Marc Dorfman, Assistant Director, Planning
Regeneration and Economy, presented the report on the
Council’s s106 policy and guidance, s106 agreements signed
and administered between 2005 -11 and the distribution of the s106
funds received by the Council. Of the approximately £13m
received, around £3.7m remained unspent, of which £0.7m
related to monitoring activity. Mr Dorfman advised that there were
currently two sites of significant concern, Winns Mews and Markfield Road, totalling around £138k, and
that the possibility of legal sanction was being explored in these
instances. A number of other schemes which were close to their
payment deadlines were also being monitored, totalling around
£300 – 400k.
The following points were raised in
discussion:
- Mr Dorfman would check the length of
time the schemes at Winns Mews and
Markfield Road had been given for the
payment of the s106 monies owed, and would report this back to the
Committee.
- It was confirmed that £7.7m
was owed in respect of Hale Village, of which the majority was
outstanding. Mr Dorfman reported that the renegotiated s106
agreement was close to completion; the signature of this would
trigger an immediate payment of £3.2 – 3.5m, with the
rest to be triggered at further points during the development. The
s106 agreement had been brought back twice to the Planning Sub
committee for revision, and it agreed that this was unusual. The
revised agreement for Hale Village was scheduled for completion in
March 2012, and it was felt unlikely that this date would
slip.
- Concern was expressed that the
recent decision in respect of Spurs might set a precedent for other
large developments, such as Hale Village, and that in agreeing to
renegotiate the s106, the Council had appeared compliant in
accepting reduced contributions. Mr Dorfman advised that it was a
balance; if a hard line were taken and the construction on the site
was closed down due to non-payment, then there would be no chance
of recovering the monies owed. Where issues arose with a
development that had previously been considered appropriate for
permission, for example as a result of a decrease in land values,
it was reasonable that renegotiation of the s106 be brought to the
Planning Sub Committee for consideration. Mr Dorfman advised that
the Spurs decision was not a precedent for other schemes.
- Mr Dorfman agreed that he would
check the date after which LVE could appeal the s106 obligations in
respect of Hale Village, and would report this back to the
Committee.
- The Committee asked about education
formula; Mr Dorfman advised that this was a detailed formula based
on child yield predictions, calculated by a mathematical model
which linked in with other boroughs. It was agreed that the formula
would be sent to Cllr Schmitz for information.
- Mr Dorfman reported that a legal
agreement had been signed in respect of the Wards Corner
development, but no money had been paid over as consent had
subsequently been overturned and any contribution had therefore not
been triggered.
- It was agreed that a training
seminar on the Community Infrastructure Levy would be held for
Committee Members.
- Mr Dorfman agreed to check that no
figures were double-counted by being included in categories for
both ‘not implemented’ and ‘value negotiated /
received’, but advised that significant effort had been made
to ensure that figures were not double-counted in the report.
- The Committee noted the scale of the
concessions made in respect of the s106 for the Spurs development,
when compared against the total s106 receipts as outlined in the
report. It was reported that Spurs was an unusual scale in
comparison with other sites in the borough, and must be considered
in the context of the associated investment.
- The Committee asked about the
education component in wards such as Highgate, where there were
significant areas which were not within the catchment area for Haringey schools. Mr Dorfman
reported that it was general practice not to transfer any s106
payments to other authorities, although an agreement had been made
in respect of the Spurs application for a contribution to be made
to Enfield. Haringey was also working with Enfield to look at the
distribution of s106 contributions between the two boroughs in
respect of proposed residential developments situated north of the
North Circular. It was confirmed that education contributions were
distributed across the borough, on the basis of need.
- In response to further discussion
around Hale Village, and why the Council should not take a firmer
stance, Mr Dorfman reported that this was an option, but that
legislation afforded developers the opportunity to argue their case
in respect of s106 agreements and viability. Mr Dorfman reported
that it was important that, once a scheme had been identified as
valuable, the planning authority made efforts to bring that
development forward. With regards to Tottenham Hale, an approach
requiring a developer to take a significant loss by meeting s106
contributions agreed under different economic conditions could have
longer term impacts on land values and regeneration reputation in
Tottenham Hale.
- The Committee asked about overage in
respect of Hale Village, and Mr Dorfman reported that whether
overage payments would be triggered was dependent on the wider
economic position and the national and London property market.
- The Committee suggested that a land
charge should have been considered at Hale Village in order to
ensure that the Council received payment at the point when the sale
of blocks had been completed. Mr Dorfman advised that issues around
viability at Hale Village had been looked into, and that such a
land charge would have impacted on the developer’s ability to
borrow. It was agreed that Mr Dorfman would look into the
suggestion that land charges be considered in respect of future
developments and report back to the Committee regarding this
issue.
- The Committee was advised that, were
there significant further delay in contributions being made in
respect of Hale Village, or payment trigger points reached in the
development without the developer advising the authority, then a
position would be reached where an enforcement approach would be
necessary.
- It was noted that Hale Village was
providing affordable housing in addition to the s106 payments due,
which did offer the Council savings on its temporary accommodation
budget.
- It was agreed that Mr Dorfman would
provide all Committee Members with an update on the position in
respect of the Hale Village development, the s106 agreement for
which was due for signature in March 2012, triggering an immediate
payment of £3.2 / £3.5m
RESOLVED
That the content of the report be noted.