Valerie Okeiyi, Principal Planning
Officer, introduced the report for pre-application proposals
for Phase 5 - Reserved Matters seeking approval of appearance,
landscaping, layout, scale and access in relation to
Buildings F01, G01, G02, J01 and J02. Use of Sustainabrick building façade facing
material on Phases 4 and 5.
The following was noted in response to
questions from the committee:
- The Sustainabrick system had a design life of 60
years, equivalent to that of a conventional wall. It met all
relevant building regulations. The foundations did not need to be
as large or as deep, resulting in reduced concrete use and improved
sustainability. It was also more cost effective.
- Regarding affordable housing
provision, this had been established within the wider
masterplan several years earlier.
The pre-applicant advised that they had
delivered the level of affordable housing they
were obligated to provide, and in some cases more than required. Recent
economic challenges had not adversely affected the scheme; the
developers had continued to progress the project and had found ways
to withstand current market pressures while still delivering the
affordable housing commitments made years ago. This was considered
a positive outcome.
- In terms of height,
the pre-applicant team stated that at their Kidbrooke
development they were delivering a 22?storey building.The tallest building in Phase
Five would not use Sustainabrick but instead an aluminium system
developed, following review by QRP. They
were also exploring the delivery of
26?storey high buildings in Greenwich.
- On the issue of adhesion, it was
acknowledged by the pre-applicant that there had been
failures in the past. The team had reviewed various slip systems,
including mechanically fixed systems and adhesive?based systems,
the latter of which had historically experienced issues. They had
spent three and a half years undertaking research and development
with Monolith, the manufacturer. The proposed system addressed
potential failure by embedding the slips in a mesh, which
would then be adhered to a waterproof Sto render.
Behind this would sit approximately 20mm
of additional waterproof render, followed by a further
waterproof sheet, insulation of varying thicknesses, and finally
the SFS (structural façade system).
- From a sustainability
perspective Officers advised that brick production
methods significantly influenced embodied carbon. Alternative
drying methods could reduce this impact, and using only part of a
conventional brick also lowered embodied carbon. Reducing
façade weight further decreased the embodied
carbon required for the superstructure. These principles
were supported in general.
- However, questions
remained regarding the sourcing of raw materials,
including transport distances, which formed part of the broader
sustainability assessment. Mortar use was also raised as an issue:
traditional lime mortars allowed bricks to be dismantled and
reused, whereas conventional cement mortars did not. It
was noted that the proposed system did not appear to allow for
deconstruction in this way.
- The pre-applicant reported
having four projects across their portfolio at various stages of
Gateway 2 approval. The scheme closest to receiving consent, which
also proposed this product, was at Royal Arsenal Riverside. The
regulator’s concerns had not related specifically to the
product but to structural engineering matters. Determination times
were inconsistent, and no applications had yet been processed
within the statutory 12?week period.
- QRP responses, and the
applicant’s response to their comments, would be
included within the committee report on the Phase 5
application, once ready for consideration by PSC
Members.
- The pre-applicant advised that
exploring alternative construction systems
helped maintain the overall viability of the scheme. This
avoided the need to reduce build quality or affordable housing
provision. Although the system was not substantially
cheaper than conventional brickwork, it contributed to making
the wider scheme financially deliverable. Pricing would still need
to reflect market conditions, but the priority remained delivering
the committed levels of affordable housing.
-
The pre-applicant stated that the 60?year
design life referred to the specification of individual building
components, rather than the lifespan of the building itself.
While components were rated for 60 years in line with manufacturer
and warranty requirements, the building was expected to
last significantly longer—potentially hundreds of
years.