FILMING AT MEETINGS Minutes: The Chair referred to the notice of filming at meetings and this information was noted. |
|
APOLOGIES FOR ABSENCE To receive any apologies for absence. Minutes: There were no apologies for absence. |
|
URGENT BUSINESS Minutes: There were no new items of urgent business. |
|
DECLARATIONS OF INTEREST A member with a disclosable pecuniary interest or a prejudicial interest in a matter who attends a meeting of the authority at which the matter is
considered: (i) must disclose the interest at the start of the meeting or when the interest becomes apparent, and (ii) may not participate in any discussion or vote on the matter and must
withdraw from the meeting room. A member who discloses at a meeting a disclosable pecuniary interest which is not registered in the Register of Members’ Interests or the subject of a pending notification must notify the Monitoring Officer of the interest within 28
days of the disclosure. Disclosable pecuniary interests, personal interests and prejudicial interests are defined at Paragraphs 5-7 and Appendix A of the Members’ Code of Conduct. Minutes: There were no declarations of interest. |
|
DEPUTATIONS/PETITIONS/QUESTIONS Minutes: There were no deputations/petitions/questions. |
|
Minutes: It was
acknowledged that there were significant delays in the work being
completed by the original contractor Cosmur Construction (London). The Cabinet Member
for Health, Social Care and Wellbeing also noted that there were
external pressures such as the Government budget and legal
challenges that affected the process and timeline in the case of
Canning Crescent.
The Cabinet Member for Health, Social Care and
Wellbeing RESOLVED: 5. To note a total award for phase 2a, 2b and 2c up to the aggregated value of £1,756,468 excluding phase 2c contingency.
6. Approve the issuance of a Letter of Intent up to
the value of £100,000. There were significant delays in the work being completed by the original contractor Cosmur Construction (London) ltd with a contract completion date of 18th March 2022 and the last projected completion date of 27th January 2023. These delays we suspect were attributed to issues with their supply chain payment and poor management which in part was explained by the company entering a Compulsory Voluntary Arrangement on 11th May 2023. Following a review by Major Projects, Haringey Procurement and Legal it was decided the best course of action was to terminate the contract with Cosmur Construction (London) Ltd which was completed on the 31st of March 2023 and for expediency to directly award a contract to a supplier with a track record of delivering similar projects using the Haringey Procurement Contract System (HPCS). With a refurbishment scheme of this nature that had extensive mechanical and electrical (M&E) alterations there is a level of complexity relating to a replacement contractor taking liability for the installation of works by the original contractor. In recognition of this Major Projects instigated a process of validation (by the incoming provider) to assist in ... view the full minutes text for item 26. |
|
NEW ITEMS OF URGENT BUSINESS Minutes: There were no new items of urgent business. |
|
EXCLUSION OF THE PRESS AND PUBLIC Minutes:
Item 9 was subject to a motion to exclude the press
and public be from the meeting as it contained exempt information
as defined in Section 100a of the Local Government Act 1972 (as
amended by Section 12A of the Local Government Act 1985); para 3,
namely information relating to the financial or business affairs of
any particular person (including the authority holding that
information). |
|
EXEMPT - CANNING CRESCENT Exempt information pertaining to Item 6. Minutes: The
Cabinet Member considered the exempt information. |
|
NEW ITEMS OF EXEMPT URGENT BUSINESS Minutes: There were no new items of exempt urgent business. |