Proposal: Demolition of existing buildings and redevelopment to provide a new care home and rehabilitation clinic (Class C2 - Residential Institution) fronting View Road and including up to 50 beds, hydro pool, salon, foyer/central hub, gym/physio room, lounge and dining rooms and consulting rooms, together with a new residential building (Class C3 - Dwelling Houses) fronting North Hill providing 9 flats (5 x1 bed, 3 x 2 bed and 1 x 3 bed), car and cycle parking, refuse/recycling storage, mechanical and electrical plant, hard and soft landscaping, perimeter treatment and associated works.
Minutes:
Valerie Okeiyi, Principal Planning Officer introduced the item fordemolition of existing buildings and redevelopment to provide a new care home and rehabilitation clinic (Class C2 - Residential Institution) fronting View Road and including up to 50 beds, hydro pool, salon, foyer/central hub, gym/physio room, lounge and dining rooms and consulting rooms, together with a new residential building (Class C3 - Dwelling Houses) fronting North Hill providing 9 flats (5 x1 bed, 3 x 2 bed and 1 x 3 bed), car
and cycle parking, refuse/recycling storage, mechanical and electrical plant,
hard and soft landscaping, perimeter treatment and associated works.
The following was noted in response to questions from the committee:
The Chair asked Catherine Smyth, Head of Development Management and Enforcement Planning to sum up the recommendations as set out in the report. The Chair moved that the recommendation be approved following a unanimous decision.
RESOLVED
That the Committee resolve to GRANT planning permission and that the Head
of Development Management is authorised to issue the planning
permission and impose conditions and informatives subject to the signing of a
section 106 Legal Agreement providing for the obligation set out in the Heads
of Terms below.
2.2 That delegated authority be granted to the Head of Development Management
and Planning Enforcement or the Director of Planning & Building Standards is
authorised to make any alterations, additions or deletions to the recommended
heads of terms and/or recommended conditions as set out in this report and to
further delegate this power provided this authority shall be exercised in
consultation with the Chair (or in their absence the Vice-Chair) of the SubCommittee.
2.3 That the section 106 legal agreement referred to in resolution (2.1) above is to
be completed no later than 30 April 2025 or within such extended time as the
Head of Development Management or the Director Planning & Building
Standards shall in her/his sole discretion allow; and
2.4 That, following completion of the agreement(s) referred to in resolution (2.1)
within the time period provided for in resolution (2.3) above, planning
permission be granted in accordance with the Planning Application subject to
the attachment of the conditions.
Conditions
1. Three years
2. Drawings
3. Detailed Drawings and External Materials
4. Boundary treatment
5. Hard and Soft Landscaping
6. External Lighting
7. Site levels
8. Secure by Design Accreditation
9. Secure by Design Certification
10. Secure by Design Accreditation at the final fitting stage
11. Contaminated Land
12. Unexpected Contamination
13. Non-Road Mobile Machinery (NRMM)
14. Air Quality and Dust Management Plan (AQDMP)
15. Considerate Constructors Scheme
16. Energy Statement
17. BREEAM
18. Living roofs
19. Whole Life Cycle Carbon Emission
20. Biodiversity Net Gain Plan
21. Urban Greening Factor
22. Overheating Report
23. Arboricultural Impact Assessment
24. Demolition and Construction Management Plan
25. Cycle parking
26. Delivery and Servicing Plan (DSP)
27. Active and Passive EV Charging
28. Wheelchair accessible car parking
29. Car Parking Management Plan
30. Satellite dish/television antenna
31. Extract flues/fans
32. Care Home – C2 Use restriction
33. Telecommunications infrastructure
34. Fire safety
35. Noise from Plant/Equipment
36. Legacy of Mary Feilding
37. Air Quality Neutral