The Committee received a
report which provided and update on intrusive fire safety
inspections. The report was introduced by Judith Page, Assistant
Director for Property Services as set out in the second dispatch
agenda pack at page 1. The following arose as part of the
discussion on this report:
- In response to a
question, officers advised that the spandrel windows in question
were in the stairwell rather than the domestic areas, so a stay put
strategy was assessed as being safer. Officers emphasised that a
stay put strategy was based on advice that residents should only
stay put as long as they felt safe. Often when there was a fire in
a block, the surrounding units did not realise there was a fire due
to the fire being compartmentalised through the building’s
design. One of the key differences between the two strategies in
terms of the infrastructure works undertaken, was that there was no
fire alarm alerting people to evacuate the building in a block with
a stay put strategy. It was noted that Headcorn & Tenterdon had
moved to an evacuation strategy and that a fire alarm system had
been installed.
- In relation to a
query about the risk of fire spreading vertically up through
stairwells, officers advised that the fire risk assessments were
carried out by external fire engineers and qualified fire risk
assessors, and they had re-evaluated each of the high risk blocks
as part of the fire safety inspection process.
- In response to a
question about building safety, officers reassured members that
there were no unsafe buildings in the borough. Stella House was
deemed as being the highest risk block and work was underway to
install a fire alarm system and a waking watch had been in place to
ensure it was patrolled constantly by staff, since the building
assessment was carried out. Officers acknowledged that there were a
number of fire safety risk assessment actions that needed to be
completed, as did all similar organisations, these actions were
being worked through.
- In response to a
question about the recruitment of a number of fire safety managers,
officers advised that these roles were going out to recruitment
shortly and that this had been delayed slightly because of
insourcing.
- Officers advised that
all blocks deemed high risk would need a building safety case in
place by September 2023. These cases were incredibly detailed.
Officers also advised that they had regular meetings with senior
officers from the fire brigade, which took place every six weeks or
so.
- Members sought
clarification around the fact that the report identified one block
as being high risk and that a number of other blocks were
identified as substantial and manageable risk. In response,
officers advised that ‘high risk’ blocks were
identified under the Building Safety Act 2022 and the Fire Safety
Act 2021, as being above 18 meters tall. These would always be
deemed as high risk due to the specialist equipment needed by the
fire brigade to tackle a fire in buildings that size. Separate to
this, when the assessments were carried out about spandrel window
panels, these were given varying levels of risk for the Council to
prioritise when it carried out works to those blocks. Officers
emphasised that these buildings were safe and that a high risk
rating for fire safety in terms of spandrel windows related to that
specific feature, rather than the whole building.
- In response to
concerns about delays to Type Four fire safety inspections,
officers advised that all Type Four surveys had been done. However,
there were a number of actions that came out of these assessments
that needed to be completed. The works identified as part of the
Type Four assessments would be undertaken as part of the major
works programme due to the type and cost of works
involved.
RESOLVED
Noted.