The Panel received a report which
provided an update on floodwater management and the highways gully
cleaning programme. The report was introduced by Mark Stevens,
Assistant Director of Direct Services, as set out in the agenda
pack at pages 53 to 64. By way of introduction, officers set out
that the Borough had suffered from two bouts of significant
flooding in July 2021 and August 2022 and that since then the
Council had cleaned all 16,000 gullies within its network. The
following arose during the discussion of this report:
- Members enquired about the water tank in Priory Park and what
was happening with it. In response, officers advise that there was
an ownership dispute taking place with Thames Water about whose
responsibility it was to manage and maintain it. Part of the
dispute emanated from the transition process from the National
River Authority to the Environment Agency in the 1970s. The Council
had challenged Thames Water’s assertion that it was not their
responsibility and were waiting for a further response.
- In response to a follow-up question, officers advised that the
tank was not functional during the severe flooding incidents in
July 2020 and August 2021 and that subsequent photographs had
showed that the tank was completely dry. In relation to a further follow-up around
timescales, officers advised that it was being handled by the
Council’s legal team and that there were no firm timescales
at present. There was a flood alleviation scheme planned for Priory
Park but that this would be undertaken following resolution of the
issue with Thames Water. Without the tank being properly maintained
there was a risk of the water being stored but not dissipating in
the right way.
- In response to a question about the balance between cyclical and
reactive cleansing, officers advised that the Council’s
highways contractor Marlborough Highways carried out reactive
maintenance as well as planned maintenance. Cleansing in response to yellow flood warnings was
undertaken and there was a degree of judgment required from
officers about how and when this was undertaken and the associated
costs.
- The Panel sought assurances that the Council was not effectively
doing Thames Water’s job for them. In response, officers
advised that as the lead local authority for flooding, the Council
could looking into the causes of an incident of flooding. It was
noted that a lots of the issues were caused by the fact that there
was a capacity issue with the Victorian sewage system in London.
Officers commented that there was some consideration needed of how
the pressure on the sewar system could be alleviated and that fact
that the Council had allowed people to pave over their gardens
which has caused problems with surface water run-off. Officers
advised that they were looking into whether enforcement action
could be taken under the Highways Act.
- The Panel queried what could be done in respect of digital
poverty and the fact that the useful advice section on flooding was
all online. In response, officers acknowledged that was challenge
and it was a challenge that was not limited to just highways or
flooding. Officers advised that social media updates had also been
provided around flooding. Non-digital forms of communication, such
as lamppost banners, were perhaps better suited to more general
information. The Chair highlighted the importance of maintaining a
level of communication to people whilst it was still relatively
fresh in their minds.
- The Panel queried whether a piece of work could be done to
identify resident associations in high-risk areas and meet with
them to discuss flooding. In response officers advised that this
was something they would consider going forwards.
- Officers advised that there was still a piece of work to be done
around improving flood reporting and that this would form part of
the multi-agency flood plan.
- The Panel raised concerns about flooding on Seven Sisters Road
and that this did not seem to be one of the priority areas
mentioned in the report. In response, officers advised that this
was a TfL managed road and that did create some problems in terms
of getting things done. Officers agreed to provide a written
response to officers on what was being done to push back to TfL
about flooding on their road network. (Action: Mark
Stevens).
- The Panel sought clarification about whether the entire gully
network would be cleaned every two years. In response, officers
advised that they had completed the first cycle and that all gully
networks had been cleansed as part of this. The second tranche was
underway which was risk based, with High, Low and Medium priority
levels.
- In response to a question about cleaning of the footway gullies
on Harringay Passage, Mark Stevens agreed to speak to the team and
provide an update on what was happening in relation to cleansing
footway gullies. (Action: Mark Stevens).
- In relation to gullies on the highway, officers set out that
rainwater gardens may be more appropriate in some circumstances.
Cllr Cawley Harrison agreed to let officers know of any specific
gullies he was concerned about.
- In response to a follow up question, officers acknowledged that
they would be willing to receive recommendations from Members about
possible locations for potentially removing a parking bay and
installing a rainwater garden or a pocket park.
RESOLVED
Noted