The Panel received report which provided a Q1
Finance update for 2025/26. The report covered the position at
Quarter 1 of the 2025/26 financial year including General Fund
Revenue, Capital, Housing Revenue Account and Dedicated Schools
Grant budgets. The forecast total revenue outturn variance for the
General Fund was £34.1m comprising £24.9m base budget
pressures and £9.2m non delivery of savings. The report was
introduced by Kaycee Ikegwu, Head of Finance and Jahedur Rahman,
Director of Housing as set out in the agenda pack at pages 43-186.
The following arose as part of the discussion of this report:
- The Panel noted the projected
overspend of £11.4m in Housing Demand and the fact that this
was related to Temporary Accommodation and the rising costs of
Nightly Paid & B&B accommodation.
- The Panel questioned the fact that
there was a significant overspend, given the amount of scrutinising
of the budget that took place last year. The Panel queried the
extent to which there were contingencies built into the budgets. In
response, officers advised that within the HRA there was a reserve
balance, which was effectively a contingency. The guidelines
suggested that this should be equivalent to 10% of annual rental
income. Officers set out that Haringey’s reserve balance was
set at a higher level than was set out in the guidelines, and that
there was a significant contingency in place.
- The Panel sought clarification
around the reasons behind the slippage in the capital programme. In
response, officers advised that 55% of the allocated capital spend
was spent last year. There were two key areas where there were
slippages. The first was delays to work in two major blocks, which
were awaiting approval from the Building Safety Regulator. The
second area of slippage related to phase 2 works coming in at an
increased cost. This required external assurance around the
additional cost, which caused delays.
- The Panel queried whether there was
some learning to be taken forward about factoring in delays arising
from legislative changes of from the creation of a new regulatory
framework. In response, officers commented that it was difficult as
it depended on the body or regulator in question. The delays in
this instance were caused by a lack of qualified surveyors to carry
out the works. The Cabinet Member commented that it seemed as
though there had been no workforce plan put in place by the
government to accompany the legislative changes.
- The Panel queried the personal
financial limit that would make someone ineligible for social
housing. The Panel also raised concerns about checks on ownership
of foreign homes not being adequately undertaken and queried what
checks were done in relation to owning a home overseas. In
response, officers agreed to come back with a written response.
(Action: Jahed).
- The Panel queried the relationship
between the projected £34.1m overspend and the £37m EFS
loan that was secured from the government. The Panel requested
clarification about where the £37m loan was reflected in the
overall budget position. (Action: Corporate Finance).
- The Panel raised concerns about the
fact that the report highlighted that the £37m exceptional
financial support may not be enough to cover the budget gap at year
end, particularly given assurances that were provided previously on
this. The Panel queried to what extent the some of the additional
revenue budget pressures could be attributed to a delays in
implementing the capital programme. The Panel also questioned how
the projected overspend was so large at an early stage in the
financial year. In response, officers commented that the Section
151 Officer was best placed to respond to questions about the size
of overall projected overspend and the financial assumptions that
were made as part of the overall budget. Officers commented that
borrowing was seen as the last resort and that other sources of
revenue would always be utilised first. Officers also stated that
the position was a forecast and the £37m EFS had not been
spent at this point. Assurances were given that the overall
position was expected to improve by Quarter 2.
- The Chair commented that the overall
budget position was a matter for the Overview & Scrutiny
Committee and he directed members to focus their questions on the
bits of the budget pertaining to housing.
- In relation to the concerns raised
about a failure to build new homes having an impact on temporary
accommodation spend in the General Fund, the Cabinet Member
clarified that the underspends in the capital programme related to
refurbishment works, rather than TA.
- The Panel sought clarification about
the fact that the report identified that the monthly costs of TA
were up 83% year on year, but that the total number of people in
Nightly Paid Accommodation (NPA) was down. In response, officers
clarified that there had been a reduction in private sector lease
accommodation and that this had led to a knock on increase in NPA.
The Director of Housing advised that the service had been targeting
B&B accommodation with the aim of consolidating some of the
provision and getting a reduced rate. It was commented that the
service was also looking to do this with NPA in order to achieve
in-year savings. In the longer term, it was commented, the Council
was looking to acquire 250 properties to reduce the reliance on
B&B and NPA accommodation, which were the most expensive forms
of TA.
- Officers confirmed that the numbers
of NPA had increased from 1850 to 2150. Officers confirmed that the
units would be used, rather than them being available if the
Council needed them. The cost of NPAs had increased by 18% since
the budget was agreed, the underlying cost assumption in the budget
was that costs would increase by 10%. The overall numbers in
B&B had reduced. Officers provided assurances that detailed
financial modelling was undertaken and that this led to an increase
in the corporate contingency within the budget. External assurance
had been carried out on the modelling and the assessment of the
modelling used was overwhelmingly positive. In addition, the
service was reviewing its future forecasting on a monthly basis
going forward.
- The Chair sought clarification about
the acknowledgement in the report around a key future risk relating
to the legal disrepair budget of £2.7m. In response, officers
advised that there had been a 20% reduction in new cases coming
through. The commentary in the report reflected new legislation
that was coming through and the associated risk that this could
lead to a wave of new disrepair claims against the
Council.
RESOLVED
That the report was noted.