Variation of condition 2 (plans and specifications) attached to planning permission HGY/2011/1576 to allow a revised basement plan showing an extension at this level.
RECOMMENDATION: grant permission subject to conditions.
Minutes:
The Committee considered a report on the application to grant permission for the variation of condition 2 (plans and specifications) attached to planning permission HGY/2011/1576 to allow a revised basement plan showing an extension at this level by 132 sq.m. The report set out details of the proposal, the site and surroundings, planning history, relevant planning policy, consultation and responses, analysis, equalities and human rights implications and recommended to grant permission subject to conditions. The planning officer gave a short presentation highlighting the key aspects of the report and advised that the minor material amendment would require the applicant under a pre-condition to enter into a deed of variation to the current s106 agreement.
The Committee queried whether the basement impact assessment undertaken for the previous approved scheme was still relevant. Officers confirmed that an addendum had been submitted to the original assessment to take into account the proposed extension and which confirmed that it was not considered to present any additional issues to those dealt with under the original proposal. Basement excavation works were already underway onsite with no adverse impacts identified.
An email summarising the key objections of a local resident to the application was circulated to the Committee focussed on the need for a further Hydrological Survey and Basement Impact assessment for the changed plans, concerns that the site was on a spring line, that the increase in volume of the basement was significant and not minor and that mitigation measures for surface water runoff should be in place. Officers reiterated the limited value in the undertaking of an additional basement survey and confirmed research on water courses in the area illustrating that no feeder streams ran near to the site. Clarification was provided that the extension of the basement was not considered significant within the context of the broader scheme.
The Chair moved the recommendation of the report and it was
RESOLVED
· That planning application HGY/2013/2287 be approved subject to conditions and a pre-condition that the owners of the application site first have entered into a deed of variation to the current s106 agreement.
IMPLEMENTATION
1. The development hereby authorised must be begun not later than the expiration of 3 years from the date of 24th December 2012, failing which the permission shall be of no effect.
Reason: This condition is imposed by virtue of the provisions of the Planning & Compulsory Purchase Act 2004 and to prevent the accumulation of unimplemented planning permissions.
2. The development hereby authorised shall be carried out in complete accordance with the plans and specifications submitted to, and approved in writing by the Local Planning Authority
Reason: In order to ensure the development is carried out in accordance with the approved details and in the interests of amenity.
EXTERNAL APPEARANCE & SITE LAYOUT
3. Samples of all materials to be used for the external surfaces of the development shall be submitted to, and approved in writing by, the Local Planning Authority before any development is commenced. Samples should include sample panels or brick types and a roofing material sample combined with a schedule of the exact product references.
Reason: In order for the Local Planning Authority to retain control over the exact materials to be used for the proposed development and to assess the suitability of the samples submitted in the interests of visual amenity.
4. A final landscaping scheme for the treatment of the surroundings of the proposed development including the planting of trees and/or shrubs in addition to an associated maintenance regime shall be submitted to, approved in writing by the Local Planning Authority. The landscaping shall be completed within 12 months, or by the end of the first planting season, after the completion of the development to the satisfaction of the Local Planning Authority.
Any trees, or plants which die within a period of 5 years from the completion of the development; are removed, or become seriously damaged, or diseased shall be replaced in the next planting season with others of similar size and species, unless the Local Planning Authority gives written consent to any variation.
Reason: In order to provide a suitable setting for the proposed development in the interests of visual amenity
5. Details of a scheme depicting those areas to be treated by means of new hard landscaping shall be submitted to, approved in writing by, and implemented in accordance with the approved details. Such a scheme to include a detailed drawing of those areas of the development to be so treated, a schedule of proposed materials and samples to be submitted for written approval on request from the Local Planning Authority.
Reason: In order to ensure the development has satisfactory landscaped areas in the interests of the visual amenity of the area.
6. Before the buildings hereby permitted are occupied the windows on the side elevation of the building facing No 112 The Bank shall be glazed with obscure glass only and shall be non-opening.
Reason: To safeguard the privacy and amenities of occupiers of adjoining residential properties
7. No external lighting, floodlighting or other means of external illumination shall be affixed to the external elevations of the buildings, or placed/erected within the site other than those approved in writing by the Local Planning Authority. Any external lighting or other means of external illumination shall be installed and thereafter retained in full accordance with the approved details.
Reason: To enable the local planning authority to retain control over these matters in the interests of the amenities of the adjoining properties.
TREE PROTECTION
8. All works associated with this development shall be undertaken in accordance with the detail as specified in the Arboricultural Report & Method Statement.
Reason: To safeguard the health of existing trees which represent an important amenity feature.
9. A pre-commencement site meeting must take place with the Architect, the consulting Arboriculturist, the Local Authority Arboriculturist and the Planning Officer to confirm tree protective measures to be implemented. All protective measures must be installed prior to the commencement of works on site and shall be inspected by the Council Arboriculturist and thereafter be retained in place until the works are complete.
Reason: To safeguard the health of existing trees which represent an important amenity feature.
ENERGY EFFICIENCY / SUSTAINABILITY
10. A supporting statement shall be submitted demonstrating consistency with submitted Energy Assessment including the siting of the PV panels. Thereafter the renewable energy technology/ system shall be installed in accordance with the details approved and an independent post-instillation review, or other verification process as agreed, shall be submitted to the Local Planning Authority confirming the agreed technology has been installed prior to the occupation of the buildings hereby approved.
Reason: To ensure the development incorporates energy efficiency measures including on-site renewable energy generation, in order to contribute to a reduction in carbon dioxide emissions generated by the development in line with national and local policy guidance.
11. A certificated BREEAM Post Construction Review, or other verification process agreed with the Local Planning Authority, shall be provided, confirming that the agreed standards have been met, prior to the occupation of the development.
Reason: To ensure that the proposal complies with the principles of sustainable development
PERMITTED DEVELOPMENT
12. The proposed development shall have a central dish/aerial system for receiving all broadcasts for these buildings hereby approved, details of such a scheme shall be submitted to and approved by the Local Planning Authority prior to the occupation of the property and the approved scheme shall be implemented and permanently retained thereafter.
Reason: In order to protect the visual amenities of the neighbourhood.
13. Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 no telecommunications antennae or associated equipment shall be erected on the exterior of this development, without a separate planning permission
Reason: In the interest of orderly development and the visual amenities of the area, and in order to permit the Local Planning Authority to assess the design quality and appropriateness of any such features on the overall streetscape and appearance of the development.
CONSTRUCTION
14. The construction works of the development hereby granted shall not be carried out before 0800 or after 1800 hours Monday to Friday or before 0800 or after 1300 hours on Saturday and not at all on Sundays or Bank Holidays.
Reason: In order to ensure that the proposal does not prejudice the enjoyment of neighbouring occupiers of their properties.
15. Prior to the commencement of work a Construction Management Plan including a scheme for the management of the construction traffic associated with implementing this scheme, shall be submitted to and approved in writing by the Local Planning Authority. The plan will specifically show the how traffic around the immediate road network are routed.
Reason: To ensure the construction period of the development does not result in unreasonable disturbance for neighbouring properties and to minimise vehicular conflict at this location.
16. Prior to the commencement of development, drawings and a method statement for the construction of the basements and the protection of the retaining wall along the boundary with No 112 The Bank shall be submitted to and approved in writing by the Local Planning Authority. This shall demonstrate a means of ensuring the safety and structural stability of this wall throughout the period of the approved works of excavation and construction. The relevant work shall be carried out in strict accordance with the approved details.
Reason: To ensure the special character, architectural interest and integrity of this historic wall is preserved.
17. No development shall take place until the applicant has secured the implementation of a programme of archaeological work, in accordance with a written scheme of investigation which has been submitted by the applicant and approved by the Local Planning Authority.
Reason: To enable archaeological investigation of the site.
18. The developer shall afford access at all reasonable times to any archaeologist nominated by the Local Planning Authority, and shall allow that person to observe the excavation and record items of interest and finds. Reason: To enable archaeological investigation of the site.
Reason: To enable archaeological investigation of the site.
.
CONTROLS ON USE
19. The use of the premises for the purposes hereby permitted shall only take place between the hours of 7.00am and 10.30pm on weekdays and, Saturdays and between 9.00am and 10.00pm on Sundays.
Reason: To ensure that the use does not prejudice the amenities of occupiers of neighbouring residential properties.
20. Prior to the commencement of the use/development a Community Use Scheme shall be submitted to and approved in writing by the Local Planning Authority. The Scheme shall include details of pricing policy, hours of use, access by non-school users/non-members, management responsibilities and include a mechanism for review. The approved Scheme shall be implemented upon commencement of use of the development.
Reason: To secure well managed safe community access to the sports facility and, to ensure sufficient benefit to the development of sport.
Supporting documents: