Report of the Director of Children’s Services. To be introduced by the Cabinet Member for Early Years, Children and Families.
The award of a construction contract to the preferred bidder for the Wood Green Youth Hub main fit out works. This report will inform Cabinet of the procurement process completed to appoint a contractor. The report will also update Cabinet on progress to date, the design development and co-design programme, the programme milestones and the project budget.
Minutes:
Cllr Diakides left the meeting at 19.55.
The Cabinet Member for Early Years, Children and Families introduced the report which sought authority to award a construction contract to Diamond Build Plc for the delivery of the Wood Green Youth Hub fit out works. The contract allowed the project to move closer to the operational opening of the facility.
The Cabinet Member outlined that the facility would create a focal point for young people in the community, allowing the young people to develop practical skillsets, promote creativity, provide a safe space for socialising and to obtain advice and support.
It was noted that Wood Green Young Voices (WGYV) had played a major role in design development, with a full Co-Design programme being completed in conjunction with the development of RIBA design stages 1 – 4 (feasibility to detailed design). The Cabinet Member advised that it had been incredibly important to ensure the users of the facility have had the ability to shape the project to ensure their needs are met.
The Cabinet Member commented that the project had progressed well and was ready to move into the next stage of project delivery to allow the physical works to commence on site. This would allow the operational opening of the facility to be completed ahead of the 2022 school summer holidays.
There was a question from Cllr Hakata on the risk of the Youth Hub not being ready for opening in July 2022. In response, it was noted that there could be issues with the current volatility in the building works market, and risk associated with delivery construction contracts. To mitigate this delay, the Capital Works team would be placing orders for materials as soon as possible. The team would also continue to monitor risks. There had already been some works to remove cross contamination at the premises and also fire safety issues addressed to contain some of the risks.
Following consideration of exempt information at item 26:
RESOLVED
1.
2.
3.
1.
To approve an award of contract to Diamond Build Plc
for the sum of £1,069,792.00 in accordance with Contract
Standing Order (CSO) 9.07.1(d).
2.
To approve the issue of a letter of intent to
Diamond Build Plc, which will be limited to
£100,000.
1.
Reasons for decision
6.
Young
people living or attending school in and around Wood Green are at
risk. Noel Park is in the 10% of the most deprived areas nationally
with young people disproportionately affected. They are at risk of
gang and knife crime with impacts felt across families and
communities. Some of the Local Authority’s highest Early Help
referring schools are in the west of the borough, with many pupils
living in the Noel Park ward. Haringey has been working with a
range of community partners and the police to embed measures to
tackle issues early.
In
addition to pre-existing challenges in Wood Green, young people
have been disproportionately affected by the Covid 19 crisis through parental job losses and
school closures. The project will deliver a youth hub as young
people need a dedicated facility urgently to provide essential
support services. The Council is also proposing a new employment
and skills focus to the hub, which will help negate the impact of
Covid 19 on progression into work for
local young people.
In
delivering this Youth Hub, the Council will significantly improve
the range and quality of youth provision, with an offer that will
appeal to young people in the Noel Park and Wood Green areas and
beyond. The space will house services designed to support improved
outcomes and will be overseen by skilled youth and community
workers and will offer a broad range of provision that will support
raised attainment and aspiration for young people in the
borough.
Delivery of the Wood Green Youth Hub is an action from the Youth
at Risk Strategy 2019 – 2023. The strategy was designed to
reduce youth crime and support attainment for young people in the
borough. The lack of a youth space in the Wood Green and Noel Park
areas has been a concern for many years and the youth hub seeks to
resolve this problem. Its presence in Wood Green will offer young
people the ability to congregate in a safe space designed to
support their development and help them to aspire and achieve. The
Bruce Grove Youth Hub in the east of the borough is well recognised
as a centre of excellence for youth work, (Ofsted 2018), and has
therefore been used as a template for the design of the new Wood
Green Youth Hub.
The
Wood Green Youth Hub project has worked well with local community
groups and has founded the WGYV to develop the design of the
facility. This contract award allows the design ambitions of the
WGYV and the local community groups to become a reality.
The
project team have completed RIBA stages 1-4 (feasibility to
detailed design) and have developed the design as per the
requirements of the Early Help team. The contract award allows the
project to move into the next delivery stage by commencing the main
construction works on site.
At
present, the building is not in a useable state, and if the main
fit out works are not completed the building will continue to sit
vacant as the lease agreement is already in place. It is considered
that this contract award will help the Council to realise best
value for money by providing a high functioning attractive
site.
The
Council has completed a competitive tender process via the
Council’s London Construction Programme (LCP) Dynamic
Purchasing System – Minor Works – Principal Contractor
lot. The project quantity surveyor – Baker Mallett LLP
– has interrogated the pricing submissions and has confirmed
that Diamond Build Plc is the most economically advantageous
bidder.
The
construction market is currently in a volatile state due to the
adverse impacts of Brexit and the
Covid pandemic to the supply of labour
and materials. The proposed contract with Diamond Build Plc is a
workable solution to project delivery, with the estimated
construction programme aligning with the Early Help team’s
ambitions for operational opening and the estimated value falling
within the constraints of the project budget. Due to the current
volatility of the construction industry, failing to approve the
current proposal or re-procuring the works could risk increased
costs and prolonged lead times for the supply of materials because
of the uncertainty.
This
report also recommends that Cabinet approve the immediate issue of
a letter of intent to Diamond Build Plc. Agreeing the issue of a
letter of intent will allow the contractor to place immediate
orders for long lead items. As noted above, the construction
industry is currently experiencing delays and reduced supplies of
materials because of Brexit and the
Covid pandemic. The letter of intent
will help secure the supply of materials without delay to ensure
the construction programme is protected.
When tenders were returned on 9th December 2021, several bids included qualifications. This required an extended period to clarify costs, which has resulted in a slightly increased programme. However, this contract award still works towards an operational opening before the 2022 school summer holidays.
2.
Alternative options considered
7.
There
is the option to re-procure the construction works, however, it
must be noted that there is no guarantee that re-procuring the
works will secure a more competitive price. Baker Mallett LLP has
completed a full review of Diamond Build Plc’s submission,
benchmarked the prices provided against comparable projects and
have confirmed that this price provides good value for money. If
re-procurement is to be considered there is a risk that the project
programme would be adversely impacted and delay the operational
opening of the facility which would put further risk to a
much-needed service.
There is an option to decline Diamond Build Plc’s appointment and close the project. However, the lease agreement has been completed and this option would mean the site would be left vacant. Additionally, this would mean that the young people of Wood Green would not be provided with a Youth Hub facility.
Supporting documents: