Cllr
Connor chaired the Committee for this item as it related to the
proposals for the Budget 2026/27 and MTFS (Medium-Term Financial
Strategy) for 2026/27 to 2030/31.
Cllr
Connor explained that the purpose of this item was to receive an
update on the progress of savings under the remit of the Overview
& Scrutiny Committee which had been approved in previous years
but were being implemented during the forthcoming MTFS period. She
commented that, because these were often multi-year savings and
that the table showed only the current MTFS years from 2026/27 to
2030/31, it would be helpful in future for the table to include
information about any part of the savings which had already been
achieved in the years prior to the MTFS period. Taryn Eves said
that a 2025/26 column could be inserted into the table.
(ACTION) Taryn
Eves commented that this was not new information and, because these
savings had previously been agreed, they had been shown as a single
line in the recent Budget papers and
this additional table provided a more detailed breakdown of that
line.
The
Committee then raised questions about specific items in the
table:
- Asked
by Cllr Connor about the reduction in Housing Benefit costs
(Corporate & Customer Services), Taryn Eves explained that
£3.5m had been added to the budget for this in 2025/26 and
the aim was to reverse this growth by £1m in 2026/27 and then
a further £2m in 2028/29. This was why it was classified as
an ‘Other Adjustment’ as opposed to a new saving.
However, the £1m reversal for 2026/27 could now no longer be
achieved and so this had been reintroduced as a budget pressure in
the 2026/27 budget proposals. The proposed saving of £2m in
2028/29 would need to be kept under review with three further
budget rounds to take place before this point. Cllr Carlin
reiterated that it had previously been expected that the Council
would no longer be administering Housing Benefit due to the
transition over to Universal Credit. However, it had since become
apparent that some groups, such as those in supported exempt
accommodation, were remaining on Housing Benefit with some
complicated cases still being administered by the
Council.
- Asked
by Cllr Connor about the reduced cost of internal audit contracts,
Taryn Eves explained that the current contact with Mazars was due
to end in February and it was forecast that a small saving could be
made by competitively re-tendering.
- Cllr
Connor referred to the Asset Management savings/income growth
(Capital Projects & Property) of £450k in 2026/27 and
£300k in 2027/28. She compared these to the £350k
savings/income growth for asset management in 2025/26 set out in
Appendix 4 of the Q2 Finance Update report (page 75 of the main
agenda pack). After some clarification of the figures, it was
understood that marginally higher improvements were anticipated in
2026/27 compared to 2025/26.
- Asked
by Cllr Connor about the agreed savings on Digital Transformation
(Digital & Change), Taryn Eves clarified that previous budget
report had forecast savings of £2.8m in 2025/26, £2m
2026/27 and £2m in 2027/28. It had since been necessary to
re-profile this forecast as the savings would now take longer. The
two £2m sections were moved back by one year with no savings
proposed for 2026/27 in order to allow
more time for the first £2.8m section to be
achieved.
- Following on the above question, Cllr Small observed that it
appeared to be the commercial and income generation parts of
savings that sometimes lagged behind.
Cllr Carlin said that she shared this frustration and that, if
there was an area that could deliver an income, the Council needed
to finance this properly, for example in digital transformation
which had taken some years to get to the current stage. She added
that it was recognised corporately that the reliance on EFS was not
sustainable and that cross-cutting savings and income generation
from assets were necessary elements of stabilising Council services
but that resources were required to achieve this. In relation to
the digital transformation, Taryn Eves added that the team only
went live in February/March 2025 with over 40 projects now underway
and this work was now delivering results, although the forecasts
for 2025/26 had been too optimistic. Cllr Carlin commented that, as
the cost of procuring digital products for public services was so
high, the benefits of delivering these bespoke programmes in-house
with permanent staff was a strong position with which to achieve
transformation.
- Asked
by Cllr Connor about the total figures for management actions and
budget changes at the bottom of the table, Taryn Eves said that
this was based on the position in July with further management
actions and pressures added through the new budget report that had
recently been seen by the Committee.