation.
g. The Panel requested that future updates on voids include comparative performance data with neighbouring boroughs in order to allow the Panel to understand what ‘good’ looks like. Officers commented that in terms of what good looked like, in the Regulator of Social Housing’s quarterly return for private registered providers the median void loss position was around 1.5%, which would be around 200 homes for LBH. Officers clarified that void loss was higher for local authorities and that LBH’s void numbers were on the high side for a London local authority.
h. In relation to paragraph f, the Chair commented that what he wanted assurances on was that the process for improving the void numbers was working. It was commented that there seemed to be too many opportunities for human error and for mis-categorisation of issues.
i. The Panel sought clarification about the extent to which the Council would offer compensation to neighbours who had been impacted by living next door to a long-term void property. The Panel commented that a long term void property that needed repairs and had overgrown garden would impact the look and feel of a particular street. In response, officers advised that they did not offer compensation to neighbouring residents as part of a coordinated approach. Residents were free to raise a complaint through the normal complaints procedure and if the Council was found to have acted in a negligent manner then compensation may be awarded.
j. The Panel queried what percentage of voids were delayed because of repairs and what percentage were delayed due to administrative delays. The Panel also queried how many properties had been void for over a year. In response, officers advised that they didn’t have the figures to hand, but that at least half of the properties were delayed due to significant repairs and the other half were put into the HRS rolling programme of fixing up voids. The long term void properties, with complex repair issues were allocated as part of the asset management programme, which was currently being mobilised. Officers clarified that the primary reason for delays to the complex repairs that were part of the asset management programme was because they were part of a long term back-log, which was exacerbated by industrial action taken by repairs staff. Officers set out that delays to turning around a particular property could also be because of a regeneration programme, such as the Love Lane estate.
k. In response to a follow up, officers advised that there were three teams of ten operatives who undertook void repairs. Each team had a target of ten properties a month (30 in total). Further repair work above that would then be allocated to a contractor who could undertake 13 a month. The total capacity within the void repairs team was 43 properties a month. In response to a further follow up question, officers advised that the team’s ability to meet its 10 properties a month fluctuated according to staff absence/sickness levels. Officers advised that performance in meeting 30 properties a month was up and down. In Quarter 1, the team over-achieved the target and under-achieved the following month. Officers advised the Panel that they were looking to expand the external void repair capacity with two longer-term contracts.
l. In response to a question, officers advised that prelims were not an issue with the contractor, as they were paid on a unit rate, so there were no additional costs.
m. In relation to measuring the time taken between a void being handed over to a contractor and completed, officers advised that they measured timescales at all parts of the process. Examples of these timescales were basic compliance checks carried out within 2 weeks and turning around a non-complex void within 28 days. Properties that required major works would take longer, depending on the scale of works required.
n. The Cabinet Member advised that they recently hosted a strategic meeting of all internal partners on voids in order to get a 360 degree view on voids and the underlying issues involved.
o. The Panel commented that there was a link with the residents panel and the spatial implications of voids on the wider community. It was suggested that this should also inform the prioritisation of voids, given the impact of ASB and other issues that could arise from clusters of empty properties. In response, officers acknowledged the need for a strategic approach to the management of spaces and places where there were significant clusters. This had already been done for Love Lane.
p. The Panel requested clarity around whether there was a voids strategy in place. In response officers advised that there was a strategy in place and that they would bring the strategy to a future Housing Scrutiny Panel meeting, when voids was on the agenda. (Action: Philip).
q. The Panel sought clarification about the extent to which there was a programme in place to address under-performance in voids. In response, officers advised that there was a programme in place, which had a number of constituent parts, including a weekly operational group.
r. The Panel suggested that there was wider communications point about needing to involve and engage with wider residents on an estate, even if they were not moving themselves under the Neighbourhood Moves Scheme. So that everybody on an estate knew what the expectations were around how long it would take to turn around the void properties.
s. The Panel agreed to have a follow-up meeting officers outside of the formal panel meetings to discuss voids further and agree how best to scrutinise the issue going forwards. (Action: Philip).
RESOLVED
That the Panel:
I. Noted the current position regarding voids performance;
II. Noted the findings of the review of voids management;
III. Noted improvements made against the Voids Improvement Programme; and
IV. Noted the priorities and next steps for the remainder of 2026/27