Report of the Corporate Director of Culture, Strategy and Communities. To be presented by the Cabinet Member for Placemaking & Local Economy
Decision:
DECLARATIONS OF INTEREST FOR ITEM:
None
RESOLVED:
That Cabinet:
1.
Pursuant to contract standing order (CSO) 2.01.C, approved the appointment of the
contractor outlined in the exempt report to undertake phase two of the new build
programme to provide a total of 139 Council rented homes and
retail/workspaces units at Ground Floor (to shell and core) for
a total contract sum as set out in the exempt report.
2.
Approved the appropriation of the land edged blue on the plan at
Appendix 1 and the land edged blue on the plan at Appendix 2 from
housing purposes to planning purposes under Section 122 of the
Local Government Act 1972 as it is no longer required for the
purpose which it is currently held, and for the purpose of carrying
out the second phase works and the demolition works for phases
three and four as approved by planning permission reference
HGY/2022/0823 and detailed further in this report.
3.
Approved the use of the Council’s powers under Section 203 of
the Housing and Planning Act 2016 to override easements and other
third-party rights and interests relating to the land edged blue at
Appendix 1 and the land edged blue at Appendix 2 for works approved
under planning permission reference HGY/2022/0823.
4.
Delegated to the Corporate Director of Culture, Strategy and
Communities, in consultation with the Corporate Director of Finance
and Resources, authority to make payments of compensation as a
result of any valid claims of third-party rights affected by the
second phase works and the demolition works for phases three and
four of the Broadwater Farm new homes programme and payable as a
result of recommendation 3.3, within the existing scheme of
delegation.
5.
Approved the appropriation of the land edged blue on the plan at
Appendix 1 from planning purposes back to housing purposes under
Section 122 of the Local Government Act 1972, on completion of the
second phase of works.
6.
Considered the results of the engagement and consultation carried
out in respect of the second phase works set out in 6.37-6.43 of
the report.
7. Pursuant to contract standing order (CSO) 2.01.C, approved the appointment of the contractor to undertake demolition works to the Northolt and Stapleford wing blocks as part of the enabling works for future phases of the new build programme (phases 3 and 4).
Reasons for decision
The Council was currently committed to an ambitious programme of estate renewal on the Broadwater Farm estate. Through the programme the council has committed to delivering almost 300 new build homes and the retrofit of existing council homes. This work was supported by extensive engagement and community development. In March 2022, residents overwhelmingly supported the Council’s proposals through a resident ballot. Through these decisions the Council would be delivering on the commitments made to residents through that ballot.
The red lined scheme agreed through the ballot received planning permission in December 2022 and since then the Council has progressed delivery of the scheme.
The new build programme had been divided into four phases for delivery purposes. Phase one (the old Moselle school site) is onsite currently and was approved by Cabinet in October 2024. Phase two is the former Tangmere site and is a subject of this report. Phases three and four are the former Northolt and Stapleford North wing block sites. The demolition of the blocks to facilitate phases 3 and 4 is a subject of this report.
Alternative options considered
The Council could have adopted a different procurement strategy for works on the estate including procuring all new homes works in one package. The Council did initially take this approach for the new homes programme, but it was unsuccessful and the procurement was abandoned.
The Council could have decided not to progress with the regeneration programme. This would have been contrary to existing cabinet decisions following the outcome of the ballot in 2022.
The Council could have combined the new build works and demolition works into one procurement exercise. This option was discounted as the demolition of large panel system buildings is specialist work and the Council needed assurance that contractor was competent to complete the works set out. The new build contractor would have sub-contracted this work which would have added cost to the overall programme.
Supporting documents: