Robbie Erbmann, Assistant
Director for Housing, introduced a report about the impact of the
Covid-19 pandemic on the Council’s Housing Delivery
Programme.
He said that the Council had previously committed to
a very ambitious programme of delivering 1,000 Council housing
completions by 2022 and that, in order to meet that target, it
would have been necessary for everything to go right. However, the
onset of the pandemic had adversely impacted on the programme in a
number of ways including:
- Illnesses to a number
of key staff;
- Migrating various
procedures online from scratch;
- Reductions to
availability within the supply chain;
- Suspension of
construction work on a number of active sites;
- A significant
shortage of building materials such as plaster;
- An exacerbation of
labour market shortages;
- A reduction to the
speed of construction work on site to around 60-70% due to social
distancing;
The latest estimate was that the Council would
achieve at least 1,000 ‘starts’ by March 2022 and
around 800 completions by May 2023. It may now not be possible to
reach 1,000 completions until 2024. However, it was not yet known
what the impact of a possible second wave of Covid-19 would have on
this timetable.
Robbie Erbmann and Peter
O’Brien responded to questions from the Panel as
follows:
- Asked by Cllr Barnes
about whether the ambitious housing target was realistic and
whether the impact of Brexit had been
factored in to the revised timetable, Robbie Erbmann said that the target was necessarily
ambitious and had mobilised resources but that everything would
have needed to go right to meet it. He added that the current
impact from Brexit is factored into the
plans though there is a wide degree of uncertainty over that impact
which would need to be closely monitored.
- Asked by Cllr Gordon
whether there was a robust and transparent system of project
management of the projects within the Housing Delivery Programme,
Robbie Erbmann said the Council had a
number of experienced project managers from the local government
and housing associations sectors leading the projects. There was a
team of 18 with more being recruited to help deliver the projects
and he was confident that the skills and the systems required to
deliver the programme was in place. He added that they had looked
at two points arising from an audit that had been carried out
earlier in the year on reporting and on financial management. A new
system of software had been introduced and embedded into the
management processes along with a new reporting system. Cllr Gordon
queried comments made in the auditor’s report which could
only give limited assurance that there had been the appropriate
monitoring procedures in place due to the speed of the programme.
Robbie Erbmann said that the report had
identified areas for improvement, all of which had been
actioned.
- Asked by Cllr Gordon
for an update about the delivery of new homes at Broadwater Farm, Peter O’Brien reported that
architects and viability consultants had recently been appointed
and more detailed consultation with residents was planned. This
consultation process had also been adversely affected by the
Covid-19 pandemic and it had been decided that consultation would
not have been appropriate during the lockdown. However, a mixed
approach to consultation had already been developed prior to this,
including both face-to-face and online engagement. The Council was
therefore assessing options on engaging with people who struggle
with online communication, perhaps for example by organising
physical events with smaller numbers of people, though this would
create some challenges. A lot of innovation was happening across
the country to address this kind of problem including new
interactive tools such as virtual rooms that people could use
instead of attending a physical event.
- Asked by Cllr Stone
about how the impact of Covid-19 on the Housing Delivery Programme
compared with other London Boroughs, Robbie Erbmann said that the overall planned trajectory
had been quicker than other Boroughs and that even those that also
had ambitious targets had started their delivery plans earlier.
However, in general, all Boroughs were in the same boat with the
timetables of their programmes being elongated. The GLA’s
Affordable Housing Grant programme had already been extended by
another year in recognition of this.
- Cllr Moyeed asked for further details about the
Council’s approach to zero-carbon developments given that the
Edith Road development in Bounds Green was described in the report
as the Council’s first zero-carbon development. Robbie
Erbmann said that the Council would get
as close as possible to zero-carbon on as many sites as possible
but that zero-carbon can’t always be achieved in every
scenario. Various methods were being looked at to achieve carbon
reductions for the projects being planned, including through the
heating methods for example, and this was a top priority for the
team.
- Asked by Cllr
Moyeed about the overall mix of homes,
who had noted that the first four-bedroom homes in the borough at
social rent in over a decade were planned at Mount View Court in
Harringay ward, Robbie Erbmann said that the current programme included
around 26% family housing and there was an ambition to provide the
3-bed and 4-bed family housing that residents need.
- Asked by Cllr
Brabazon about the viability of the
programme and the delivery partners given the current economic
circumstances, Robbie Erbmann said that
there were some negative signs relating to the HRA including for
example a decline in rent collection, though it was hoped that this
would be a temporary issue. However, the negative impact of these
factors was outweighed by the reduction of the interest rate
through the Public Works Loans Board so viability was currently
looking quite positive. In terms of procurement, while more due
diligence may be required in selecting financially viable partners,
there was still quite a lot of work in the sector so the risk was
expected to be limited.
- Asked by Cllr
Brabazon about the funding position
relating to the Love Lane Estate, Peter O’Brien said that
primary focus of the Council’s efforts has been on securing a
funding package from the GLA which would enable the delivery of 500
Council homes through the High Road West scheme. Discussions were
ongoing and it was hoped that more information on this would
available later in the year.