Report of the Corporate Director of Culture, Strategy and Communities. To be presented by the Cabinet Member for Placemaking & Local Economy
Decision:
DECLARATIONS OF INTEREST MADE FOR THIS ITEM:
Cllr Beckford noted that they were appointed by the Council to the membership of the North London Waste Authority in May 2026 by virtue of my Cabinet responsibilities. The North London Waste Authority have a working relationship with the Lee Valley Heat Network referred to in the report and recommendations. It was noted that Councillor Beckford was granted dispensation to vote on matters relating to North London Waste Authority by the Standards Committee in June.
Councillor Kuper noted that they were appointed by the Council to the membership of the North London Waste Authority the North London Waste Authority agreed by full Council in July. The North London Waste Authority have a working relationship with the Lee Valley Heat Network .Due to Committee meeting scheduling, the Standards Committee are due to consider a dispensation in relation to my council membership role of North London Waste Association at their November meeting and therefore recused themselves from the meeting at items 15 and 23.
RESOLVED:
That Cabinet:
1.
Approved the award of Heat Connection Agreements, for a term of 40
years, to Lee Valley Heat Network Operating Company Limited
(Company No. 09763702) for: Selby Village (residential); Commercial
Unit Space within the residential development; Commercial
Connection – Selby Centre; and Commercial Connection –
Sports Pavilion. The total contract value was as set out in the
exempt recommendations.
2.
Approved the award of the Selby Urban Village Framework Supply
Agreement, for a term of 40 years, to Lee Valley Heat Network
Operating Company Limited (Company No. 09763702). This committed
the Council to the relevant supply costs contained within the
subsidiary supply agreements over the 40-year contract term,
including those identified within the exempt
recommendations.
3.
Noted that, through the subsidiary Construction Supply Agreement,
the Council would meet the cost of heat supply during the
construction period, including commissioning activities, with these
costs already accounted for within the project's capital
budget.
4.
Noted that, through the subsidiary Residential Customer Supply
Agreements, the Council would contribute the landlord’s
availability charge applied by Energetik for the residential heat network at Selby
Urban Village. The proportion of the total availability charge and
the estimated cost to the Council over the 40-year contract term
were set out in the exempt recommendations.
5.
Noted that, through the subsidiary Residential Customer Supply
Agreements, social housing tenants would contribute the tenant
availability charge applied by Energetik for residential heat supply at Selby
Urban Village. The proportion of the total availability charge was
set out in the exempt recommendations.
6.
Noted that, through the subsidiary Residential Customer Supply
Agreements, social housing tenants would be responsible for their
variable heat usage charges during their tenancy.
7.
Noted that, through the subsidiary Commercial Customer Supply
Agreements, commercial tenants occupying the Community Centre,
Sports Pavilion and Commercial Unit would be responsible for their
availability charges and variable usage charges during their
occupation.
8.
Noted that, through the subsidiary Void Supply Agreements, the
Council would be responsible for the availability and usage charges
for heat supplied to residential and commercial void properties for
a term of 40 years with Lee Valley Heat Network Operating Company
Limited. The estimated cost to the Council over the contract term
was set out in the exempt recommendations.
9. Delegated authority to the Corporate Director of Finance and Resources, following consultation with the Head of Legal and the Lead Member for Placemaking, to finalise the terms of the contracts, ensure that they remained fair and reasonable, agree the final legal documentation and complete execution of the agreements.
Reasons for the Decision
The overall design concept and sustainability objectives for the Selby Urban Village project had previously been approved by Cabinet in September 2023 and subsequently through the Gateway 0 Report - Phase 2, Selby Urban Village in June 2024. The energy strategy was developed in accordance with the energy policies of the London Plan and the policies of both Haringey and Enfield Councils, with the aim of achieving low-carbon development in line with the London Plan energy hierarchy. These policies, together with the project's planning approvals, required connection to a district heat network on fair and reasonable commercial terms, unless such a connection was not possible, practical or viable.
Energetik was identified as the only viable district heat network provider serving the area. As a result, the Council undertook a review of the proposed agreements and entered into direct negotiations with Energetik regarding the connection to the network, the supply of heat to residential and non-residential buildings, and the management and maintenance of residential heat supply systems. This approach was consistent with the direct procurement strategy approved by Cabinet on 7 January 2026.
The Heat Connection Agreement and Framework Supply Agreement were long-term contracts covering different aspects of the district heat network. Together, they established the framework for both operation of the network infrastructure and the supply of heat to customers.
Under Section 11 of the Landlord and Tenant Act 1985, the Council was required to provide and maintain a functioning heating system for secure tenants. The Council therefore needed to implement heat supply arrangements for the 202 new council homes being delivered through the development. It also needed to ensure reliable heating provision for the new Community Centre, Sports Pavilion and Commercial Unit so that these facilities could be occupied and operated as intended. The proposed allocation of residential availability charges between the landlord and social tenants had been reviewed and was considered to accurately reflect the responsibilities established under the Landlord and Tenant Act 1985.
Work had been undertaken to mitigate the risks associated with connecting to the Energetik district heat network and with the proposed contractual arrangements. Further details of these risks and mitigations were contained within the exempt report. Delegated authority was recommended to allow final contract terms to be negotiated and refined, ensuring that the final agreements remained fair and reasonable to the Council before execution.
Alternative Options Considered
Option 1: Do Not Connect to the Energetik District Heat Network
This option was considered but discounted.
Planning policies and planning approvals required the development to connect to the nearest district heat network, namely Energetik, unless fair and reasonable contractual terms could not be secured. To mitigate against the possibility that acceptable terms could not be agreed, the Council explored alternative technical solutions, including the construction of an on-site energy centre using low-carbon heating technologies. However, as the principal contract terms were considered fair and reasonable, subject to final negotiation, this alternative option was not pursued. Further details, including cost implications, were contained within the exempt report.
Option 2: Connect to an Alternative District Heat Network Supplier
This option was considered but rejected.
Although other district heat network operators existed elsewhere in London, the capital costs and practical challenges associated with installing pipework over the distances required to connect the Selby Urban Village development to networks in locations such as Stratford or Brent rendered this option unviable.
Option 3: Procure Heat Supply from Energetik but Manage the Network Separately
This option was considered but rejected.
The Council considered procuring heat supply from Energetik while separately managing and maintaining the residential secondary heat network, either directly or through another provider. Technical advice indicated that this approach would have significant ongoing financial, resource and capacity implications. Procuring both the heat supply and the associated management and maintenance services from Energetik was considered more cost-effective and operationally efficient than establishing separate management arrangements.