The Panel received a verbal presentation on the
council housing elements of the proposed High Road West (HRW)
scheme, along with a briefing paper that was included in the agenda
pack at pages 87-90. The presentation was introduced by Sarah
Lovell, Head of Area Regeneration. Peter O’Brien, AD for
Regeneration and Economic Development was also present. The
following key points were noted from the presentation:
- There are
three key ways in which the Council can ensure that the agreed
number of Council homes are delivered – The Development
Agreement with Lendlease, GLA funding contracts and Planning
policy.
- HRW is a
phased agreement. The Development Agreement is structured in such a
way as to ensure that conditions are met before a phase can
progress. Land will not be passed to Lendlease until conditions are
met. The core requirements of the scheme are the primary
requirements which must be delivered. These include the delivery of
500 council homes at social rents. The scheme cannot proceed until
the core requirements are met.
- GLA Funding
contracts – Should the scheme not deliver the social rent
homes by the agreed milestone dates, GLA funding for the whole
scheme could be withdrawn. Consequently, 500 social rented homes
must be delivered otherwise the scheme cannot progress.
- Planning
Policy also provides protections on the amount of affordable homes
delivered. Planning policy requires the scheme re-provides the
existing social rented homes on Love Lane Estate. HRW is targeting
40% affordable homes across the whole scheme. Phase A already has a
firm commitment to deliver 40% affordable housing, including 500
social rent homes.
- The Love Lane
Estate currently has c.220 tenanted and 45 leaseholder properties,
the scheme has to be delivered in phases. The Council has agreed
phasing commitments, which are enshrined in the landlord offer,
which seek to minimise disruption to residents and maximise the
number of residents who move once from their existing homes on the
Love Lane Estate into their new homes within the
scheme.
- To meet this
commitment, Lendlease must build social rented homes early to
ensure that residents can move to their new homes. If Lendlease do
not do this, vacant possession of Love Lane cannot be achieved, and
development can’t proceed. This is the reason that the first
phase includes 100% council homes that council homes are
prioritised in the subsequent phases.
The following arose during the discussion of this
agenda item:
- The Panel
noted that there had been a number of rumours floating around that
Lendlease were going to reduce the number of homes for social rent
down from 500 and that they would seek to build this element of the
scheme last.
- The Panel
welcomed the assurances given in the presentation that this was not
the case and suggested that the Council should be proactively
seeking to counter these rumours with the information provided in
the presentation. The Panel noted that Members had received an
email from the Love Lane Temporary Accommodation Group that set out
a number of concerns based on incorrect information. The Panel
requested that officers engage with TAG to assuage their concerns
and counter some of the rumours that were circulating. In response,
officers acknowledged that they were happy to do so but they had
not seen the email in question. Officers assured Members that the
Council was seeking to move residents out into replacement
accommodation as quickly as possible and that it needed the social
housing elements built first, in order to achieve this. Email to
Members from TAG to be circulated to officers. (Action:
Clerk).
- In response
to a follow-up question, officers agreed that the reserve matters
planning process provided additional safeguards around the ability
of the Council to ensure that the social housing elements of the
HRW scheme were front-loaded.
- The Panel
sought assurances around the risk management processes that were in
place for the scheme. In response, officers advised that as with
any scheme this size, there was a robust set of risk management
processes in place and that a Risk Register was part of this.
Officers identified the 17th of March Planning Committee
date and the need to secure vacant possession in order to secure
the site for development as examples of some of the key risks for
the scheme.
- In response
to a question, officers acknowledged that Spurs owned a relatively
small area of land south of White Hart Lane and that officers hoped
to be able to secure this site through negotiations with Spurs.
However, as with any other site, the Council had the option to
pursue a CPO although this was very much seen as a last
resort.
- In terms of
timescales, officers advised that Plot A of the scheme, which
included the GRACE Centre, was being progressed and that everything
was in place to deliver this. However, there were risks with the
other plots and that these could require a CPO to progress.
Officers advised that a report was being prepared for June Cabinet
which would begin the CPO process. It was anticipated that the
process would take 18-24 months. By the end of this process, it was
anticipated that Plot A would be finished, and that the development
would move on to other phases of the scheme.
RESOLVED
Noted