Proposal:Full planning application for the redevelopment of the existing rear car park for the erection of a three storey building (plus roof enclosure) comprising of Class E floorspace; 2 x two storey links; creation of central courtyard; parking and landscaping; and refurbishment and external alterations of the existing Civic Centre and offices, including alterations to entrance facade and fenestration; and associated works for the continuation of mixed civic (Class F1) and office (Class E) uses
Listed Building Consent application for the refurbishment and extension of the Civic Centre including the replacement of elevational pre-cast concrete panels; replacement of windows and curtain walling; removal of entrance steps and replacement with a ramp; removal of part of the roof structure to create an open plant room; installation of photovoltaic panels at roof level; installation of thermal insulation; removal of internal partitions in the north wing; extension to the Civic Centre to provide three-storey building and 2x two-storey links; and associated works
Recommendation: GRANT
Minutes:
Samuel Uff, Planning Officer introduced the report for full planning application for the redevelopment of the existing rear car park for the erection of a three storey building (plus roof enclosure) comprising of Class E floorspace; 2 x two storey links; creation of central courtyard; parking and landscaping; and refurbishment and external alterations of the existing Civic Centre and offices, including alterations to entrance facade and fenestration; and associated works for the continuation of mixed civic (Class F1) and office (Class E) uses. Listed Building Consent application for the refurbishment and extension of the Civic Centre including the replacement of elevational pre-cast concrete panels; replacement of windows and curtain walling; removal of entrance steps and replacement with a ramp; removal of part of the roof structure to create an open plant room; installation of photovoltaic panels at roof level; installation of thermal insulation; removal of internal partitions in the northwing; extension to the Civic Centre to provide three-storey building and 2x two-storey links; and associated works.
The following was noted in response to questions from the Committee:
Cllr Iyngkaran attended the Committee and spoke in support of the application.
The Chair invited the Applicant Team – Jonathan Kirby – to respond to questions from the Committee. The following was NOTED:
Cllr Rice put forward a motion to amend the number of ordinary parking spaces to 10 within the scheme. There was no seconder so the motion was not carried.
Cllr Bevan put forward a motion seeking an amendment for the number of accessible parking bays, Cllr Rice seconded this motion. Following a vote with 4 against, the motion was not carried.
The Chair asked Robbie McNaugher, Head of Development Management and Enforcement Planning to sum up the recommendations as set out in the report. The changes to conditions and obligations in the addendum were noted to members. The Chair moved that the recommendation be granted and following a vote with 6 in favour, 0 against and 0 abstention.
RESOLVED
1. To GRANT planning permission and that the Head of Development Management or the Assistant Director Planning, Building Standards & Sustainability is authorised to issue the planning permission and impose conditions and informatives subject to signing of a shadow Section 106 Legal Agreement providing for the obligations set out in the Heads of Terms below and a section 278 Legal Agreement providing for the obligations set out in the Heads of Terms below.
2. That delegated authority be granted to the Head of Development Management or the Assistant Director Planning, Building Standards and Sustainability to make any alterations, additions or deletions to the recommended measures and/or recommended conditions as set out in this report and to further delegate this power provided this authority shall be exercised in consultation with the Chair (or in their absence the Vice-Chair) of the Sub-Committee
3. That, following completion of the agreement(s) referred to in resolution (1) within the time period provided for in resolution (2) above, planning permission is granted in accordance with the Planning Application subject to the attachment of the conditions.
4. To GRANT Listed Building Consent and that the Head of Development Management or the Assistant Director Planning, Building Standards & Sustainability is authorised to issue the Listed Building Consent and impose conditions and informatives.
5. That delegated authority be granted to the Head of Development Management or the Assistant Director of Planning, Building Standards & Sustainability to make any alterations, additions or deletions to the recommended heads of terms and/or recommended conditions (planning permission and/or Listed Building Consent) as set out in this report and to further delegate this power provided this authority shall be exercised in consultation with the Chair (or in their absence the Vice Chair) of the Sub-Committee.
Conditions Summary – Planning Application HGY/2023/1043 (the full text of recommended conditions is contained in Appendix 01 of this report).
2) Approved Plans & Documents
3) External materials
4) No occupation until LBC substantially complete
5) Site levels
6) Detailed Fire Statement
7) Landscape Details – incl. boundary treatment
8) Art installation strategy
9) Community and Civic Use Plan
10) Trees protection plan
11) Arboricultural Method Statement
12) Biodiversity
13) Living roofs
14) Energy Strategy
15) Retrofit strategy and monitoring
16) Future DEN Connection
17) Overheating
18) BREEAM Outstanding (PRE-COMMENCEMENT)
19) PV Arrays
20) Secured by Design
21) Secure by Design Accreditation
22) Land Contamination – Part 1 (PRE-COMMENCEMENT)
23) Unexpected Contamination
24) Car Parking Design & Management Plan
25) Cycle Parking Details (PRE-COMMENCEMENT)
26) Vehicular Barriers
27) Refuse and other stores
28) Delivery and Servicing Plan
29) Management and Control of Dust (PRE-COMMENCEMENT)
30) Non-Road Mobile Machinery 1 (PRE-COMMENCEMENT)
31) Non-Road Mobile Machinery 2 (PRE-COMMENCEMENT)
32) Impact Piling Method Statement (PRE-COMMENCEMENT)
33) Telecommunications
Informatives Summary – Planning Application HGY/2023/1043 (the full text of Informatives is contained in Appendix 01 to this report).
1) Working with the applicant
2) Community Infrastructure Levy
3) Hours of Construction Work
4) Party Wall
5) Asbestos Survey prior to demolition
6) Dust
7) Disposal of Commercial Waste
8) Piling Method Statement Contact Details
9) Land Ownership
10) Site Preparation Works
11) Listed Building Consent
12) Early Purchase of Trees
Conditions Summary – Listed Building Consent Application HGY/2023/1044 (the full text of recommended conditions is contained in Appendix 02 of this report).
1) 3-year time limit.
2) Development to be in accordance with approved plans and documents.
3) Detailed external elevations
4) Roof level repairs and alterations
5) Interior plans and methodologies
6) Lobby reception area details and methodologies
7) Registrars wing area details and methodologies
8) North wing office area details and methodologies
9) Committee rooms area details and methodologies
10) Council Chambers area details and methodologies
11) Hidden historic features
12) Plumbing, mechanical & electrical services
13) Lighting
14) 5-10-year cycle of surveys
15) Installation of any fixtures to fabric of building
Informatives Summary – Listed Building Consent HGY/2023/1044 (the full text of Informatives is contained in Appendix 02 to this report).
Working with the applicant
Planning Obligations
(ii) Planning obligations are usually secured through a S106 legal agreement. In this instance the Council is the landowner of the site and is also the local planning authority and so cannot legally provide enforceable planning obligations to itself.
(iii) Several obligations which would ordinarily be secured through a S106 legal agreement will instead be imposed as conditions on the planning permission for the proposed development.
(iv) It is recognised that the Council cannot commence to enforce against itself in respect of breaches of planning conditions and so prior to issuing any planning permission measures will be agreed between the Council’s Housing service and the Planning service, including the resolution of non-compliances with planning conditions by the Chief Executive and the reporting of breaches to portfolio holders, to ensure compliance with any conditions imposed on the planning permission for the proposed development.
(v) The Council cannot impose conditions on planning permission requiring the payment of monies and so the Director of Placemaking and Housing has confirmed in writing that the payment of contributions for the matters set outbelow will be made to the relevant departments before the proposed development is implemented.
1. Employment & Skills Plan
a) Submission of an employment and skills plan
b) No less than 20% of the peak construction workforce to be Haringey
Residents;
c) Provision of skills-based training to the 20% referenced above;
d) 5% of the peak workforce to be provided with traineeships;
e) Provision of a construction apprenticeships at one per £3m development construction cost up to a maximum of 10% of total construction workforce;
f) Provision of a £1,500 support contribution per apprentice;
g) Provision of no less than five STEM/career inspirational sessions per
construction phase;
h) Regular liaison with the Council to allow local businesses and suppliers to
tender for works;
i) Other requirements as agreed in discussions with the Council’s Employment and Skills Officer.
2. Future connection to District Energy Network
a) Submission of Energy Plan for approval by LPA;
b) Ensure the scheme is designed to take heat supply from the proposed DEN (including submission of DEN Feasibility Study)
c) Design of secondary and (on-site) primary District Heat Network (DEN) in accordance with LBH Generic Specification and approval of details at design, construction, and commissioning stages.
d) Use all reasonable endeavours to negotiate a supply and connection agreement with the DHN within a 10-year window from the date of a planning permission.
3. Highways Agreement and Works Plan
a) £366,000 for agreed highway works, including but not limited to, footway improvement works, access to the Highway, measures for street furniture relocation, carriageway markings, and access and visibility safety requirements;
4. Site Wide Workplace Travel Plans
Submission of a Travel Plan to maximise usage of public transport to also include:
a) Provision of welcome workplace induction packs containing public transport and cycling/walking information, available bus/rail/tube services, map and timetables;
b) Provision of showers lockers and changing room facilities for the workplace element of the development;
c) Payment of £2,000 (two thousand pounds) per year per travel plan for monitoring of the travel plan for a period of 5 years.
5. Construction Logistics and Management
a) Provide a contribution of £5,000 towards the assessment and monitoring
of a detailed construction logistics and management plan (secured by condition)
6. Energy Statement and Carbon offsetting
a. An amended energy statement is to be provided before building works commence of the development;
b. Provision of a contribution to offset the carbon emissions of the development where not met on site against the zero-carbon target;
c. Estimate of the carbon offset figure is £98,325 (+ 10% management fee) for the whole development which is to be reviewed once the amended energy statement has been reviewed
7. Monitoring
Provision of a financial contribution towards monitoring of the planning obligations in accordance with the Planning Obligations SPD.
(vi) In the event that members choose to make a resolution contrary to officers’ recommendation, members will need to state their reasons.