Minutes:
The Panel received a report which provided details of the Council’s financial position at Quarter 1 of the 2026/27 financial year including the General Fund (GF) Revenue and Capital, and Housing Revenue Account (HRA). The report was originally published as part of the agenda papers for Cabinet on 15th September 2026. Overview and Scrutiny considered the report at its meeting on 17th September. The Panel was asked to scrutinise the elements of the budget that were relevant to its remit. The report was set out in the agenda pack at pages 11-84. The Corporate Director of Adults, Housing & Health was present for this item, along with; the Director of Housing, the Assistant Director (AD) of Repairs and Compliance, the AD for Asset Management, and the AD for Housing Management. The Cabinet Member for Housing and Co-Deputy Leader was also present for this item. The Head of Finance for Adults, Housing and Health was also present online. The following arose in discussion of the report:
a. The Chair enquired about the impact of the Renter’s Reform Act on the availability of private-sector housing in the borough. The Chair also questioned whether there was appetite in the market to work with the Council going forward. In response, officers advised that there had been a reduction in PSL properties available in the market, as landlords reclaimed their properties ahead of the legislation coming into force. Officers stressed that private sector landlords were one of the most cost effective form of temporary accommodation for the Council. The Panel was advised that the Council was seeking to strengthen its offer to private sector landlords and was also working to secure longer term arrangements with landlords for their properties, in exchange for a higher proportion of upfront payments.
b. The Panel queried the extent to which there were budget pressures arising from delays in the housebuilding programme in respect of Temporary Accommodation. Officers agreed that Housing Delivery would provide a written response. (Action: Taryn Eves).
c. The Panel enquired whether the Council was at risk of losing any GLA funding, given the deadline of September 2026. The Cabinet Member advised that the deadline for the latest tranche of funding was 5th November and that the outcome of this bidding process would be announced in due course. Officers would provide a response in writing. (Action: Taryn Eves).
d. The Panel sought assurances around whether there were additional costs/savings that arose from the Council moving people out of hotels and into other forms of temporary accommodation. In response, officers advised that this saving had been delivered early, and was part of the wider savings proposals put forward in Housing Demand. Officers drew attention to the fact that there was an assumption made in-year that some of those people moved from hotels would require private sector leases. The saving had also led to an increase in nightly paid accommodation.
e. The Panel raised concerns about delays to some works with particular contractors, such as the works at Broad Water Farm. The Panel sought assurances around whether there was a financial impact. In response, officers acknowledged that there were delays in the refurbishment project at BWF as a review of projected work and projected expenditure were carried out, due to the fact that costs were rising above what had been budgeted for.
f. The Panel queried whether there had been any work done to approach private sector landlords who were looking to exit the market and for the Council to buy those properties. In response, officers confirmed that they shared intelligence with the acquisitions team in these situations and that there had been instances were the Council had been able to purchase a property before it had come to the open market.
g. The Panel noted that the HRA deficit was projected at £3.47M and the Panel contended that this figure was largely down to empty properties/voids. The Panel questioned what the council tax costs were from empty properties. *Clerk’s note – Officers have advised in writing that the council tax cost to the HRA is forecast at 2.2m for this year.*
h. The Panel queried what the impact of not making the in-year savings target would be on housing improvements. In response, officers advised that that the General Fund and Housing Revenue Account were both ringfenced and that there would be no impact to the HRA if the Council was unable to make savings in the General Fund. Savings that were not met in the General Fund would ultimately either reduce the amount of money available within the General Fund for services, or increase the amount of money the Council needed to borrow. Officers highlighted that there were instances where the Council acquired properties through the HRA in order to discharge its housing duties. The Cabinet Member set out that a failure to turn around voids meant that the Council was paying significantly more in council tax and that there was also no rent receipt coming in for that property. The Cabinet Member highlighted the fact that there was a Major Works programme of £570m that was ringfenced and that this was in the process of being mobilised.
i. The Panel questioned whether there was a budget constraint on undertaking repairs. In response, officers advised that there were no budget savings proposed around the repairs department and that, if anything, this was an area that the Council was looking to provide additional investment in. The Panel was advised that previously a financial assumption was made that repair costs would have started to decease by this year, but that assumption was being reevaluated.
j. The Panel questioned whether the budget pressures outlined in the report would undermine the Council’s ability to meet the Decent Homes standard. In response, officers advised that there was a 10-year capital investment programme in place to meet Decency and that this was not affected by pressures in the revenue budget.
k. The Panel questioned the extent to which the capital investment was over-budget. Officers advised that the capital budget was not over-budget. Instead, historically, this was some thing that was usually under-budget. In response to a request for clarification, officers advised that they had tested the market for value for money as part of a recent procurement exercise. It was commented that the problem tended to be scope-creep i.e. that there was more work to be done than had originally been thought, rather than the work costing more. The Panel questioned what the reporting mechanism was for ensuring the capital programme was being delivered. In response, officers advised that their internal governance arrangements were that they reported back to Capital Board, including regular updates on planned progress.
l. The Panel queried whether there was a correlation between delays in carrying out repairs and additional costs when carrying out works to schemes. In response, officers confirmed that they undertook stock condition surveys as an initial part of the process, and that this showed the extent of works required for a particular scheme. The Asset Strategy was agreed in 2023 and this sets out the priorities for investment. One of the priorities was around whether a property had a high number of repairs. Officers commented that the main contributing factor to why capital works suffered from scope-creep was the fact that the housing stock had suffered from a lack of investment over a long time.
m. The Panel noted that Cabinet agreed a Major works programme of £570m in February 2026. The Panel commented that under the spend profile for the scheme, it was presented as being £57m spent every year over ten years. The Panel questioned how much money had been spent so far. In response, officers advised that the spending profile was not flat and that they were still in the process of mobilising the contract, with schemes only starting on site in August at the earliest. Officers set out that a significant proportion of the investment would need to be spent by 2028 in order for the Council to meet its decency target. The Panel was advised that less than £10M had been spent so far this year. Officers agreed to circulate a ten-year breakdown of the spend on the Major Works programme, as well as a breakdown of spending by ward. (Action: Christian Carlise).
n. The Panel requested that regular financial updates on the spending for the Major Works programme be included in either future budget monitoring reports, or else as part of future KPI updates. (Action: Philip/Kristian).
o. The Panel requested more information about the financial impact on the acquisitions programme arising from delays in turning around empty properties. In response, officers advised that TA acquisitions sat in two places, in the revenue budget of the General Fund and in the capital budget of the HRA. Officers advised that by the end of Q2 the service was on track to have completed on 82 homes, with a further 100-120 homes to be completed upon by the end of the year. Officers commented that some block acquisitions had slipped from this year to next year, but that the service expected to be on track with its acquisitions.
p. In regard to the rent convergence programme, officers advised that there was a net-benefit to the Council of around £2m, but that the programme had resulted in an increase in subsidy-loss as a result (arsing from the Council only being able to claim 90% of the LHA rate based on 2011 rates). Officers confirmed that the projection for rent convergence was on target.
RESOLVED
That the Panel gave consideration to the contents of the report and, following questions to the Corporate Director of Adults, Housing & Health and the Director of Housing, submitted any recommendations that arose to the Overview & Scrutiny Committee.