Agenda item

PPA/2021/0011 - BRUNEL WALK, TURNER AVENUE ESTATE, N15 5HQ

Proposal: Demolition of the existing 36 temporary accommodation homes on site and redevelopment of Brunel Walk and some of the space between the Council buildings of Turner Avenue to create 44 additional new homes for Council rent.

Minutes:

The Committee considered the pre-application briefing for the demolition of the existing 36 temporary accommodation homes on site and redevelopment of Brunel Walk and some of the space between the Council buildings of Turner Avenue to create 44 additional new homes for Council rent.

 

The applicant team and officers responded to questions from the Committee:

·         The Committee welcomed the mix of unit sizes that were proposed.

·         In relation to parking, it was clarified that no parking spaces would be lost in the estate and that there would be two additional spaces in the Turner Avenue Estate area. Some members noted that the proposals included a number of family sized units and that this was likely to result in additional cars and stress on parking.

·         It was noted that the Quality Review Panel (QRP) and the application report discussed the permeability of the site. Some members enquired whether the permeability of the site would be increased and cautioned that increasing the permeability of the site for vehicles could create some safety issues. The applicant team noted that the site was an alleyway at present with a number of avenues that were used as cut through routes. It was explained that the proposals would aim to reduce permeability of the site by defining public and private space more clearly with landscaping and boundary treatments.

·         The Committee enquired about outlook and the proximity of balconies in Blocks B and C to the existing blocks, about the outlook from the mews houses, and about overlooking into the gable ends of existing blocks. The applicant team explained that the existing Turner Avenue Estate wings had outlook from the southern end and would look directly onto the new courtyards. It was noted that it had recently been confirmed that the units in the existing blocks were two bed units and that the applicant team would need to consider the position and treatment of the balconies in reference to the windows; it was added that consultation responses were also being considered.

·         The Chair commented that there was a sketch which showed projecting balconies and that she would be opposed to having those, especially at the lower levels. She explained that these would not be very private and that people would likely cover up the transparent elements. It was explained that the application sought to optimise the number and types of accommodation on site and that recessed balconies used potential accommodation area and had a significant impact on the thermal performance of the building. The applicant team believed that the projecting balconies worked as part of the design. It was noted that they were considering the treatment of the balustrade and that some screening or alternative positioning of balconies might be possible but this would need to be weighed against the need to deliver as much high quality accommodation as possible.

·         In response to a question from the Committee, the applicant team stated that some of the key challenges would be to integrate the development with the wider estate, to deliver the significant enhancements to the existing public realm and open spaces, and to ensure that the buildings also respected the wider context and the properties on Seaford and Kirkton Roads. It was noted that there was the possibility of remodelling, potentially with reduced units or setting back, and that the balance of delivering affordable accommodation and safeguarding residential amenity would need to be carefully considered.

 

The Chair thanked the applicant team for attending.