Variation of conditions to existing planning permission HGY/2009/0503 is now being sought as follows "Site Preparation Works" to include
demolition of (including the removal of the gas holders and remediation works but excluding the Olympia Trading Estate), surveys, site clearance, works of archaeological or ground investigations or remediation, the erection of fencing or hoardings, the provision of security measures or lighting, the erection of temporary buildings or structures associated with the Development, the laying, removal or diversion of services, construction of temporary access, temporary highway works, temporary estate roads and
erection of the "Pressure Reduction Stations" and variation of conditions to allow for such works to be carried out prior to the submission of detailed reserved matters applications and for phased submission of these reserved matters applications.
RECOMMENDATION: grant variation of conditions subject to referral to Mayor of London and conditions and s106 Legal Agreement
Minutes:
The Committee considered a report on the application to grant permission for variation of conditions to existing outline planning permission HGY/2009/0503 granted in March 2012 to allow a defined set of works known as ‘site preparation works’ to take place without triggering the requirement to submit all reserved details and completion of all s106 contributions. The report set out details of the proposal, the site and surroundings, planning history, relevant planning policy, consultation and responses, analysis, equalities and human rights implications and recommended to grant variation of conditions subject to referral to the Mayor of London and subject to conditions and a s106 legal agreement.
The planning officer gave a short presentation highlighting the key aspects of the report. It was emphasised that the details of the original scheme remained the same and that the merits of the proposal including the demolition of the gas holders could not be revisited at this stage. The Committee’s attention was drawn to a tabled addendum to the report setting out a number of proposed amendments to conditions and informatives and details of additional consultation responses received.
Members sought clarification on the reasons for the current application and concern over the risk in granting permission for site clearance to go ahead whilst full plans for the redevelopment of the site remained outstanding and in the absence of a confirmed developer. Officers confirmed that a guarantee could not be provided that the redevelopment scheme would go ahead but that allowing the site preparation works to go ahead would be pragmatic due to the complexity of the works required to clear the site and which in turn would make it more saleable.
A number of objectors addressed the Committee and raised the following points regarding the application:
· Concerns were expressed that the impact of the site preparation works on businesses located in the Olympia Trading Estate would be significant and that the applicant had not sufficiently assessed or shared appropriate details of the works with local businesses to allow for the consideration of mitigation measures. The potential health and safety risks to employees was of particular concern.
· It was considered that the applicant should be required to establish a liaison group to facilitate the sharing of information with local businesses and residents.
· There was a lack of reference in general within the application to businesses on the Olympia Trading Estate and Brook Road, with a number closest to the site appearing to have been omitted from the scope of the monitoring.
· It was considered that the historical and architectural merit of the gas cylinders located on the site had not been sufficiently recognised as a heritage asset and that instead of removal, a developer should be sought with the ability to integrate the holders within the future redevelopment scheme.
Officers reiterated that the decision regarding the removal of the gas holders could not be revisited under the current application and advised that a condition of the original permission was the historical documentation of the gas holders prior to demolition.
It was advised that the establishment and maintenance of a residents and businesses liaison group would be secured by condition, accompanied by an informative for the makeup of the group to be agreed in writing with the Council. Officers proposed an amendment to strengthen the condition to read ‘prior to submission to discharge of condition 22, for the duration of the development the applicant will establish and maintain a liaison group.......’ which was agreed.
Assurances were provided that condition 22 of the permission would require submission and approval of a Construction Environmental Management Plan for the site preparation works to ensure the amenities of local residents, businesses etc in the area during construction works. This aimed to address the concerns raised by the objectors regarding air and dust management, operating hours, noise and vibration control etc. The Olympia Trading Estate would fall within the scope of this Plan.
Representatives for the applicant, National Grid, addressed the Committee and raised the following points:
· Allowing the site preparation works would facilitate and speed up the regeneration of the site.
· The process for seeking a development partner to take the regeneration scheme forward would begin in the summer inline with the development of detailed plans for the scheme.
· Conditions attached to the permission would address the concerns of local people including businesses in the vicinity.
· Discussions were continuing with English Heritage regarding the historical importance of the gas holders, despite them twice being rejected for listed status.
· In response to a question regarding the decision to demolish the gas holders, it was advised that the shape of the steel frame and high costs of restoration precluded the incorporation of the cylinders within the scheme on the grounds of viability. In addition to the requirement for the gas holders to be documented prior to demolition, the applicant advised they would be willing to consider donating small pieces of the frame to any museum expressing an interest in their history.
· In response to the concern expressed by Members regarding the advancement of the site preparation works element of the scheme considering that no guarantee could be provided that the wider regeneration scheme for the site would come to fruition, the applicant confirmed that the undertaking of these works would constitute a significant investment into the scheme and speed up the wider regeneration project. In addition, the risk of the redevelopment scheme not going ahead would remain even if the site preparation works were not brought forward under the application.
The Committee agreed to the addition of an informative to encourage the applicant to explore the potential for reusing material from the gas holders.
The Chair moved the recommendation of the report including the proposed amendment to condition 68 and additional informative detailed above and it was
RESOLVED
· That permission be granted for planning application HGY/2013/2455 for the variation of conditions subject to referral to the Mayor of London, subject to conditions and a s106 legal agreement.
RESERVED MATTERS
1. The application is granted in OUTLINE, in accordance with the provisions of Regulations 3 & 4 of the Town & Country Planning (General Development
Procedure) 1995 and before any development with the exception of the Site
Preparation Works is commenced, the approval of the Local Planning Authority shall be obtained to the following reserved matters, namely: a) Scale (within parameter plan range (Drawing Ref: P003(REV06) – Maximum and Minimum Storey Heights); b) Layout c) Landscape and d) Appearance.
Reason: This condition is imposed by virtue of Section 92 of the Town & Country Planning Act 1990.
TIME LIMIT – RESERVED MATTERS
2. Application must be made to the Local Planning Authority for approval of any matters reserved in this OUTLINE planning permission not later than the expiration of 5 years from the date of this Permission, and the development hereby authorised shall be started not later than whichever is the later of the following dates, failing which the permission shall be of no effect:
a. the expiration of 5 years from the date of this permission; or
b. the expiration of 2 years from the final date of approval of any of the reserved matters.
Reason: To comply with the provision of Section 92(2) of the Town and Country Planning Act 1990.
IN ACCORDANCE WITH APPROVED PLANS
3. The development hereby authorised shall be carried out in complete accordance with the plans and specifications (except for the Design and Access Statement which is for illustrative purposed only) submitted to, and approved in writing by the Local Planning Authority.
PHASING PROGRAMME
4. No development with the exception of the Site Preparation Works shall take
place until a programme of phasing for implementation of the whole development has been agreed in writing by the Local Planning Authority. Any amendment to the approved phasing programme must be first agreed in writing by the Local Planning Authority.
Reason: To ensure satisfactory comprehensive development within a reasonable timescale and proper planning of the area.
MATERIALS
5. At the reserved matters stage, full details of the external appearance of the
development, including samples of all materials to be used for all external facing surfaces and roofing materials for each phase of the development, as set out in an agreed phasing plan, shall be submitted to, and approved in writing by, the Local Planning Authority before any development is commenced on that phase. Samples shall include sample panels in addition to a schedule of the exact product references. All approved materials shall be erected in the form of a samples board and shall be retained on site throughout the works period for the phase concerned. Thereafter only such approved materials and finishes shall be used in carrying out the development.
Reason: To ensure a comprehensive and sustainable development and to achieve good design throughout the development.
MAXIMUM BUILDING HEIGHTS
6. The maximum height of the proposed development, including lift overruns,
rooftop plant etc, shall be no greater than indicated on the parameter plan Drawing Number P003(REV06) – Maximum and Minimum Storey Heights.
Reason: In order to ensure the development is carried out in accordance with the approved details and in the interests of amenity.
MAXIMUM DWELLING NUMBERS
7. The outline planning permission hereby approved for a residential-led mixed use development shall not exceed 1080 separate dwelling units, whether flats or houses. The dwelling mix shall be approved in writing by the Local Planning Authority in consultation with the Greater London Authority, prior to commencement of the development with the exception of the Site Preparation Works.
Reason: To ensure a comprehensive and sustainable development in order to
control the overall density levels within the development.
ACCESSIBILITY AND LIFETIME HOMES
8. Within the development hereby approved, at least 10% of the dwellings shall be wheelchair accessible or easily adaptable for residents who are wheelchair users. This percentage should be applied to both market and affordable housing, should be evenly distributed throughout the development, and cater for a varying number of occupants. In addition, 100% of the dwellings shall be built to meet Lifetime Homes standards, unless otherwise agreed in writing by the Local Planning Authority. Evidence of compliance with the above shall be submitted to and approved in writing by the Local Planning Authority, prior to the commencement of each phase of the development comprising dwellings.
Reason: In order to ensure adequate accessibility for the disabled and mobilityimpaired throughout their lifetime.
HOUSING DESIGN STANDARDS
9. The development shall comply with the London Plan (2011) Policy 3.5 and
London Housing Supplementary Planning Guidance 2012 space standards and as far as practical shall meet all other requirements within the London Housing Supplementary Planning Guidance 2012, particularly the requirements dual aspect units.
Reason: In order to ensure a satisfactory standard of accommodation for future occupiers of the development.
LANDSCAPING – LANDSCAPING SCHEME
10. At the reserved matters (excluding the reserved matters for the utility
compounds as shown on plan P006/05) stage, full landscaping scheme for the entire site shall be submitted to and approved in writing by the Local Planning Authority a scheme for landscaping, which shall include a) those existing trees to be retained; b) those existing trees to be removed; c) those new trees and shrubs to be planted together with a schedule of species d) roof top gardens/allotments/amenity space e) hard surfacing f) boundary treatment e) street furniture. At the reserved matters stage for the utility compounds, as shown on Plan P006/05, a landscaping scheme to be submitted to the Local Planning Authority for approval which shall include details of the interim landscaping scheme for the utility compounds as shown on plan P006/05.
Reason: To enhance the appearance of the development and in the interest of safeguarding the amenities of residents in the area.
LANDSCAPING – IMPLEMENTATION/MAINTENANCE
11. All landscaping and ecological enhancement works, including planting, seeding or turfing comprised in the approved scheme of landscaping as described in condition “Landscaping – Landscaping Scheme” shall be completed no later than the first planting and seeding seasons following the occupation of the building or the completion of the development in each phase, whichever is the sooner. Any trees or plants which within a period of FIVE years from the completion of that phase of development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species. The landscaping scheme, once implemented, is to be maintained and retained thereafter to the satisfaction of the Local Planning Authority save that the interim landscaping scheme for the for the utility compounds, as shown on Plan P006/05 referred to in Condition 10, shall be replaced in accordance with the landscaping scheme. All hard landscaping and means of enclosure shall be completed before the development is occupied.
Reason: To enhance the appearance of the development in the interest of the visual amenities of the area.
LANDSCAPING – PROTECTION OF EXISTING TREES
12. No development shall commence until an Arboricultural method statement, including a tree protection plan, has been prepared in accordance with BS5837:2005 Trees in Relation to Construction”, and approved by the Local Planning Authority. A pre-commencement site meeting must be specified and attended by all interested parties, (Site manager, Consultant Arboriculturalist, Council Arboriculturalist and Contractors) to confirm all the protection measures to be installed for trees. Robust protective fencing / ground protection must be installed prior to commencement of construction activities on site and retained until completion. It must be designed and installed as recommended in the method statement. The protective fencing must be inspected by the Council Arboriculturalist, prior to any works commencing on site and remain in place until works are complete.
Reason: To protect the trees which are to be retained and in the interest of the visual amenities of the area.
JAPANESE KNOTWEED
13. Prior to the commencement of the development, a detailed method statement for the removal or long-term management/eradication of Japanese knotweed on the site shall be submitted to and approved in writing by the local planning authority. The method statement shall include proposed measures to prevent the spread of Japanese knotweed during any operations such as mowing, trimming or soil movement. It shall also contain measures to ensure that any soils brought to the site are free of the seeds / root / stem of any invasive plant covered under the Wildlife and Countryside Act 1981. Development shall proceed in accordance with the approved method statement. Please note that if any of the Japanese knotweed plants are close to water, including watercourses, ditches or standing water, then Environment Agency consent is required if it is to be treated with a herbicide.
Reason: In order to ensure the eradication of Japanese Knotweed which is an
invasive plant and the spread of which is prohibited under the Wildlife and
Countryside Act 1981.
BOUNDARY TREATMENT
14. Notwithstanding the details contained within the plans hereby approved, full details of boundary treatments, including fencing and gates, to the entire site be submitted to and approved by the Local Planning Authority prior to the
commencement of the development.
Reason: In order to safeguard the visual amenity of the area and to ensure adequate means of enclosure for the proposed development.
ECOLOGICAL MANAGEMENT
15. The development hereby approved shall not commence with the exception of the Site Preparation Works until full details of a site wide Ecology Management Strategy including an Ecological Mitigation and Management Plan which shall provide details of how the proposed measures will be monitored, managed and funded in the future, has been submitted to and approved in writing by the Local Planning Authority.
Reason: In order to ensure that the proposed development maximises the
ecological potential of the site
POLLUTION PREVENTION
16. The development hereby approved shall not commence until full details of a site wide Pollution Prevention Strategy has been submitted to and approved in writing by the Local Planning Authority.
Reason: In order to ensure that the proposed development prevents pollution of the environment.
CONTAMINATED LAND – VERIFICATION REPORT
17. No phase of the development shall not be occupied or brought into use until verification by a competent person approved under the provisions of Condition “Contaminated Land – Remediation Strategy” that any remediation scheme required for that phase and approved under the provisions of the above condition has been implemented fully in accordance with the approved details, shall be submitted to and approved by the Local Planning Authority. Unless otherwise agreed in writing by the Local Planning Authority such verification shall comprise: (a) as built drawings of the implemented scheme; (b) photographs of the remediation works in progress; and (c) certificates demonstrating that imported and/or material left in situ is free from contamination. Thereafter the scheme shall be monitored and maintained in accordance with the scheme approved under Condition “Contaminated Land – Remediation Strategy”.
Reason: To safeguard the health of future residents or occupiers of the site.
USE OF CLEAN UNCONTAMINATED MATERIAL
18. No soils or infill materials shall be imported onto the site until it has been
satisfactorily demonstrated that they present no risk to human health and the
environment. Documentary evidence to confirm the origin of all imported soils and infill materials, supported by appropriate chemical analysis, test results, shall be submitted to and approved by the Local Planning Authority prior to that import. The import on site of material classified as ‘waste; is only acceptable with the prior written approval of the Local Planning Authority.
Reason: To ensure that no contaminated land is brought on site.
METHOD OF PILING
19. No phase of the development hereby approved (including the Site Preparation Works) shall commence until the method of piling foundations for that phase of development for the development has been submitted to and approved in writing by the Local Planning Authority prior to any development commencing. Piling or any other foundation designs using penetrative methods shall not be permitted except for those parts of the site where it has been demonstrated that there is no resultant unacceptable risk to groundwater. The development shall be carried out in accordance with the approved details.
Reason: To prevent the contamination of the underlying aquifer.
ARCHAEOLOGICAL WATCHING BRIEF
20. No development shall take place within the application site until the applicant has secured the implementation of an archaeological watching brief and a programme for the recording of built heritage structures, including the existing gas holders, in accordance with a written scheme of investigation which has been submitted to and approved in writing by the Local Planning Authority.
Reason: To ensure that archaeological remains on the site shall be adequately investigated and recorded during the course of the development and the findings of such investigation and recording reported
HOARDINGS
21. Prior to the commencement of development full details of a scheme for the provision of hoardings around the site during the construction period including details of design, height, materials and lighting shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of the works and unless otherwise agreed in writing by the Local Planning Authority. The development shall be carried out only in accordance with the scheme as approved.
Reason: In order to have regard to the visual amenity of the locality an the amenities of local residents, businesses, visitors and construction sites in the area during construction works.
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
22. No phase of the development hereby approved shall commence until a
Construction Environmental Management Plan, including Site Waste Management Plan, Site Management Plan, Construction Logistics Travel Plan, construction traffic management plan (CTMP) has been submitted to and approved in writing by the Local Planning Authority for the relevant phase. The Construction Management Plan shall include but not be limited to the following: a) Public Safety, Amenity and Site Security; b) Operating Hours, Noise and Vibration Controls; c) Air and Dust Management; d) Storm water and Sediment Control and e) Waste and Materials Reuse. The Site Waste Management Plan will demonstrate compliance with an appropriate Demolition Protocol. The development shall be carried out in accordance with the approved details. Additionally the site or Contractor Company must be registered with the Considerate Constructors Scheme. Proof of registration
must be sent to the LPA prior to any works being carried out on the site.
Reason: In order to have regard to the amenities of local residents, businesses, visitors and construction sites in the area during construction works.
CONSTRUCTION DUST MITIGATION
23. No phase of the development shall commence until the appropriate mitigation measures to minimise dust and emissions are incorporated into the phase specific Construction Environmental Management Plan based on the Mayor’s Best Practice Guidance (The control of dust and emissions from construction and demolition). This should include an inventory and timetable of dust generating activities, emission control methods and where appropriate air quality monitoring). This must be submitted to and approved in writing by the LPA prior to any works carried out in the relevant phase. Additionally the site or Contractor Company must be registered with the Considerate Constructors Scheme. Proof of registration must be sent to the LPA prior to any works being carried in the relevant phase.
Reason: To protect the environment and amenities of the locality.
CONSTRUCTION HOURS
24. Operations in relation to construction for which noise is greater than 50dBLAeq, 1hour at the nearest residential boundary shall be restricted to the hours of 0800 and 1800 on Mondays to Fridays and between 0800 and 1300 on Saturdays and at no time on Sundays or Statutory holidays without the prior written approval of the Local Planning Authority under Section 61 of the Control of Pollution Act 1974. The following enabling activities shall be permitted to take place within a period one hour before and one hour after normal working hours:
• Arrival and departure of workforce on site;
• Deliveries and unloading;
• Check and examinations of plant and machinery (including test running) and the carrying out of essential repairs / maintenance to plant and machinery;
• Site inspections and safety checks; and
• Site clean-up
Reason: To ensure that the development does not prejudice the enjoyment of
neighbouring occupiers of their properties.
CONSTRUCTION – ON-SITE CONTACT
25. At the time of the commencement of works, an onsite contact shall be
provided on a 24 hour per day basis for residents to report any disturbances or issues arising from the construction of the site
Reason: To ensure that any disruption to neighbouring residents can be reported immediately.
CCTV AND SECURITY LIGHTING
26. At the reserved matters stage for each phase, a scheme showing full details of the following for that phase shall be submitted to and approved in writing by the Local Planning Authority.
a) CCTV;
b) Security lighting
Reason: In order to ensure that the proposed development achieves the safer
places attributes as detailed by Planning Policy Statement 1: Safer Places: The Planning System & Crime Prevention and to prevent crime and create safer, sustainable communities and in order to ensure the location of CCTV protects the privacy of neighbouring residential properties.
EXTERNAL LIGHTING STRATEGY
27. At the reserved matters stage for each phase, an external lighting strategy for that phase of the development shall be submitted to and approved in writing by the Local Planning Authority. The details of the external lighting for each phase shall be in accordance with the approved strategy.
Reason: In order to ensure that the proposed development achieves the safer
places attributes as detailed by Planning Policy Statement 1: Safer Places: The Planning System & Crime Prevention and to prevent crime and create safer, sustainable communities
SURFACE WATER DRAINAGE
28. At the reserved matters stage for each phase, details of a scheme for the
surface water drainage works including the provision of a Sustainable Urban
Drainage System shall be submitted to and approved by the Local Planning
Authority (in consultation with Thames Water) prior to the commencement of works within that part of the site. The surface water drainage details shall include that petrol/oil interceptors shall be fitted in all car parking/washing/repair facilities and an Impact Study of existing Sewerage infrastructure.
Reason: In order to ensure the satisfactory surface water drainage of the site.
WATER SUPPLY IMPACT STUDY
29. At the reserved matters stage for each phase, a Water Supply Impact Study for that phase of the development, including full details of anticipated water flow rates, and detailed site plans shall be submitted to, and approved in writing by the Local Planning Authority (in consultation with Thames Water).
Reason: To ensure that the water supply infrastructure has sufficient capacity to cope with the additional demand
WASTE STORAGE AND RECYCLING
30. At the reserved matters stage, (excluding the reserved matters for the utility compounds as shown on Plan P006/05) details of the arrangements for storage and collection of refuse for each phase of the development, including location, design, screening, operation and the provision of facilities for the storage of recyclable materials shall be submitted to and approved in writing by the Local Planning Authority and the development shall be carried out only in accordance with the details so approved and shall be permanently retained thereafter.
Reason: To ensure good design, to safeguard the amenity of the area and ensure that the development is sustainable and has adequate facilities for the storage of waste and recyclable materials.
BREEAM – DESIGN STAGE ASSESSMENT
31. The development hereby permitted shall be built to a minimum standard of
“Very Good” under the Building Research Establishment Environmental Assessment Method (BREEAM). A BREEAM design stage assessment shall be submitted to the Local Planning Authority prior to the commencement of construction on the site except the utility compounds as shown on Plan P006/05. The BREEAM design stage assessment will be carried out by a licensed assessor.
Reason: To ensure that development takes place in an environmentally sensitive way.
BREEAM CERTIFICATE
32. The development hereby permitted shall be built to a minimum standard of
“Very Good” under the Building Research Establishment Environmental Assessment Method (BREEAM). Within THREE months of the occupation of the completed development, a copy of the Post Construction Completion Certificate for the relevant building verifying that the “Very Good” BREEAM rating has been achieved shall be submitted to the Local Planning Authority. The Certificate shall be completed by a licensed assessor.
Reason: To ensure that development takes place in an environmentally sensitive way.
TRANSPORTATION – S72 AGREEMENT
33. The developer will we required to dedicate a 3m strip of land by way of a
section 72 agreement along Mary Neuner Road to construct the proposed vehicular inset parking as per Drawings No’s 0083-B-23 and 0083-B-24 as submitted by the applicant’s consultant Savell Bird and Axon.
Reason: Ensure safe and efficient vehicle access.
TRANSPORTATION – PARKING PROVISION
34. The applicant shall provide 23 per cent (276 car spaces) parking provision for the residential component of the development, including 60 disabled spaces.
Reason: To ensure appropriate levels of car parking within the development.
TRANSPORTATION – PARKING PROVISION – ELECTRIC VEHICLES
35. At the reserved matters stage (excluding the reserved matters for the utility compounds as shown on Plan P006/05), details of electric vehicle provision within the parking areas (which shall include a minimum of 20 per cent of all parking spaces and an additional 20 per cent passive provision for electric vehicles in the future) shall be submitted to an approved in writing by the Local Planning Authority.
Reason: In order to ensure adequate provision of electric vehicle infrastructure within the development.
TRANSPORTATION - CYCLE PARKING
36. At the reserved matters stage (excluding the reserved matters for the utility compounds as shown on Plan P006/05) a detailed plan for cycle parking which shall include a) 1 cycle rack per residential unit; b) 50 cycle spaces for the shop/office/community aspects of the development (36, 4 and 10 cycle spaces correspondingly) and c) secure shelters, shall be submitted to and approved in writing by the local planning authority.
Reason: In order to ensure adequate provision of safe and secure cycle parking.
TRANSPORTATION – TRAVEL PLAN AND CAR CLUB
37. At the reserved matters stage (excluding the reserved matters for the utility compounds as shown on Plan P006/05), Travel Plans and welcome pack, in compliance with Transport for London Guidance, shall be submitted to and approved in writing by the local planning authority, at least 3 months in advance of occupation of each phase of the development (excluding the occupation of the utility compounds as shown on Plan P006/05). The Car Club scheme and number of onsite Car Club car parking spaces to be agreed as part of the Travel Plan.
Reason: In order to encourage the use of sustainable modes of transport for
journeys to/from the site.
DETAILS OF FLUES
38. Within each phase full details of the location and appearance of any flues,
including height, design, location and sitting shall be submitted and approved in writing by the Council before work commences on that phase.
Reason: To ensure a comprehensive and sustainable development and to achieve good design through the development.
COMMERCIAL PREMISES – ACCESS
39. The commercial premises shall be minimum door widths of 900mm and a
maximum threshold of 25mm to allow access to people with disabilities and people pushing double buggies.
Reason: In order to ensure that the premises are accessible to all those people who could be expected to use it, in accordance with policy RIM 2.1 “Access for All” of the Haringey Unitary Development Plan (2006).
SHOPFRONTS
40. Within each phase detailed plans of the design and external appearance of the shopfronts, including detailed design of the fascias, shall be submitted to and approved in writing by the Local Planning Authority at the reserved matters stage.
Reason: In the interest of visual amenity.
SIGNAGE
41. Prior to the commencement of the use, precise details of any signage proposed as part of the development shall be submitted to and approved in writing by the local planning authority.
Reason: to achieve good design throughout the development and to protect the visual amenity of the locality.
HOURS OF OPERATION – A3, A4 and A5 Uses
42. Any restaurant (A3), public house and wine bar (A4) or takeaway (A5) use shall not be operated before 0800 or after 2400 hours on any day of the week.
Reason: In order to ensure that the proposed development does not prejudice the amenities of the future occupiers of the development.
ENVIRONMENT AGENCY – STRUCTURAL SURVEY
43. The development hereby permitted shall not be commenced until such time as a structural survey of the Moselle Brooke culvert to identify the life of the flood defences compared to the life of the development has been submitted to, and approved in writing by, the local planning authority. If the assessment identifies that the life of the culvert is not commensurate with the life of the development, then a scheme of remedial measures shall be submitted to and approved in writing by the Local Planning Authority before development commences. Development shall proceed only in accordance with the approved remedial measures.
Reason: To ensure that the flood defences have a life commensurate with the life of the development in order to safeguard the development and area from the risk of flooding.
ENVIRONMENT AGENCY – FLOOD RISK ASSESSMENT
44. The development permitted by this planning permission shall only be carried out in accordance with the approved Flood Risk Assessment (FRA) Waterman Group (C-37407-10-ES-002 Rev: A05 February 2009) and the following mitigation measures detailed within the FRA:
• Limiting the surface water run-of generated so that it will not exceed a run-off rate of 17.7ls/ha from the site and not increase the risk of flooding off-site.
• Provision of attenuation of surface water on site through the use of SUDS systems including living roofs, permeable paving and a swale and the use of storage tanks.
• Building and structures on site to be set a minimum of 8m back from the outer culvert wall of the Moselle Brook.
Reason: To prevent flooding by ensuring the satisfactory storage of/disposal of surface water from the site and to ensure the structural integrity of and access to existing flood defences thereby reducing the risk of flooding.
ENVIRONMENT AGENCY – SITE INVESTIGATION AND CONTAMINATED LAND
45. Prior to the commencement of development approved by this planning
permission (or such other date or stage in development as may be agreed in writing by the Local Planning Authority), the following components of a scheme to deal with the risks associated with contamination of the site shall each be submitted to and approved, in writing, by the local planning authority:
1) A preliminary risk assessment which has identified:
• All previous uses
• Potential contaminants associated with those uses
• A conceptual model of the site indicating sources, pathways and receptors
• Potentially unacceptable risks arising from contamination at the site
2) A site investigation scheme, based on (1) to provided information for a detailed assessment of the risk to all receptors that may be affected, including those off site.
3) The site investigation results and the detailed risk assessment (2) and, based on these, an options appraisal and remediation strategy giving full details of the remediation measures required and how they are to be undertaken.
4) A verification plan providing details of the data that will be collected in order to demonstrate that the works set out in (3) are complete and identifying any
requirements for longer-term monitoring of pollutant linkages, maintenance
arrangements for contingency action. Any changes to these components require the express consent of the local planning authority. The scheme shall be implemented as approved.
Reason: There are controlled water bodies at, and in the vicinity of the proposed development site, which could be polluted by the known soil and shallow (perched) groundwater contamination which exists at the site. The identified Controlled Water bodies are the Moselle Brook, the New River, the reservoirs to the west and the deeper groundwater system that underlies the site. The deeper groundwater and the New River are used to supply drinking water to the public and therefore must be kept free from pollution. The Moselle Brook which flows through the site in culvert flows into Pymmes Brook to the east. If pollution were to enter the brook it would have a detrimental impact on aquatic life in the brook and also to its aesthetic appeal. As such, site investigation is required to assess the risk that the contamination at the site poses to Controlled Waters. Note: The information provided to the Environment Agency in the report titled 'Environmental Statement' which was prepared by Waterman Energy, Environment & Design and dated February 2009 (Ref EN6847/R/2.1.1/MN) is sufficient to satisfy Part 1 of this condition. Also, part of the site has previously been investigated and remediated to an acceptable standard with regards to any risk posed to Controlled Waters. This area is referred to as the Spine Road and is detailed in Celtic Technologies report titled 'Haringey Heartlands Spine Road Improvement Corridor - Factual Validation Report' dated October 2008 (Ref R1199/08/3325). The above recommended condition is not applicable to this part of the site.
ENVIRONMENT AGENCY – PILING
46. Pilling or any other foundation designs using penetrative methods shall not be permitted other than with the express written consent of the Local Planning Authority, which may be given for those parts of the site where it has been demonstrated that there is no resultant unacceptable risk to groundwater. The development shall be carried out in accordance with the approved details.
Reason: Piled foundations are proposed to facilitate development at the site.
The advancement of such foundations through contaminated material, which is known to be present in the soil and shallow (perched) groundwater at the site, has the potential to mobilise contaminants and result in their release into the deeper groundwater system. The deeper groundwater underlying the site is abstracted a short distance from the site and is used to supply drinking water to the public. Therefore, it is very important that a suitable piling design and methodology is used as to not to pollute the deeper groundwater system below the site.
ENVIRONMENT AGENCY – LANDSCAPE MANAGEMENT PLAN
47. Prior to the commencement of development (excluding Site Preparation Works) a landscape management plan, including long term design objectives, management responsibilities and maintenance schedules for all landscaped areas (except privately owned domestic gardens), shall be submitted to and approved in writing by the Local Planning Authority. The landscape management plan shall be carried out as approved.
Reason: This condition is necessary to protect the natural features and character of the area and identify opportunities for enhancement of biodiversity.
ENVIRONMENT AGENCY – PLANTING
48. Planting all landscaped areas (except privately owned domestic gardens but including green roofs) shall be of locally native plant species only, of UK genetic origin.
Reason: The use of locally native plants in landscaping is essential to benefit local wildlife and to help maintain the region's natural balance of flora. Native insects, birds and other animals cannot survive without the food and shelter that these plants provide. Introduced plants usually offer little to our native wildlife. Local plants are the essence of regional identity and preserve the character of the British landscape. Local plants are adapted to local soils and climate, so have low maintenance requirements. In addition, planting locally native plants helps to prevent the spread of invasive plants in the region.
ENVIRONMENT AGENCY – FOUL AND CONTAMINATED WATER
49. Before the commencement each phase of the development, including
demolition, remediation and construction, a scheme to manage surface, foul and contaminated water on the site for that phase will be submitted to, and approved in writing by, the local planning authority. Each scheme shall be implemented as approved the Environment Agency asks to be consulted before approval.
Reason: To prevent the pollution of local surface and ground-waters and protect potable water supplies in the area.
NETWORK RAIL – DEVELOPMENT
50. Prior to the commencement of any works on site, developers must contact
Network Rail to inform them of their intention to commence works. This must
be undertaken a minimum of 6 weeks prior to the proposed date of
commencement.
Reason: It is useful for Network Rail to inform drivers, maintenance, signallers and any other railway personnel involved in the operation of the railway of development occurring adjacent to the operational railway.
NETWORK RAIL – DEMOLITION
51. Any demolition of refurbishment works must not be carried out on the
development site that may endanger the safe operation of the railway, the stability of the adjoining Network Rail structures.
Reason: To ensure that the railway is not damaged during demolition.
NETWORK RAIL – CONSTRUCTION
52. Any scaffold, cranes or other mechanical plant must be constructed and
operated in a “fail safe” manner that in the event of mishandling, collapse or failure, no materials or plant are capable of falling within 3.0m of the nearest rail of the adjacent railway line, or where the railway is electrified, within 3.0m of overhead electrical equipment or supports. To avoid scaffold falling onto operational lines, netting around the scaffold may be required. In view of the close proximity of these proposed works to the railway boundary the developer should contact Network Rail’s Outside Parties Engineer on opsoutheast@networkrail.co.uk before any works begin. Any scaffold which is to be constructed within 10 metres of the railway boundary fence must be erected in such a manner that at no time will any poles over-sail the railway and protective netting around such scaffold must be installed. Where vibro-compaction machinery is to be used in development, details of the use
of such machinery and a method statement should be submitted for the approval of the Local Planning Authority acting in consultation with the railway undertaker prior to the commencement of works and the works shall only be carried out in accordance with the approved method statement.
Reason: To ensure railway infrastructure is not damaged during construction.
NETWORK RAIL – SITE LAYOUT
53. Any proposed buildings shall be at least 2 metres from the boundary with the operational railway, at least 5 metres from overhead power lines, or 3 metres from viaducts.
Reason: This will allow construction and future maintenance to be carried out from the application land, thus avoiding provision and costs of railway look-out
protection, supervision and other facilities necessary when working from or on
railway land.
NETWORK RAIL – NOISE AND VIBRATION
54. The potential for any noise/vibration impacts caused by the proximity between the proposed development and any existing railway must be addressed in the context of PPG24 and the local planning authority should use conditions as necessary. Consideration should be given to the need to provide for on-site residential amenity within the development site.
Reason: To mitigate noise and vibration from operational land.
NETWORK RAIL – FENCING
55. This development will create a trespass and vandalism risk on to the railway. In the interests of promoting public safety, before any part of the development (except the utility compounds as shown on Plan P006/05) is occupied, a 1.8 metre high trespass resistant fence should be erected. The new fencing provided must be independent of existing Network Rail fencing and a sufficient distance should be allowed between the fences to allow for future maintenance and renewal.
Reason: To prevent trespass.
NETWORK RAIL – DRAINAGE
56. No water or effluent should be discharged from the site or operations on the site into the railway undertaker’s culverts or drains. Details of the proposed drainage must be submitted to, and approved by the Local Planning Authority, acting in consultation with the railway undertaker, and the works shall be carried out in accordance with the approved details.
Reason: To ensure the operation of the railway.
SECURE BY DESIGN
57. The development hereby authorised shall comply with BS 8220 (1986) Part 1 'Security Of Residential Buildings' and comply with the aims and objectives of the Police requirement of 'Secured By Design' and 'Designing Out Crime' principles.
Reason: In order to ensure that the proposed development achieves the required crime prevention elements as detailed by Circular 5/94 'Planning Out Crime'.
SITE PARKING MANAGEMENT PLAN
58. That details of onsite parking management plan shall be submitted to and
approved by the local planning authority prior to the commencement of the use of the undercroft car parking area. Such agreed plan to be implemented and permanently maintained in operation to the satisfaction of the Local Planning Authority.
Reason: In order to ensure that the proposed development does not prejudice the free flow of traffic or the conditions of general safety along the neighbouring highway.
SATELLITE AERIALS
59. Notwithstanding the provisions of Article 4 (1) and Part 25 of Schedule 2 of the General Permitted Development Order 1995, at the reserved matters stage (excluding the reserved matters for the utility compounds as shown on Plan P006/05), details of a scheme for satellite dish/aerials shall be submitted to and approved by the Local Planning Authority prior to the occupation of the property in the relevant phase, and the approved scheme shall be implemented and permanently retained thereafter.
Reason: In order to prevent the proliferation of satellite dishes on the development.
OPEN SPACE MANAGEMENT PLAN
60. That details of a management plan for the management and maintenance of the public and communal open spaces including roof top gardens, allotments, and children’s play spaces shall be submitted to and approved by the Local Planning Authority prior to the occupation of the residential units such agreed details to be implemented and maintained thereafter to the satisfaction of the Local Planning Authority.
Reason: In order to ensure that a satisfactory standard of amenity space and play facilities is maintained for the future occupiers of the proposed development.
NOISE
61. The design and structure of the development shall be of such a standard that it will protect residents within it from existing external noise so that they are exposed to levels indoors not more than 35 dB LAeq 16hrs daytime and not more than 30 dB LAeq 8 hrs in bedrooms at night.
Reason: In order to ensure that design, structure and acoustic insulation of the development will provide sufficient protection for residents of the development from the intrusion of external noise.
VENTILATION
62. Reserved matters applications for any phase which residential units, must be accompanied by a PPG24 (or any equivalent that may replace it) Noise Assessment and “cooling strategy” in accordance with BS8233 and Building Regulations to demonstrate that the residential units will comply with the criteria set out in condition 61 of this permission. The noise assessment must include a full acoustic report of how the flats will be insulated to reduce and mitigate external and internal noise/vibration break in and meet the requirements of condition 61 and provide details of how the heating and ventilation system will provide adequate natural ventilation and adequate cooling to prevent overheating (no overheating in bedrooms and living rooms where in these rooms there is a need for windows to be kept shut to achieve compliance with the noise levels set in condition 61. No works shall commence (excluding the Site Preparation Works) until these details have been submitted to and approved by the local planning authority and the development carried out in accordance with those details approved.
Reason: In order to secure a comfortable internal environment for the occupants of the residential properties.
NOISE – PLANT
63. The design and installation of new items of fixed plant shall be such that, when in operation, the cumulative noise level LAeq Tr arising from the proposed plant, measured or predicted at 1m from the facade of any residential premises shall be a rating level of at least 5dB(A) below the background noise level LAF90 Tbg. The measurement and/or prediction of the noise should be carried out in accordance with the methodology contained within BS 4142: 1997. A noise report shall be produced by a competent person(s) to demonstrate compliance with the above criteria, and shall be submitted to and approved by the local planning authority.
Reason: In order to protect the amenity of nearby residential occupiers.
TRAVEL PLAN
64 That the applicant shall submit 2 travel plans, one for the residential one for the commercial use, the details of which shall be agreed in writing by the Local Planning Authority prior to the occupation of the proposed development. Such agreed details shall be implemented and permanently maintained to the satisfaction of the Local Planning Authority.
Reason: In order to ensure sustainable travel and minimise the impact of the
proposed development in the adjoining road network.
DETAILS OF CHILDRENS PLAY AREAS
65. No phase of residential development hereby permitted shall commence until a specification for the Children’s Play Areas, has been submitted to and approved in writing by the Local Planning Authority. The development shall be undertaken in accordance with National Playing Field Association ‘Six Acre Standard’ Best Practise Guidance (2001) and, unless otherwise agreed in writing by the Local Planning Authority, should include the following as a minimum:
i. An activity zone of at least 400sqm in area that caters for children of 4-8 years in age
ii. At least 5 types of play equipment (i.e. balancing, rocking etc.)
iii. Appropriate boundary treatment to provide a continuous and secure boundary
iv. A barrier to limit the speed of a child entering or leaving the facility
v. At least 10 metres between the edge of the play area and the boundary of the nearest property
vi. Planting around the perimeter
vii. Adequate adult seating provision
viii. Signage
ix. Litter bin
Reason: In the interests of health and safety of users of the site and the amenity of local residents.
ENERGY
66. A detailed energy strategy for the whole site shall be submitted with the detailed application for the first phase of residential development. This energy strategy should commit to meeting 2010 Building Regulations through energy efficiency alone. The details shall be approved by the Local Planning Authority and the development carried out in accordance with the approved details.
Reason: In order to ensure an appropriate level of energy efficiency and
sustainability is provided by the development.
CODE FOR SUSTAINABLE HOMES
67. Reserved Matters applications in respect of each phase of the development which includes residential properties shall be accompanied by an Independent Sustainability Assessment, in accordance with Building Research Establishment guidelines, demonstrating that the residential properties are to achieve a minimum Level 4 rating under the Code for Sustainable Homes.
Reason: In order to ensure an appropriate level of energy efficiency and
sustainability is provided by the development.
RESIDENTS AND BUSINESSES LIAISON GROUP
68. For the duration of the development the Applicant will establish and maintain a Liaison Group having the purpose of:
(a) informing local residents and businesses of the design and development
proposals;
(b) informing local residents and businesses of progress of pre-construction and construction activities;
(c) considering methods of working such as hours and site traffic;
(d) providing local residents and businesses with an initial contact for information relating to the development and for comments or complaints regarding the development with the view of resolving any concerns that might arise;
(e) producing a leaflet prior to commencement of demolition for distribution to local residents and businesses identifying progress of the Development and which shall include an invitation to register an interest in the Liaison Group;
(f) providing advanced notice of exceptional works or deliveries;
(g) providing telephone contacts for residents advice and concerns.
The Liaison Group will meet at least once every month with the first meeting taking place one month prior to Implementation and the meetings shall become bi-monthly after the expiry of a period of four (4) months thereafter or at such longer period as the Liaison Group shall agree.
Reason: In order to ensure satisfactory communication with residents, businesses and local stakeholders throughout the construction of the development.
THAMES WATER
69. When it is proposed to connect to a combined public sewer, the site drainage should be separate and combined at the final manhole nearest the boundary. Connections are not permitted for the removal of Ground Water. Where the developer proposes to discharge to a public sewer, prior approval from Thames Water Developer Services will be required. They can be contacted on 0845 850 2777.
Reason - to ensure that the surface water discharge from the site shall not be
detrimental to the existing sewerage system.
AIR QUALITY ASSESSMENT
70. Before development commences (excluding the Site Preparation Works), an air quality assessment report, written in accordance with the relevant current guidance, for the existing site and proposed development shall be submitted to and approved by the Local Planning Authority. It should also have regard to the air quality predictions and monitoring results from the Authority's Review and Assessment, the London Air Quality Network and London Atmospheric Emissions Inventory. A scheme for air pollution mitigation measures based on the findings of the report shall be submitted to and approved by the Local Planning Authority prior to development. The approved mitigation scheme shall be implemented in its entirety before any of the units are occupied. In determining both the significance of exposure to air pollution and the levels of mitigation required, consideration should be given to the following Air Pollution Exposure Criteria Table.
Reason: In order to monitor and mitigate, where necessary, air quality in the
immediate vicinity of the development.
HEALTH AND SAFETY EXECUTIVE – REVOCATION OF HAZARDOUS
SUBSTANCES CONSENT
71. No part of the development shall be occupied until The Hazardous Substances Consent for the gasholder station has been revoked or varied in accordance with the Planning Hazardous Substances Act 1990, as amended, such that the Health and Safety Executive (HSE) does not advise that permission should be refused on safety grounds, and written confirmation of the necessary revocation or variation has been issued by the London Borough of Haringey as local planning authority.
Reason: In the interests of health and safety, it is necessary to ensure that the
adjoining gas infrastructure will not present a risk to safety.
INFORMATIVES:
INFORMATIVE – DEFINITION OF SITE PREPARATION WORKS
“Site Preparation Works” is defined as “Works of demolition (including the removal of the gas holders and remediation works but excluding the Olympia Trading Estate), surveys, site clearance, works of archaeological or ground investigation or remediation, the erection of fencing or hoardings, the provision of security measures or lighting, the erection of temporary buildings or structures associated with the development, the laying, removal or diversion of services, the provision of construction compounds or piling works) the removal of hard-standing, construction of temporary access, temporary highway works temporary internal estate roads and relocation and erection of the Pressure Reduction Stations"”.
INFORMATIVE – AIR QUALITY ASSESSMENT
The Air Quality Review and Assessment for the London Borough of Haringey has highlighted that this area currently experiences or is likely to experience
exceedances of Government set health-based air quality standards. A list of
possible options for mitigating poor air quality is as follows: 1) Use of passive or active air conditioning; 2) Use of acoustic ventilators; 3) Altering lay out – habitable rooms away from source of poor air quality; 4) Non residential usage of lower floors;
5) Altering footprint - setting further away from source of poor air quality. 6) Having non openable windows.
The Air Quality Assessment report should have regard to the air quality predictions and monitoring results from the Authority’s Review and Assessment available from
the Council web site and the London Air Quality Network. The report should be written in accordance with the following guidance: 1) NSCA Guidance: Development Control: Planning for Air Quality and the Planning Policy Statement 23: Planning and Pollution Control; 2) Environment Act 1995 Air Quality Regulations, Planning Policy Statement 23: Planning and Pollution Control, Annex 1: Pollution Control, Air and Water Quality; 3) Local Air Quality Management Technical Guidance LAQM.TG(09); 4) London Councils Air Quality and Planning Guidance, revised version January 2007.
INFORMATIVE – LONDON FIRE AND EMERGENCY PLANNING AUTHORITY
Burning is not the recommended method of disposing of waste materials and you should contact the Local Authority’s Environmental Health Department who will advise on any legislation or by-laws that may be applicable before such methods are employed. However, if burning is to take place, then the following precautions should be taken: All timber and other flammable materials are to be removed from the building and timber buildings are to be demolished, before burning is commenced, to prevent: Persons being trapped with burning buildings; and Premature collapse of the buildings due to heat damage or to the burning away of supporting structure.
The controlled burning of all materials is to take place at one point. The surrounding area should be clear of all other flammables to prevent fire spread to adjoining properties. The Fire Brigade is to be consulted prior to the commencement should any doubt arise.
The contractor is to ensure the burning of flammable materials is under the direct control of a designated person who shall be provided with suitable emergency fire fighting equipment and instruction on how to call the Brigade, including the location of the nearest exchange telephone.
Should the fire get out of control the Fire Brigade is to be called immediately using the ‘999’ system procedure.
No fire is to be left unattended under any circumstances. All fires are to be
extinguished completely before the site is vacated at the end of the day or on
completion of the contract.
NB. It should be noted that demolition of masonry on top of a fire is not acceptable as a means of extinguishing the fire.
Where demolition is to include the ‘hot cutting’ of oil storage tanks or associated plant, further advice on “process safety” issues should be sought from the Health and Safety Executive (HSE).
NB. Where hot cutting has already commenced and advice on process safety has not already been sought from HSE, then operations should cease until such time as that advice is provided.
INFORMATIVE - ENVIORNMENT AGENCY - WATER RESOURCES ACT 1991
Under the terms of the Water Resources Act 1991, and the Thames Region Land Drainage Byelaws 1981, the prior written consent of the Environment Agency is required for any proposed works or structures, in, under, over or within 8 metres of the top of the bank of the Moselle Brook, designated a 'main river'. Drainage plans should be submitted for each phase of the development showing how discharges will be managed. A schematic drawing showing drainage features including foul and surface drainage runs, interceptors, the location and protective measures employed around areas used for the storage of waste, oils and chemicals will be helpful in approving each scheme. Dewatering has the potential to affect watercourses and groundwater and is subject to control by the Environment Agency under the Water Resources Act 1991 and the Water Act 2003. The applicant should contact the Environment Agency on 08708 506 506 for further information if dewatering is necessary.
INFORMATIVE - ENVIRONMENT AGENCY – WATER EFFICIENCY
The Thames Region including all London Borough's have been identified as an area of ‘serious’ water stress'. Therefore water conservation and water efficiency measures need to be core themes in any new development.
Through committing to Code for Sustainable Homes Level 4 in all residential
properties, this will achieve the London Plan Policy 4A.16 of the maximum water use target of 105 litres per person per day for residential development.
In terms of commercial development proposals, they will need to demonstrate that the proposal incorporates water conservation measures. We suggest that all such commercial developers design their building sin accordance with the Building Research Establishments Environmental Assessment Method (BREEAM) recommendations'. Water efficiency measures can found on the Envirowise website www.envirowise.gov.uk. This is to ensure compliance with communities and Local Government standards for water efficiency in new buildings.
INFORMATIVE – PROTECTION OF SPECIES
The protection afforded to species under UK and EU legislation is irrespective of the planning system and the applicant should ensure that any activity they undertake on the application site (regardless of the need for planning consent) must comply with appropriate wildlife legislation. Failure to do so may result in fines and potentially, a custodial sentence.
INFORMATIVE – REMOVAL OR VARIATION OF CONDITIONS
The applicant is advised that Section 73 of the Town and Country Planning Act 1990 (Determination of applications to develop land without compliance with conditions previously attached) requires formal permission to be granted by the Local Planning Authority for the removal or variation of a condition following grant of planning permission.
INFORMATIVE – NAMING AND NUMBERING
The new development will require naming/numbering. The applicant should contact the Transportation Group at least six weeks before the development is occupied (tel. 020 8489 5573) to arrange for the allocation of a suitable address.
INFORMATIVE – WASTE
In accordance with Section 34 of the Environmental Protection Act and the Duty of, Care, any waste generated from construction/excavation on site is to be stored in a safe and secure manner in order to prevent its escape or its handling by unauthorised persons. Waste must be removed by a registered carrier and disposed of at an appropriate waste management licensed facility following the waste transfer or consignment note system, whichever is appropriates.
INFORMATIVE – PUBLIC EVENTS
Any events to be held in the public squares or parks will be subject to applicants for appropriate licenses from the local authority.
INFORMATIVE – THAMES WASTE – WASTE COMMENTS
Surface Water Drainage – With regard to surface water drainage it is the
responsibility of a developer to make proper provision for drainage to ground, water courses or a suitable sewer. In respect of surface water it is recommended that the applicant should ensure that storm flows are attenuated or regulated into the receiving public network through on or off site storage.
INFORMATIVE – THAMES WASTE – PUBLIC SEWERS AND WATER MAINS
There are public sewers crossing this site, and no building works will be permitted within 3 metres of the sewers without Thames Water's approval. Should a building over / diversion application form, or other information relating to Thames Waters assets be required, the applicant should be advised to contact Thames Water Developer Services on 0845 850 2777. There are large water mains adjacent to the proposed development. Thames Water will not allow any building within 3 metres of them and will require 24 hours access for maintenance purposes.
INFORMATIVES – THAMES WATER – WATER MAIN DIVERSIONS
There is a Thames Water main crossing the development site which may/will need to be diverted at the Developer's cost, or necessitate amendments to the proposed development design so that the aforementioned main can be retained. Unrestricted access must be available at all times for maintenance and repair. Please contact Thames Water Developer Services, Contact Centre on Telephone No: 0845 850 2777 for further information.
INFORMATIVE – RESIDENTS AND BUSINESSES LIAISON GROUP
The makeup of the Residents and Businesses Liaison Group that is required to be established under condition 68 is to be agreed in writing with the Council prior to its establishment.
Supporting documents: