The Committee was presented with a table outlining
the Outstanding Requests for Information on the MTFS/ Budget
Scrutiny Proposals.
The following was noted in discussion around the
Overview & Scrutiny Committee (Corporate, CS&E and
E&RE):
- In response
to a question from the Committee in relation to the budget position
regarding Community Safety, Waste & Enforcement, Officers
advised that the underspend predominantly related to an underspend
in maintenance and there was a small element of the underspend in
staffing.
- The Committee
sought assurances around possible impact on services by the
underspend in CCTV. The Committee was advised that the service was
prioritising the use of CCTV in areas that most require it. The
suspension in the maintenance programme would have minimal impact
as the current coverage in CCTV would be enhanced to cover a wider
area.
- In relation
to the response provided for the Outturn Position & 2024/25
Budget Position regarding Culture, Strategy & Engagement, The
Committee recommended that colleagues in Strategic Procurement,
Finance and Digital services should meet with members to provide a
more informed briefing as to how contracts were managed across the
Council; of which digital services have approximately 300
contracts. This should be discussed during an Overview &
Scrutiny meeting.
- In regard to
the Management Actions (page 56 of agenda pack) table 7.2c, the
Committee noted that under Environment & Resident Experience
for 2025/26, there was an overspend of £35k predicted.
Officers advised that it was not unusual to see minus figures in
tables as sometimes you would see a financial benefit that were
greater in year one than in year two and thus would not necessarily
constitute as an overspend. However, in relation to the overspend
of £35k, this was not substantiated and the Committee
recommended that this would need to be clarified when presented to
the Cabinet. The Committee also suggested that if this could not be
substantiated, this line in the report must be removed from the
pack.
- The Committee
sought assurances around the events income increases. The Committee
had requested further details on how these savings would be
achieved and clarification on the reasons for the variation in the
savings target in each of the years over the MTFS period, and
whether these targets were realistic and achievable. The response
on the table stated that the figure of £124k shown in column
N does not appear to be correct and the Committee queried why this
was continuing on the tracker and the Cabinet papers. Officers
advised that they would be reviewing this to confirm if the figure
of £124k was correct and if not, then this would need to be
removed from the papers.
- The Committee
noted that there was a growth of £946k for the delivery of
the Leisure Management Service in-house and in response to a follow
up question, Officers advised that the decision to insource two and
a half leisure centres meant that the Council was able to join up
the provision into a wellbeing strategy to improve the health of
the residents in Haringey. As a result, there was a reduction in
cost in the Adults Social Care Budget. Officers added that
the leisure centres themselves should not be
seen in isolation and the benefit gained by bringing the leisure
services together within a leisure and wellbeing strategy across
the borough would outweigh any additional cost. The aim was to look
into preventative costs and methods that would reduce costs in the
future.
- To follow up,
the Committee queried about transparency on how the revenue impacts
of decisions were being shown. The Committee was advised that the
positive effects on people’s health would be reflected in
other areas of the Council and the Committee sought assurances on
how the Council was accounting for that. The Committee asked that
when budgets were scrutinised, would there be transparency of the
revenue impacts of the decisions that were being made as the
figures presented on the report suggest that there would be a cost
of around £1 million a year. In response to this, Officers
advised that the cabinet report at the time reviewed the
assessments of the ramifications of the decisions to insource and
had also gone through the risks and benefits associated. At the
time the decision was made, it was recognised that there would be
additional costs that would be incurred and would need to be built
into the budget, this was what gave the rise to the £900,000
being discussed. Officers advised the Committee that when
constructing a budget, it can be difficult as officers can only
include figures that they were confident about and data that can be
quantified. In addition, the budget would also need to factor in
pressures in growth within services and the authority would need to
respond to the demand.
- The Committee
noted the response on the table in regard to the enhanced
enforcement on environmental crime. In response to a follow up
question, the Committee noted that by law, Fixed Penalty Notices
(FPNs) did not have an appeal or challenge system. If people felt
they were unfairly fined, they could choose not to pay the fine,
take the notice to court and then let the judge decide. It was also
noted that although the Council being in partnership with a private
contractor, all the appeals and challenges would be overseen by the
Community Safety and Enforcement team within the
Council.
- The Committee
noted the response in terms of the self-financing for the New River
Sports & Fitness. In response to a question form the Committee,
Officers advised that there would be an investment of
£533,000 into New River next year as part of the original
assessment to take forward for maintaining assets. This would be a
part of an overall investment in other assets at New River and not
just in terms of achieving the additional revenue income savings
and would be self- financing without incurring a cost to the
Council.
- The Committee
noted the update presented on the report on Tottenham Hale Green
Space. The Committee sought assurance on if this scheme would be
viable as the table highlighted £3.2 million as an unfunded
amount. Officers advised that this would not be a case of assessing
viability as when starting the Capital Programme, Officers included
predicted totalities for what the scheme would cost and the budget
would represent all its phases. It was noted that each phase would
only progress once the funding solution was solved and that was
when the project would go forward.
- The Committee
noted that the term unfunded meant that the funding source was not
identified, however, officers had to put totality of everything in
the budget as it happens in phases once funding was identified.
Most of the time the schemes would be waiting for funding form the
GLA as they fund in tranches. The Council would need to bid or
apply for the funding to progress with projects.
- The Committee
was assured that the Capital Programme was a framework which
enabled the delivery of all capital schemes that the Council would
be engaging in the next 5 years. Officers explained that as it was
a framework, it was difficult to predict exactly how the project
would turn out in two or three years’ time. As the phases
were based on assumptions, Officers were only able report back to
the Committee on how reality would be matching against the
framework in real-time.
- The Committee
noted the response received in regard to Future High Street
Project.
The following was noted in discussion of the Adults
& Health Scrutiny Panel:
- In relation
to the proposal on funding for Connected Communities and Continuing
Healthcare, the Panel noted the response provided and recommended
for this to be referred back to the Adults Health Scrutiny Panel to
be looked at as part of a wider agenda item.
- In relation to Strength Based Working MTFS
proposal, the Committee had requested details of support groups
available in each of the three locality areas in the Borough. It
was noted that a piece of work was underway with Haricare and this would be integrated into the
locality model. The Committee recommended that this information to
be rolled out to all community groups and not just on Haricare site, as this may not be accessed by all
residents in the borough.
The following was noted in discussion of the
Housing, Planning and Development Scrutiny Panel:
- In response
to a question regarding the saving on the tracker being double
counted, officers assured the Committee that the MTFS had been
adjusted to eliminate the double count. The main report now
reflects the overall financial position that was being reported and
the final budget had improved in totality.
- The Committee
sought for further clarification on this as it was noted that the
initial proposed saving was being considered as a written off
savings and then the adjusted saving was being considered as a new
saving. The Committee questioned this approach as the adjusted
figures would not be a new saving and wanted clarity on why this
was being presented as a new saving. In response to this, Officers
advised that this would be reviewed to assess whether this was the
best depiction of how to make the adjustments.
- In response
to a follow up question on how this double count occurred, the
Committee was advised that there had been discussions with
Directors to evaluate how this error occurred. It was noted that a
presentational fault could have led to some of the savings being
misinterpreted and being double counted. The Committee was assured
that there had also been engagement with colleges to review and
tighten processes to prevent this from happening in the
future.
RESOLVED
That the responses to
outstanding queries from 18th January OSC meeting were
noted.