This item covered two separate reports,
one on the size of homes in the Housing Delivery Programme and one
on the Cranwood Housing Development
Site.
Size of Homes in the Housing Delivery
Programme
Robbie Erbmann, Assistant Director for Housing, introduced
the report on the size of homes in the Housing Delivery Programme,
noting at the outset that while family sized housing was required,
there was also a desperate need for Council housing of all sizes.
The housing register showed that, of the 581 households in the most
urgent need, 364 needed a one-bedroom home and 130 needed a
two-bedroom home. Of the 11,300 households on the housing register,
73% required a one or two bedroom home.
Of the 475 Council homes in the programme
that already have planning permission 22% were three-bedroom homes
and 2% were four-bedroom homes. At this early stage of the
programme there was a high proportion of Council homes being
delivered through acquisitions which meant that the bedroom mix was
constrained. However, across the whole programme 31% of properties
would have three or more bedrooms. The site at Ashley Road was
expected to deliver around 150 Council homes, 65% of which will
have three or four bedrooms.
There were also financial challenges involved with building family
sized Council homes because of the rent generated.
The revenue on a one-bedroom Council home exceeded
the cost of interest in year one, and it would take 20 years to pay
off the loan required to build it. However, revenue for a
four-bedroom home in the same scheme would not exceed the cost of
interest until year 30, and it would take 80 years to pay off its
loan. This was why the Council was working with the GLA to make the
case for increased investment for family-sized homes in the next
funding programme. This would help to improve the proportion of
family-sized housing in future and, while the family housing target
may not have been met in the first 1,000 homes delivered, it was
hoped that the target could be met in the next 1,000.
Robbie Erbmann, Anna
Blandford, Head of Housing Development, and Cllr Ibrahim, Cabinet
Member for Housing and Estate Renewal, then responded to questions
from the Panel:
- Cllr Barnes
asked how many of the remaining 525 homes (i.e. the 1,000 target
minus the 475 identified in the report) in the current phase would
be acquisitions and how many would be direct delivery. Robbie
Erbmann said that there were actually
around 800 homes identified for the rest of the phase,
approximately 250 of which were expected to be acquisitions. More
precise figures could be provided in writing. (ACTION) Cllr
Ibrahim said that Council housing stock may be increased through
different mechanisms, including through acquisitions, and that it
was important to ensure that this was the kind of housing that was
needed and that the Council was not paying over the odds for it.
Robbie Erbmann added that internal
financial controls would prevent over the odds payments in any
case.
- Asked by Cllr
Barnes for further details about the next phase of 1,000 housing
deliveries, Robbie Erbmann said that,
of the projects that were in the early stages of feasibility, there
were around 2,300 homes. New sites and opportunities for
acquisitions were being identified from time to time to add to the
programme.
- In response
to a question from Cllr Say about scaling up direct delivery,
Robbie Erbmann said that it was
incumbent on the Council to look at all opportunities to increase
its housing stock and to scale up both direct delivery and
acquisitions from developers given the level of housing need in the
borough. The direct delivery programme was now large with over 70
sites in the borough, while the size of the Council’s
delivery team had been doubled since he had joined the
Council.
- Cllr Say
asked whether the business plan for the programme could be
provided. Robbie Erbmann and Cllr
Ibrahim referred to the regular updates provided to the Cabinet
which were publicly available and said that any specific
information could be circulated to the Panel on
request.
- Asked by Cllr
Diakides for further details on the
attempts to obtain increased GLA funding, Robbie Erbmann and Anna Blandford said that two bids were
being prepared for submission in about a month’s time. One
was a bolt-on to the existing Building Council Homes for Londoners
Programme which runs until 2023, the other was the Council’s
future affordable housing programme for 2021-26. It was hoped that
the funding would be more flexible with higher grants for larger
units (the current tariff provided a fixed grant per home) but
clarification on this was still being sought. Asked by Cllr
Brabazon about the implications of the
new GLA guidance which did not favour demolition, Robbie
Erbmann said that the bids were not yet
complete but that he would be happy to update the Panel when the
outcomes were known.
- Asked by Cllr
Diakides about the Chocolate Factory
development, Robbie Erbmann and Anna
Blandford said that the Council was currently in the process of
finalising the acquisition of the site. Delivery was expected to be
in two phases, the first involving about 80 homes for social rent
while proposals for the second phase were still being developed,
though was likely to include some properties for private
sale.
- Asked by Cllr
Brabazon for further details on the
Ashley Road development, which was expected to deliver 150 Council
homes, Anna Blandford said that there would be around 300 homes in
total with 50% for private sale. The focus was on family-sized
Council homes and so the private sale units were required to
finance the scheme. Detailed plans on the development were not yet
available but would be taken through consultation and the planning
process in due course.
- Asked by Cllr
Say about the current Right to Buy rates, Robbie Erbmann said that the assumption in the
Council’s business plan was that 50 homes would be sold under
Right to Buy per year. However, around 100 former Right to Buy
homes were being purchased each year for the Haringey CBS
(Community Benefit Society). Cllr Ibrahim added that she did not
think that concerns about new Council homes being lost through
Right to Buy would be a significant problem in practice. People who
had been on the waiting list for a long period were unlikely to be
in a position to exercise Right to Buy for a number of years and
also it was not possible for Councils to sell a property under
Right to Buy for less than it cost to build it.
- Asked by Cllr
Say for further details about the Neighbourhood Move Schemes
highlighted in paragraph 3.14 of the report, Robbie Erbmann said that having new build properties
available for secure tenants significantly impacts on whether
people in underoccupied properties are
prepared to move so it was hoped that this would free up more
family-sized homes.
- In response
to a question from Cllr Say about why building was planned at
Waltheof Gardens despite there being a
conservation area, Anna Blandford said that Cabinet approval had
been given for this to enter the programme and, as it was at a very
early stage, the feasibility work had not yet been
completed.
- In response
to a point from Cllr Gordon that, in the context of the 1,000 new
homes target, the size of those homes was also an important factor,
Cllr Ibrahim agreed that more family-sized housing was needed.
However, she said that 1-bed and 2-bed homes were also needed, for
example for young care leavers or for people who were currently
under-occupying larger homes.
- Asked by Cllr
Gordon for an update on the recent audit report on the department,
Robbie Erbmann said that the actions
had been progressed, that there was monthly reporting to the
Council Housing Delivery Board and he believed that the level of
project control and governance was now strong.
- Asked by Cllr
Gordon for an update on the Clarendon Road site, Robbie
Erbmann said that the intention was to pursue a Council-led scheme
although he was unable to comment on the conversations between the
Council and the various parties that had ownership positions on the
site.
Cranwood Housing Development Site
Robbie Erbmann, Assistant Director for Housing, introduced
the report regarding the site of the former Cranwood Care Home. The negotiations that had taken
place over the site had predated his appointment to his role at
Haringey Council. Robbie Erbmann
explained that the site had been included in the portfolio of sites
for development under the Haringey Development Vehicle (HDV). These
proposals and the subsequent HDV designs for a scheme of 62 homes
presupposed the demolition of the adjoining terrace of eight
three-bedroom houses at 102 to 116 Woodside Avenue. The Council was
the landlord of six of the homes but the freeholds of 104 and 106
Woodside Avenue had been sold under the Right to Buy.
The demolition of these houses was
desirable for two reasons:
- This would increase the footprint of the site by 50% and the
developable area by up to 100%.
- The Local Plan includes the whole site within the Site
Allocations DPD.
In July 2018, the Council had decided to
end the HDV in favour of a programme of direct Council housing
delivery. At the same time a private developer was negotiating with
the owners of 104 & 106 Woodside Avenue in an attempt to create
a ransom position in the site. The Council therefore aimed to make
offers that were attractive enough to incentivise the freeholders
to sell to the Council rather than to the developer.
In September 2018, the Cabinet agreed to
acquire 106 Woodside Avenue for £2.15m and 104 Woodside
Avenue on terms delegated to the then Director of Housing,
Regeneration and Planning and the Director of Finance. The reasons
that this was felt, at the time, to be worth doing was that by
unlocking these two homes the whole site could be unlocked and 98
new homes could potentially be built rather than only 40 and that
20 of the new properties would be for private sale thereby bringing
substantial additional funds into the Housing Revenue Account
(HRA).
The Council had also been in discussion with the four secure
tenants at Woodside Avenue who said that they wanted to remain in
their homes. In June 2019, the Council had decided to respect their
wishes to remain and terminated the negotiations to acquire 104
Woodside Avenue. As a consequence, a smaller development scheme was
now being pursued by the Council of 41 homes on the site, of which
32 would be for social rent and nine for private sale. The terrace
of eight house would remain with four being occupied by the secure
Council tenants, three being used by the Council to provide homes
for homeless families and one occupied by the remaining freeholder.
The proposals would be submitted to Planning shortly with the aim
of being on site by November 2021.
Robbie Erbmann then responded to questions from the
Panel:
- Cllr Barnes asked whether the new development would include
separate entrances for social tenants and private tenants. Robbie
Erbmann said that, while different
blocks would have separate entrances, the properties would be of
exactly the same quality and that the bulk of the common space
would be open amenity space for all residents. He added that for
management purposes and to keep services charges low, it is better
to have ownership of a whole block as a freeholder.Cllr Barnes said
that there were advantages to mixed housing and that it was
disappointing to see separation of private and social tenants in
Haringey. Robbie Erbmann said there was
only a small amount of private housing proposed in the development
and so it could not be compared to cases involving large blocks of
private housing with a small proportion of social tenants being
marginalised. Cllr Gordon said that the separation of tenants was a
recurring issue in the Borough and suggested that further
consideration could be given to the overall issue in more detail at
a future meeting. (ACTION) Cllr Brabazon said that her understanding was that
segregated housing was not supported by the new London Plan and
queried why integrated housing was not being implemented in
Haringey. Cllr Ibrahim said that she agreed with the Panel Members
on their general views about housing segregation and understood
their concerns but did not think that this was necessarily an issue
in relation to this specific small scheme. She suggested that
further written information about the layout of scheme could be
provided to the Panel. (ACTION)
- Cllr Barnes asked whether the difficulties in building on the
site due to the water mains pipes were known prior to the purchase
of 106 Woodside Avenue for an above-market price. Robbie
Erbmann said that this had not been a
factor as, while the pipes do create problems with building, they
are in a different part of the site to the Woodside Avenue
homes.
- Cllr Gordon asked why the development could not simply have been
built around the two houses that the Council did not own. Robbie
Erbmann said this wouldn’t have
worked from a development point of view and that the whole terrace
would have needed to be cleared. It may not have been suitable for
large block to overlook two houses for example.
- Asked by Cllr Gordon who the private developer involved in the
negotiation was, Robbie Erbmann said
that this was a small local developer but that he was not able to
divulge the name of this developer for reasons of commercial
confidentiality. To be informed on a confidential basis, the
scrutiny panel would need to submit a request demonstrating their
need to know.
- Asked by Cllr Hare why a CPO process was not pursued an as
alternative to the option of above market value purchases, Robbie
Erbmann said that, while he
wasn’t at Haringey Council at the time, his understanding was
that the advice received was that a CPO would be legal and
technical difficulties with that option on this site. Cllr Hare and
Cllr Diakides asked whether this advice
could be made available to the Panel. Cllr Diakides suggested that the matter could be
referred to the Corporate Committee for further
examination.
- Cllr Diakides asked how many private
houses were being built on Council land, Robbie Erbmann estimated that there were about 400 private
homes out of the 1,600 that were being built through the first
phase of the housing delivery programme. He added that this 75%
social to 25% private sale position had improved from a 60%-40%
split in the previous business plan. Cllr Ibrahim, Cabinet Member
for Housing and Estate Renewal, sad that the building of homes for
private sale was necessary to be able to cross-subsidise the social
housing in the developments. Robbie Erbmann added that the housing delivery programme
would need to modestly grow its income through private sales in
order to continue to invest at a rate of 250 new homes per year.
Cllr Diakides said that the Panel
should be provided with the figures and calculations to demonstrate
that this was necessary. Robbie Erbmann
replied that he would be happy to run a session for the Panel on
the HRA Business Plan though there would be difficulties in
providing costs for individual schemes as this could put the
Council in a poor position in terms of being able to secure
competitive build contracts. Cllr Gordon said that a discussion on
the financing of a housing programme was a useful suggestion to be
added to the Panel’s Work Programme.
(ACTION)
- Cllr Brabazon said that, if there
was no other way of establishing what had happened regarding the
Woodside Avenue properties, then the matter should be referred for
a value for money audit of the purchase of 106 Woodside Avenue from
internal auditors and possibly an external auditor as
well.
Cllr Ibrahim then made further observations on the
Woodside Avenue purchase. She said that an early commitment of the
administration was to build Council homes at the Cranwood site and that, following engagement with
the residents, it was felt that the scheme should be changed. A lot
of campaigning had taken place and the Council had listened to
concerns meaning that plans considered earlier in the scheme were
no longer judged to be suitable. Cllr Ibrahim said that it had been
important to listen to secure tenants whose homes would have been
demolished under the original proposals.
However, earlier on at the time of the purchase of
106 Woodside Avenue, the investment had been considered necessary
to unlock the rest of the site, generating a larger return and more
homes but the situation then changed. Cllr Ibrahim said that Cllr
Brabazon would have had access to the
exempt information at the time as part of the same Cabinet that
collectively took that decision. She concluded that a decision had
been taken which was subsequently changed but that there was
nothing to hide in terms of the finances.
Cllr Gordon said that a question mark remained over
the decision not to pursue the CPO route. Cllr Brabazon said that the project should be looked at
with hindsight and that a value for money look at the matter would
help the Council in the future. Cllr Hare added that the additional
information that he had asked for on the advice received against
using a CPO should be provided to the Panel.
RESOLVED –
That the Panel refers the Cabinet decision to acquire 104 & 106
Woodside Avenue to internal auditors, with oversight from the
Corporate Committee.
That the advice provided to senior officers and the
Cabinet on the potential legal and technical difficulties of using
a CPO to acquire the properties be made available to the Panel and,
if required, to the Corporate Committee.