Minutes:
This report sought approval by the Cabinet Member for Placemaking and the Local Economy for a contract variation under Contract Standing Order (CSO) 10.02.1 (B), to increase the contract value. CSO 10.02.1 (B) states that subject to provisions of CSO 3.01 and the Regulation 72 of Public Contracts, compliance with Financial Regulations and subject to satisfactory outcomes of contract monitoring, Cabinet may authorise a variation to a contract.
As noted, in 2017 the Council entered into a DA and CPOIA with Lendlease to deliver the Scheme. The DA sets out the agreed commitment to deliver the regeneration of the Love Lane Estate and surrounding land to deliver the following:
Over 2,600 high-quality, sustainable homes, including at least 546 council owned social rent homes.
Over 130,000sqft of commercial, retail and leisure space throughout the Scheme
Funding for social and economic support for businesses and residents
A new Library and Learning Centre and a refurbished Grange Community Hub
Public Realm investment including a civic square, c.143,000sqft of green space, a large new community park with an outdoor gym, children’s play area and new gardens.
The CPOIA sets out both the Council and Lendlease’s obligations to acquire and
secure vacant possession of the land within the Scheme, including considering
the use of CPO powers.
RESOLVED
The Cabinet Member for Placemaking and the Local Economy was recommended to approve the variation of the contract with Pinsent Masons LLP, to increase the value of the contract by the amount set out in the exempt report, pursuant to CSO 10.02.1 (B), for the reasons set out in the body of this report.
Reasons for decision
The Council required the support of a strong and highly regarded legal practice
for the Scheme, to provide legal advice and support across a range of legal
issues, including land assembly, CPO and management of funding agreements
and the DA in place between the Council and Lendlease.
In March 2022, following a competitive procurement exercise, the Council awarded a contract to Pinsent Masons as the Most Economically Advantageous Tender for the legal advisor contract to support the Scheme and was appointed on a four-year contract. Since being appointed, Pinsent Masons has provided valuable support to the Council in key workstreams across the range of legal issues mentioned above and delivered on their brief to a high standard.
Although there were two years remaining on the contract, the contract spend was
projected to reach the current limit within the next six months. This was a result of
the Council requiring a significantly greater level of legal service provision over
the course of the contract to date, particularly in relation to the land assembly and
CPO workstreams. In this period, the Council had made a CPO to enable delivery
of Phase A, which was confirmed on behalf of the Secretary of State for Levelling
Up, Housing and Communities in February 2024. In addition, the Council and
Lendlease have been working towards satisfying the phase conditions within the
DA for the first sub-phase, Phase 1A.
It was therefore recommended that the current contract be varied to accommodate further expenditure on legal services. This will include ongoing advice related to
land assembly and the DA, to prepare for the delivery of the next sub-phases of
the Scheme following Phase 1A. There was clear justification for continuing the
service provision by Pinsent Masons, based on their performance under the
contract to date and strong knowledge of the Scheme, and given that there were
two years remaining on the contract.
It was anticipated that this increase in the contract value would allow for approximately twelve months of additional work beyond the current allowance. This would provide the Council with consistency of service up to this date, and additional time to reprocure a new service provider on a longer-term contract.
A significant majority of the costs of the legal contract, specifically all the costs relating to land assembly and CPO, would be reimbursable by Lendlease on a phased basis over the duration of the Scheme through the provisions within the CPOIA. The Council would grant leases to Lendlease for individual phases once conditions within the DA are met, and the costs that the Council had incurred in assembling the land interests for each phase, including the costs of legal advice, would be reimbursed to the Council. While a small portion of the costs of the legal contract will not be reimbursable, that being costs for advice on the DA, CPOIA and GLA funding agreements, it was important that the Council had access to the appropriate expert legal advice for these matters, to ensure that it delivered on its legal obligations and that it maintains a robust position in any discussions related to these agreements.
Alternative options considered
To carry out the work in house:
As spend on this contract reaches capacity, the Council may consider reverting
to these services to an inhouse resource. Currently, however there was insufficient
capacity to carry out the scope of this legal advisor function in house. This
variation allowed the Council to benefit from Pinsent Masons skills, knowledge and
resources, as well strong previous track record on the Scheme that will support
the Council progressing into the next stage of the programme
Not to vary this contract and procure a new provider:
Not to vary this contract would result in the loss of technical expertise to support
the Scheme for a period of time until the new legal advisor services were procured
and onboarded. This would represent a substantial risk to the delivery of the
scheme, including financial, legal and programme risks. By varying the value of
this contract, the Council would benefit from consistent service delivery for a further
period of around twelve months and provide additional time to reprocure a new
service provider on a longer-term contract when the spend limit was reached.