Alexandra Court 122-124 High Road N22 6HE

Change of use of the second, third and fourth floors from B1 office to C1 hotel and roof top extension to create an additional floor. Works also include external refurbishment of existing and small extension into the car park on the second floor.

 

RECOMMENDATION: grant permission subject to conditions and subject to s106 Legal Agreement

Minutes:

The Committee considered a report on the application to grant planning permission for the change of use of the second, third and fourth floors from B1 office to C1 hotel and roof top extension to create an additional floor. Works also include external refurbishment of existing and small extension into the car park on the second floor. The report set out details of the proposal, the site and surroundings, planning history, relevant planning policy, consultation and responses, analysis, equalities and human rights implications and recommended to grant permission subject to conditions and subject to a s106 legal agreement.

 

The planning officer gave a short presentation highlighting the key aspects of the report. The Committee had approved a previous application for the hotel on 5 October, with the current application reflecting the incorporation of an additional floor to increase the number of bedrooms from 35 to 78. The attention of the Committee was drawn to a tabled addendum setting out an amendment to condition 8 and regarding the energy statement and carbon offsetting obligations.

 

The Committee raised the following points in discussion of the application:

·         Clarification was sought on the siting of the proposed extension. Officers advised that it would be located above the existing office space and above the top level of the car park.

·         In response to a question, the applicant advised that 12 parking spaces would be allocated to the second floor of the carpark for hotel guests.

·         The Committee sought assurance that consultation letters on the application had been sent to all residents of the Sky City housing estate. Officers confirmed that notification letters had been sent to the residential blocks on both sides of the High Road.

·         It was questioned why a revised application had been submitted so soon following approval of the original scheme. The applicant confirmed that the approved scheme was considered inefficient for a hotel operation due to the small number of bedrooms. It had taken time for a structural engineer to complete the necessary assessment of the loads to the buildings to support the additional roof top extension.

 

The Chair moved the recommendation of the report and it was

 

RESOLVED

·         That planning application HGY/2015/3255 be approved subject to conditions and subject to a s106 legal agreement.

 

1.   The development hereby authorised must be begun not later than the expiration of 3 years from the date of this permission, failing which the permission shall be of no effect.

Reason: This condition is imposed by virtue of the provisions of the Planning & Compulsory Purchase Act 2004 and to prevent the accumulation of unimplemented planning permissions.

 

2.   The development hereby authorised shall be carried out in accordance with the following approved plans and specifications:

150164(D)001, 002, 003, 004, 005, 006, 007A, 008, 009, 010, 011A, 012, 0123, 014C, 015, 016A, 017, 018A, 19D

Reason: In order to avoid doubt and in the interests of good planning.

 

3.   Notwithstanding the information submitted with this application, no development shall take place until precise details of the external materials to be used in connection with the development hereby permitted be submitted to, approved in writing by and implemented in accordance with the requirements of the Local Planning Authority and retained as such in perpetuity.

Reason: In order to retain control over the external appearance of the development in the interest of the visual amenity of the area and consistent with Policy SP11 of the Haringey Local Plan 2013 and Saved Policy UD3 of the Haringey Unitary Development Plan 2006.

 

4.   The applicant/developer is required to submit a Construction Management Plan (CMP) and Construction Logistics Plan (CLP) for the local authority's approval prior to construction work commencing on site. The Plans should provide details on how construction work (including any demolition) would be undertaken in a manner that disruption to traffic and pedestrians on Willoughby Road, Frobisher Road and the surrounding road network is minimised.  It is also requested that construction vehicle movements should be carefully planned and co-ordinated to avoid the AM and PM peak periods.

Reason: To reduce congestion and mitigate any obstruction to the flow of traffic on the transportation and highways network.

 

5.   The development hereby permitted shall not be commenced until detailed design, method statements and load calculations (in consultation with London Underground), have been submitted to and approved in writing by the local planning authority which provide details on all structures to accommodate the location of the existing London Underground structures and tunnels accommodate ground movement arising from the construction thereof and mitigate the effects of noise and vibration arising from the adjoining operations within the structures and tunnels.  The development shall thereafter be carried out in all respects in accordance with the approved design and method statements, and all structures and works comprised within the development hereby permitted which are required by the approved design statements in order to procure the matters mentioned in paragraphs of this condition shall be completed, in their entirety, before any part of the building hereby permitted is occupied.

Reason: To ensure that the development does not impact on existing London Underground transport infrastructure, in accordance with London Plan 2011 Table 6.1 and 'Land for Industry and Transport' Supplementary Planning Guidance 2012

 

6.   Prior to installation, details of the Ultra Low NOx boilers for space heating and domestic hot water are to be forwarded to the Local Planning Authority. The boilers to be provided for space heating and domestic hot water shall have dry NOx emissions not exceeding 20 mg/kWh.

Reason: To protect local air quality.

7.   Prior to commencement of the development, details of the CHP must be submitted to evidence that the unit to be installed complies with the emissions standards as set out in the GLA SPG Sustainable Design and Construction for Band B.

Reason:  To Comply with Policy 7.14 of the London Plan and the GLA SPG Sustainable Design and Construction.

 

8.   The development herby approved shall not be occupied until a final Certificate has been issued certifying that BREEAM (or any such equivalent national measure of sustainable building which replaces that scheme) ‘very good’ has been achieved for this development,

Reasons: To ensure that the development achieves a high level of sustainability in accordance with Policies 5.1, 5.2, 5.3 and 5.15 of the London Plan 2011 and Policies SP0 and SP4 the Haringey Local Plan 2013.

 

9.   The development hereby permitted shall be built in accordance with the energy and sustainability statements and the energy provision shall be thereafter retained in perpetuity, no alterations to the energy or sustainability measures shall be carried out without the prior approval, in writing, of the Local Planning Authority.

Reason: To ensure that a proportion of the energy requirement of the development is produced by on-site renewable energy sources to comply with Policy 5.7 of the London Plan 2011 and Policies SP0 and SP4 of the Haringey Local Plan 2013.

 

10.Prior to commencement of the development, save for stripping out the existing office, full details of the single plant room/energy centre, CHP and Boiler specifications, thermal store and communal network future proofing measures, including details of the safeguarded connection between the plant room and property boundary, should be submitted to and approved in writing by the Local Planning Authority.      

Reason: To ensure that the completed development is future proofed to enable connection to an area wide decentralised energy network to comply with Policies 5.5 and 5.6 of the London Plan 2011 and Policies SP0 and SP4 of the Haringey Local Plan 2013.

 

11.The design and installation of new items of fixed plant hereby approved by this permission shall be such that, when in operation, the cumulative noise level LAeq 15 min arising from the proposed plant, measured or predicted at 1m from the facade of nearest residential premises shall be a rating level of at least 5dB(A) below the background noise level LAF90. The measurement and/or prediction of the noise should be carried out in accordance with the methodology contained within BS 4142: 1997. Upon request by the local planning authority a noise report shall be produced by a competent person and shall be submitted to and approved by the local planning authority to demonstrate compliance with the above criteria.

Reason: In order to protect the amenities of nearby residential occupiers consistent with Policy 7.15 of the London Plan 2011 and Saved Policy UD3 of the Haringey Unitary Development Plan 2006.

 

12.                                                          No works shall be carried out on the site until a detailed Air Quality and Dust Management Plan (AQDMP), detailing the management of demolition and construction dust, has been submitted and approved by the LPA.  The plan shall be in accordance with the GLA SPG Dust and Emissions Control and shall also include a Dust Risk Assessment.  

Reason:  To Comply with Policy 7.14 of the London Plan

 

13. Prior to the commencement of any works the site or Contractor Company is to be registered with the Considerate Constructors Scheme.  Proof of registration must be sent to the LPA.

Reason:  To Comply with Policy 7.14 of the London Plan

 

Informatives:

 

INFORMATIVE 1: THE NPPF

In dealing with this application, Haringey Council has implemented the requirements of the National Planning Policy Framework and of the Town and Country Planning (Development Management Procedure) (England) (Amendment No.2) Order 2012 to foster the delivery of sustainable development in a positive and proactive manner.

 

INFORMATIVE 2: COMMUNITY INFRASTRUCTURE LEVY

Based on the information given on the plans, the Mayoral CIL charge will be £78,400 (2,240m2 x £35) and the Haringey CIL charge will be £0 (Hotels are charged at a NIL Rate). This will be collected by Haringey after/should the scheme is/be implemented and could be subject to surcharges for failure to assume liability, for failure to submit a commencement notice and/or for late payment, and subject to indexation in line with the construction costs index.

 

INFORMATIVE 3: Hours of Construction Work:

The applicant is advised that under the Control of Pollution Act 1974, construction work which will be audible at the site boundary will be restricted to the following hours:-

- 8.00am - 6.00pm          Monday to Friday

- 8.00am - 1.00pm          Saturday

- and not at all on Sundays and Bank Holidays.

 

INFORMATIVE 4: Party Wall Act:

The applicant's attention is drawn to the Party Wall Act 1996 which sets out requirements for notice to be given to relevant adjoining owners of intended works on a shared wall, on a boundary or if excavations are to be carried out near a neighbouring building.

 

INFORMATIVE 5: Thames Water- drainage

In respect of surface water it is recommended that the applicant should ensure that storm flows are attenuated or regulated into the receiving public network through on or off site storage. When it is proposed to connect to a combined public sewer, the site drainage should be separate and combined at the final manhole nearest the boundary. Connections are not permitted for the removal of groundwater. Where the developer proposes to discharge to a public sewer, prior approval from Thames Water Developer Services will be required. They can be contacted on 0800 009 3921.

 

INFORMATIVE 6:  WATER PRESSURE

Thames Water will aim to provide customers with a minum pressure of 10m head (approx. 1 bar) and a flow rate of 9 litres/minute at the point where it leaves Thames Waters pipes.  The developer should take account of this minimum pressure in the design of the proposed development.

 

INFORMATIVE 7: WASTE MANAGEMENT

Commercial Business must ensure all waste produced on site are disposed of responsibly under their duty of care within Environmental Protection Act 1990. It is for the business to arrange a properly documented process for waste collection from a licensed contractor of their choice. Documentation must be kept by the business and be produced on request of an authorised Council Official under section 34 of the Act. Failure to do so may result in a fixed penalty fine or prosecution through the criminal Court system. The business must ensure that all area around the site are managed correctly by the managing agent to keep areas clean of litter and detritus at all times.  The waste collection point will need to be at rear of the property from the service yard and will need to be accessible for refuse collection vehicles to enter and exit safely.

 

INFORMATIVE 8: ASBESTOS

Prior to demolition of existing buildings, an asbestos survey should be carried out to identify the location and type of asbestos containing materials. Any asbestos containing materials must be removed and disposed of in accordance with the correct procedure prior to any demolition or construction works carried out.

 