The Committee noted a report
summarising resident feedback from the 2025 Summer Series and the
operational improvements implemented for the 2026 Summer Series,
together with key issues arising from the 2026 events.
The following points were
noted:
- Transport and
traffic: Additional security was
deployed to manage taxi pick-ups, and a pilot Uber geo-fencing
scheme was introduced around The Avenue and Dukes Avenue during
event times. One resident complaint was received regarding the
geo-fencing, which was referred to Uber. The approach would be
reviewed for future events.
- The Avenue
parking: Parking suspensions had
been introduced in response to previous resident concerns. Further
discussion with residents and Haringey Council was identified as
necessary to determine whether these should remain, be amended or
removed.
- W3 bus
service: Following feedback from
residents and ward councillors, Alexandra Palace worked with TfL to
introduce a revised diversion route. This ensured that no stops
were entirely unserved during road closures, with only five stops
missed across the eastbound and westbound services, excluding
Alexandra Palace Way.
- Alexandra Palace
Way closures: The Committee noted
that the road closure remained necessary to facilitate event
infrastructure and safe delivery. The team continued to review
whether the duration of the closure could be reduced for future
events.
- Hire
bikes: Alexandra Palace worked with
Lime and other operators to manage the increased number of hire
bikes around the park and remove obstructions where necessary.
Increased usage was particularly noted on the day of the Piccadilly
line closure.
- Plant and
machinery noise: Less intrusive
white-noise warning systems were used where possible, with 9 of the
11 items of plant fitted with the alternative systems.
- West-side
entrance: A second entrance was
introduced on the west side of the site to provide more direct
access and reduce additional footfall along Dukes
Avenue.
- Sound
management: Across the seven events,
recorded sound levels remained below the permitted 75dB limit, with
a maximum of 65dB recorded. A total of 46 noise complaints were
received, of which 26 included addresses and requested monitoring
visits. No breaches of permitted sound levels were identified.
Additional post-event teams were also deployed to address noise and
anti-social behaviour associated with departing crowds, with
positive resident feedback received.
- Piccadilly line
closure: The closure on the final
event day resulted in increased pressure on local transport,
Alexandra Palace Station and hire bike provision. The matter was
raised with TfL, with discussions continuing around advance
notification and mitigation of future closures.
- Policing and
safety: There was only one occasion
when police were called to site during the concert run. A
Metropolitan Police presence was maintained on each event day,
providing a visible and reassuring presence.
- Cleaning: Full post-event
cleaning was undertaken across the event site and key surrounding
routes, including Alexandra Palace Way, Dukes Avenue and The
Avenue. Alexandra Palace continued to offer support to neighbouring
businesses where appropriate.
- Wildflowers: Minimal impact from
event fencing was identified. The wildflower area was scheduled to
be reseeded in a different location for 2027 to avoid future
conflict with event infrastructure.
- Communications: A comprehensive
communications campaign had been undertaken, including 8,000
resident leaflets, signage, stakeholder emails, committee updates
and social media activity. Further communication methods were being
reviewed.
- Safety Advisory
Group: The post-event debrief with
the Safety Advisory Group, attended by representatives from the
Metropolitan Police, LBH Licensing, TfL and LBH Highways, was
reported as wholly positive. No licensing concerns were raised, and
agencies confirmed that they were satisfied with the planning and
delivery of the Summer Series. The main action was for Alexandra
Palace to investigate options for shortening the Alexandra Palace
Way road closure for future events.
Members queried whether the
introduction of the additional west-side entrance had reduced
footfall along Dukes Avenue. It was explained that the entrance had
been introduced in response to resident feedback and provided
visitors approaching from the west with a more direct route into
the event site, although no quantitative data was available to
measure the reduction in footfall. Members also asked about
measures to manage noise and anti-social behaviour as attendees
left the events. It was noted that a post-event team had been
deployed to remind attendees to be considerate of residents,
discourage gatherings outside residential properties, address
vehicle idling and intervene where anti-social behaviour was
identified, with positive feedback received from residents. Members
further queried the impact of the Piccadilly line closure on the
final event day. It was reported that the closure had increased
pressure on local transport, including Alexandra Palace Station and
hire bike usage, but no significant issues were reported. The
matter had been raised with TfL, with discussions continuing to
improve advance notification and mitigation arrangements for future
events.