The Panel received a presentation which
provided an update on the Housing Improvement Programme which
included; the voluntary undertaking to the Regulator of Social
Housing, safety and compliance, Decent Homes, and damp and mould.
The presentation was introduced by Jahedur Rahman, Director of
Housing as set out at pages 247-279 of the agenda pack. Christian
Carlise, AD Asset Management and Scott Kay, AD Repairs and
Compliance were also present for this item, along with Cllr Sarah
Williams, Cabinet Member for Housing and Planning. The following
arose in discussion of this item:
- As part of the voluntary undertaking
to the Regulator of Social Housing, the Council undertook a
commitment to improve in ten key areas. The Director of Housing
advised the Panel that the Council had met those ten commitments
and the next step was for this to be validated by external
auditors.
- The Panel sought clarification about
the extent to which the service was affected by delays within the
courts, in relation to getting a Court Order to access a property.
In response, officers advised that it varied from month to month.
There was no permanent backlog, but some months there were more
cases that the service would like to put through than the courts
were willing to accept.
- In response to a question about
whether going through the courts was expensive, officers advised
that it depended on the type of order that was being sought. This
varied from a few hundred pounds for an EPA warrant to very
expensive for an injunction. Officers also commented that for gas
safety certificates and electrical safety certificates, they
undertook warrant applications were possible as this was quicker
and more cost effective. A trial of electrical warrants had
resulted in 40 warrants, which resulted in 19 being enforced to
date.
- The Panel queried the table of FRA
Overdue Actions and questioned what the Pennington’s figure
related to. In response, officers advised that Pennington’s
were an external company that the Council brought in to conduct a
review of it’s housing stock, following the ALMO being
brought back in-house. Following that review, the Council
self-referred itself to the Regulator of Social Housing in January
2023. The table showed the number of fire safety actions that were
outstanding at the point of Pennington’s completing an
internal review, the point that the Council referred itself to the
Regulator and the current position as of 2nd
September.
- The Panel was advised that the
achievement of 100% homes being brought up to the Decent Homes
Standard was part of a five-year plan and the profile of the number
of homes being brought up to decency each year was agreed with the
regulator. In year one, the target was for 1000 homes to be made
decent and the Council achieved 1600. In year two, 719 homes were
made decent against a target of 700. The current position was that
80.65% of council homes were at the decency standard. Since the
ALMO came in-house the non-decency position had gone from 31.83% to
19.35%. The Council was working toward 100% decency by the end of
2027/28.
- The Chair queried the fact that the
profile of the delivery of 100% Decent Homes was backloaded over
the period and sought assurances that the Council would be able to
meet the ramping up of decency works that was required. In
response, officers acknowledged that the profiling of work was
backloaded and that this was based on a recognition that the
Council did not have an adequate long-term supply chain in place to
deliver the works. Officers provided assurances that they expected
that the target of 100% would be met by the end of 2027/28.
Officers advised that a lot of the focus over the next three years
would be around external works and that the Council was well on the
way with internal Decent Homes work.
- In response to a follow up, officers
advised that as part of the Asset Management Strategy agreed by
Cabinet in December 2023, the Council set out its investment
priorities within the HRA within three key areas; building safety;
fire safety and decency. Officers gave assurances that the Council
would ensure that the HRA had enough funding to fund these three
areas, and that they would be prioritised above other areas of
investment.
- The Panel queried whether the
service understood the profile of the Decent Homes work that was
left to do in terms of geographic location and clustering. In
response, officers advised that they had a profile of the works
which derived from the stock condition surveys that provided
information on the condition each property and the works would be
formulated on that basis. In order to achieve VfM, the service
would also look at what other works could be done whilst the
scaffolding was up on a particular block.
- The Chair queried the extent to
which it was possible to be certain that all decency works could be
carried out on time, given damp and mould and the fact that to some
extent the extent of damp and mould was unknown. In response,
officers advised that they had achieved 75% access to internal
properties and 90% access to communal areas as part of the first
programme and so they knew the condition of the vast majority of
properties. In terms of the 25% that they were unable to access,
these would be prioritised again this year as part of the rolling
inspection of 20% of properties every year.
- In response to a query, officers
commented that they had a stronger delivery partner in place
through the presence of the partnering contractors. The Council
would be working with four Tier one contractors across the borough
to deliver the planned investment works. It was commented that it
took nearly two years to get the contract in place and that once it
was in place, the capacity existed to ramp up decency works in the
later part of the five-year timescale.
- The Panel queried whether the
contractors were in place. In response, officers advised that the
Council was in the process of awarding contracts and mobilising
works. It was expected that the works would begin in February/March
2026. The Council had two contracts in place on an interim basis to
carry out works whilst the new contracts were mobilised. The Chair
noted that monitoring the performance of these contracts may be
something that the Panel wanted to look into as part of the 2026/27
work programme.
- The Chair sought further information
about the dedicated team in place for damp and mould cases and the
extent to which an increase in demand had been modelled following
the introduction of Awaab’s Law as part of the Social Housing
(regulation) Act 2023. In response, officers advised that the team
had dedicated damp and mould surveyors in place who were able to
respond within the required timescales. There were also dedicated
contractors in place who had the capacity to take on additional
work if needed. The service could also draw on other areas of the
business to meet additional demand. Officers acknowledged that
demand could increase as Awaab’s Law became more well known.
Assurances were provided to the Panel that there was sufficient
capacity within the current team at present to meet expected
demand.
- The Panel sought clarification on
anecdotal accounts that the Regulator of Social Housing based their
judgement on statistical evidence rather talking to residents. In
response, officers advised that it would likely vary according to
the inspection team. Officers advised that they would interview a
number of senior figures within the organisation, attend meetings
of the HIP Board, likely attend scrutiny panel meetings, attend
resident engagement meetings and possibly do estate walkabouts. The
Director of Housing advised that the service carried out a mock
inspection last year to look at how the organisation would meet the
new regulatory standards. Following that mock inspection, 48
actions were put forward, and the Council had been working on
implementing these actions over the last 7 months.
- The Panel noted that the timelines
for delivery were set out in the report as five days to start
relevant safety work following an initial investigation and that
works had to start within 12 weeks.
Officers commented that there were prioritising working through a
backlog of 300 existing cases before Awaab’s law came into
effect in mid-October. It was hoped that being able to reduce this
backlog would allow the service to meet demand and the above
timeframes. The Director of Housing commented that ultimately the
service would have to see what the demand was like at the time of
implementation.
- The Chair cautioned that, similar to
a spike in legal disrepair cases, the service would likely see
another spike following implementation of Awaab’s Law.
- The Panel sought assurances about
what the impact might be on other service areas from prioritising
damp and mould and whether the Council might need to de-prioritise
fire safety assessments for example. In response, officers advised
that there would be no de-prioritisation of other areas of repair
and that damp and mould was being prioritised on top of maintaining
all of the other business areas.
- The Chair commented that in
capturing the risks of non-compliance with Awaab’s Law, it
was also important to recognise that the biggest risk was to the
health of Council residents.
- The Chair queried what the damp and
mould vulnerability data was. In response, officers advised that
the Housing service was working with Children’s social care
and Adults social care so that when colleagues in those services
visited vulnerable people in their homes, they could make referrals
to housing around damp and mould. There was a concern that some
people with vulnerabilities might not be reporting it themselves.
The Director of Housing also advised that the service was triaging
the information from Adults and Children’s with its own
housing data, to get a more holistic data set. It was also noted
that there were a series of questions asked by staff when someone
called to report damp and mould and the answers to these questions
were used for internal analysis of the risks to those living there
and the severity of the case.
- The Panel enquired about the extent
which external contractors were used for damp and mould works and
what was being done to build up the in-house capacity through the
DLO. In response, officers advised that the internal Director
Labour Organisation was made up of 120 trades operatives and that
they carried about 70% of repairs, whilst the other 30% was
contracted out. Officers set out that the intention was to continue
to grow the DLO and to bring in new apprentices each year. A new
Training Manager had just been recruited who would be responsible
for bringing through the operatives through their
apprenticeships.
- In response to a question, officers
confirmed that other contractors across the Council had the ability
to report damp and mould cases and that they were encouraged to do
so.
RESOLVED
Noted.