The Panel received a report which provided an
update in Legal Disrepair cases. The report set out the current
status of legal disrepair claims, as well as the work being
undertaken to meet the strategic objective of reducing open case
levels to a business-as-usual scenario. The report was introduced
by Scott Kay, Assistant Director for Repairs and Compliance, as set
out in the addendum report pack at pages 17-26. Richard Purvis,
Senior Disrepair Manager was present for this item, along with the
Interim Director for Housing and Cllr Sarah Williams, Cabinet
Member for Housing and Planning. The
following arose as part of the discussion of this item:
- The Panel sought clarification
around how long officers anticipated it would be before maintenance
was of a standard that the number of claims would be significantly
reduced. In response, officers stated that the report set out a
trajectory of caseloads at paragraph 4.11. The Panel was advised
that, in essence, the length of time would depend on how much the
Major Works programme was scaled up, as well as the number of
claims that the Council received.
- The Panel queried the extent to
which an increase in the number of damp and mould cases was
anticipated following the introduction of Awaab’s Law. In
response, officers advised that the organisation did see a bit of
spike following the introduction of the legislation, but that the
increase was not as large as it might have been. It was suggested
that the change had been widely publicised in the media in the run
up to it being enacted. Officers set out that they were comfortable
that the Council had adequate resources in place to deal with
claims at the level they are at present. The service was also
working to increase supply chains in order to deal with any future
spike in claims as-and-when that might happen.
- The Panel raised concerns around a
failure to deal with regular repairs and these ending up being
escalated into legal disrepair claims. In response, officers
acknowledged that there had been some issues with the volume of
calls into the call centre and the ability to handle all of those
calls. In response to this, additional routes for reporting repairs
directly through to the repairs team had been established, to sit
alongside the call centre. It was commented that improvements to
customer satisfaction scores had started to happen. The Corporate
Director advised that additional resources had been put into
customer services and that there was ongoing transformation work to
improve digital contact with the Council.
- The Panel queried the report’s
assertion that part of the solution was that sector reform was
needed, in order to prevent the incentive for volume-based
litigation firms. The Chair suggested that the claims were a
problem only if they were legitimate claims. In response, officers
agreed that claims needed to be valid, but cautioned that the legal
standard was very low. The Panel was advised that even in cases
that could be defended through the legal process, the claim still
had to be treated as a disrepair claim - which took up additional
resources to resolve that claim. Officers clarified that the
salient point was that the resolution process under the protocol
was not very cost effective. The legal costs in defending these
claims were high, especially given the low legal standard.
Furthermore, repairs were delayed by the legal process, which often
made the repair more expensive to resolve.
- The Panel welcomed the progress that
had been made overall on the issue of legal disrepair. The Panel advocated that the Council should be
doing all it could to clear the backlog and to pre-empt cases from
going to court in the first place given the costs involved, rather
than challenging claims and effectively seeking to prevent people
from claiming their rightful compensation. The Panel commented that
the Council’s expectation should be that there are zero cases
of legal disrepair.
- The Chair requested that in future,
graphs in reports show the figures on the axes rather than just the
trend. (Action: Officers to note).
RESOLVED
Noted.