[ Report of the Assistant Director for Housing. To be introduced by the Cabinet Member for Housing and Estate Renewal.]
Cabinet is asked to approve the following in respect of Mount View Court & Romney Close, to contribute to the delivery of housing in the borough: 1) approve the award of Contract; 2) the appropriation of the land for planning purposes under Section 122 of the Local Government Act (LGA) 1972; 3) to execute our rights under Section 203 of the Housing and Planning Act (HPA) to remove the risk of an injunction being served which could stop the development proceeding.
Minutes:
The Cabinet Member for Housing and Estate Renewal introduced the report which sought approval to appoint the recommended contractor, NFC Homes Limited, to complete a new build development of seven Council rented homes: three at Romney Close N17 and four at Mount View Court N8, and to appropriate the land for planning purposes to facilitate the development process.
The Cabinet Member highlighted that this decision was responding to the need for housing with more than 2 bedrooms. There would be three two-bedroom homes, including one that is accessible for wheelchair-users, in Northumberland Park, and four four-bedroom homes in Harringay.
Further to considering exempt information,
RESOLVED
Reasons for decisions
The two sites, Romney Close and Mountview Court, were approved by Cabinet on 9 July 2019 to be included in the Council housing delivery programme. These schemes have subsequently been granted planning consent and are ready to progress to construction. This report therefore marks the third, and final, Member led decision to develop these two sites.
Following a formal tender process, a contractor has been identified to undertake these works.
The appropriation of the two sites for planning purposes is required as it will allow the Council to use the powers contained in section 203 to override easements and other rights of neighbouring properties and will prevent injunctions that could delay or prevent the Council’s proposed developments. Section 203 converts the right to seek an injunction into a right to compensation. Both sites will need to be appropriated back from planning purposes to housing purposes on completion of the development to enable the Council to use the land for housing and let seven new Council homes at Council rent.
The new development at Romney Close will also allow the Council to secure the boundary of the site and improve security for new and existing residents, alleviating the anti-social behaviour currently attracted to the site.
This decision is also necessary at this time to support the Council’s COVID-19 response, in as much as it will be part of a portfolio of oven-ready schemes that are ready to go onsite as soon as the lockdown rules allow – supporting the recovery of the local and wider economy.
Alternative options considered
It would be possible not to develop these sites for housing purposes. However, this option was rejected as it does not support the Council’s commitment to deliver a new generation of Council homes.
This opportunity was procured via a direct appointment from the London Construction Programme (LCP) Major Works 2019 Framework Agreement, the recommended route for a contract of this value. An alternative option would have been to run a competitive tender from the LCP, but this option was rejected due to limited interest from the framework contractors.
The Council could continue with the schemes without appropriating the site for planning purposes, but this would risk the proposed developments being delayed or stopped by potential third party claims. By utilising the powers under Section 203 of the Housing and Planning Act 2016 (HPA 2016), those who benefit from third party rights will not be able to seek an injunction since those rights or easements that are overridden are converted into a claim for compensation only. The Council recognises the potential rights of third parties and will pay compensation where a legal basis for such payments is established. The housing delivery team actively engaged with local residents about the development of these sites as they proceeded through the feasibility and design stages and any comments or objections raised were taken into consideration by Planning Committee in reaching its decision. For these reasons, this option was rejected.
The Council could decide not to appropriate the land at both sites for housing purposes upon practical completion of the building works. This option was rejected because it could prevent the Council from being able to offer up these homes for occupation as social housing thereby not supporting the delivery of much needed affordable homes.
Supporting documents: