The Cabinet Member for Housing
and Estate Renewal introduced this report which sought approval for
additional funding for variations to the Broadwater Farm District
Heating contract which was approved by Cabinet on 14 August
2018.
The Cabinet Member noted that
since the health and safety issues at Broadwater Farm became known,
the Council had taken action to manage the risks and ensure the
safety of residents. This included the replacement of all gas
cookers, estate wide door knocking and engagement, the fitting of
gas interrupter valves and the decant of two blocks. This report
related to the ongoing works to install a new modern District
Heating system on the estate. Since the inception of the project,
officers had identified a number of enhancements to the programme
to improve outcomes for residents and the quality of the upgraded
heating system. These are detailed at paragraph 6.7. This report
sought to extend the existing contract to allow for these
additional works to be completed.
In response to questions from
Cllr Connor, the following information was provided:
- The decant of
Northolt block had started but completion would not be according to
the same level of urgency as Tangmere.This was due to there being
no piped gas in this block
- Disruption to
residents was acknowledged by the Cabinet Member. This was further
acknowledged to be a really challenging time for residents in
Broadwater Farm with different works taking place at the same time.
The Council were regularly exchanging information with residents
and making sure information was available on the works and their
impact. Ultimately, the Council had to ensure all the tenants were
living in safe homes. There was a need to be realistic with
residents about the scale and timing of the works. In particular
the enhancing works being completed on the heating systems was to
ensure that additional works were not needed in 10 years’
time.
- In relation to
thedecant at Tangmere Block, the latest information indicated that
there were 12 leaseholder remaining. Homes for Haringey had agreed
terms for moving 6 of the leaseholders. It was expected to agree
terms with the remaining 6 leaseholders.
- Thedecant of Northolt
Block had a longer timescale .This had started with 53 of 83
tenants moved or moving. There were 14 leaseholders, and Homes for
Haringey had agreed terms with 1 leaseholder .It was noted that
Homes for Haringey staff would be referring to the experience of
Tangmere leaseholder decant and were confident of making acceptable
housing offers to the remaining 13 leaseholders.
- Officers outlined
that the new heating supply also provided an opportune time to
replace some needed bathrooms and kitchens in Broadwater Farm. It
was noted that 260 out of 830 tenants would have brand new kitchens
or bathrooms or both by February 2020. The other works concerning
the district heating system were due to complete in November. A
further piece of work being included with the heating works, were
changes to the cold water supply so that there was a single
cold-water supply to people’s dwellings. These works would
have been needed to replace stored water supply in tanks in roofs.
Also fire stopping works had been the identified when completing
survey works for kitchens and bathrooms and these works had been
brought forward.
RESOLVED
- Toapprove the
variation of the District Heating
contract with Engie LTD (formerly Keepmoat LTD) of an additional
£5,531,172. More details of the variations required are set
out in section 6.7 of this report.
- To approve the
additional consultancy fees of £180k as set out in paragraph
10.1 in this report.
- To
agree not to seek to recharge leaseholders their proportion of the
cost of these works
Reasons for decision
The nine medium rise blocks on
Broadwater Farm (Croydon, Debden, Hawkinge, Hornchurch, Lympne,
Manston, Martlesham, Rochford and Stapleford) have failed
structural tests for Large Panel System buildings.
To mitigate the risks, Cabinet
gave authority to enter into the contract with the contractor on 14
August 2018. The work set out in the original contract was
established following structural surveys which identified that it
was not safe to have individual gas supplies within each flat on
Broadwater Farm.
The project was divided into
two substantive elements. Firstly, the Council was required to
remove all gas supplies from flats and replace them with a new
heating system by the end of October 2018. This deadline was set by
the statutory gas body, Cadent (who have statutory responsibility
for the provision of gas supplies) and required the switch over of
725 flats from gas to district heating over a six week period (this
deadline was met last year).
The second element of the
scheme was to complete the site wide distribution of the new energy
network and upgrade the energy centre, from which the new network
would be powered. The current forecast date of completion for this
element is November 2019.
Due to the time constraints,
officers focussed on developing a detailed strategic design for the
heating system in the absence of some survey data, such as survey
data within flats and survey data of the other mechanical and
electrical systems across the estate
Since the project has
commenced, a number of technical opportunities and constraints have
arisen which have allowed Homes for Haringey to amend its approach.
These have led to the variations in 6.7. The variations mean that
Homes for Haringey will be delivering additional works for
residents and reducing future disruption.
Alternative options considered
The option of
undertaking this work under a separate contract was considered but
was discounted on the basis that it would: -
- Prevent the technical
completion of the existing agreed district heating contract. For
example:
- Fire stopping in
flats is essential where compartmentation issues are
identified
- Renewal of floors
where they have collapsed is essential to upgrade kitchens and
bathrooms
- Renewal of kitchens
and bathrooms essential as re-piping of water pipes required
removal of units. Due to condition some units are impossible to
retrofit.
- Cost the
council considerably more to deliver if separated out into
different contracts. For example:
- Returning
to flats to complete kitchen and bathroom upgrades would require
additional visits from contractors which would be an additional
cost to the Council.
- Similarly,
returning to flats to upgrade water supplies to the bathrooms and
separate WCs would require additional visits from contractors which
would be an additional cost to the Council.
- Cause considerably
more disruption to residents if delivered through a separate
contract. For example:
- Doing as much work
inside people’s flats at the same time reduces the number of
visits required to people’s flats and the amount of
disruption each resident experiences. By upgrading all water
supplies, kitchens, bathrooms and WCs where necessary, we reducing
the number of times we are disrupting the residents.
- Returning
to flats to complete kitchen and bathroom upgrades would leave
residents without essential services for an unacceptable period of
time