Agenda and minutes

CHESTNUTS PRIMARY SCHOOL & LORDSHIP LANE PRIMARY SCHOOL & WEST GREEN PRIMARY SCHOOL, Cabinet Member Signing
Friday, 2nd July, 2021 1.30 pm, NEW

Media

Items
No. Item

7.

APOLOGIES FOR ABSENCE

To receive any apologies for absence.

Additional documents:

Minutes:

There were no apologies for absence.

 

8.

Declarations of interest

A member with a disclosable pecuniary interest or a prejudicial interest in a matter who attends a meeting of the authority at which the matter is considered:

 

(i) must disclose the interest at the start of the meeting or when the interest becomes apparent, and

(ii) may not participate in any discussion or vote on the matter and must withdraw from the meeting room.

 

A member who discloses at a meeting a disclosable pecuniary interest which is not registered in the Register of Members’ Interests or the subject of a pending notification must notify the Monitoring Officer of the interest within 28 days of the disclosure.

 

Disclosable pecuniary interests, personal interests and prejudicial interests are defined at Paragraphs 5-7 and Appendix A of the Members’ Code of Conduct

Additional documents:

Minutes:

None.

9.

Chestnuts Primary School - External Envelope and Building Services Improvement - Award of Construction Contract pdf icon PDF 223 KB

Additional documents:

Minutes:

The Cabinet Member for Early Years, Children & Families considered the report which sought approval to award a contract to Kind Diamond Build Consortium Ltd up to the value of £4,060,282.22 to undertake external envelope and building services improvement works at Chestnuts Primary School pursuant to contract standing order 16.02, and pursuant to Contract Standing Order (CSO) 16.02, to approve the issuance of a letter of intent.

 

RESOLVED that the Cabinet Member

i.          Approve an award of contract to Kind Diamond Build Consortium Ltd to the value of £3,691,165.66.

ii.         Approve a contingency allowance of 10% that equates to £369,116.56 which will be strictly managed under change control governance arrangements

iii.        Approve the issuance of a letter of intent for up to 10% of the contract value, totalling £369,116.56.

 

Reasons for decision

A major review of the condition and suitability of the Children’s Services estate has been undertaken which has informed the Children’s Service’s asset management plan (CSAMP).  This identified condition and suitability deficiencies in the primary, secondary, and wider Children’s Service estate need addressing in the short, medium, and long-term. 

 

Chestnuts Primary School is high priority for major works due to issues relating to health and safety or the school is at risk of school closure.

 

In 2019 a commission was given to further investigate and address urgent works relating to the condition of building services (i.e. heating, electrics and plumbing), external envelope (i.e. roofs, windows) and boundary security.

 

The scheme has been granted an allocation of funding £0.262m from the public sector decarbonisation programme, a government initiative sponsored by the Department for Business, Energy & Industrial Strategy and administered by Salix (Salix works). The grant will be used to part fund the scheme thus reducing the amount of borrowing that the Council will need to undertake. The terms of the grant are that the relevant works need to be completed by the 30th September 2021. If this date is missed, then there is a risk that the grant allocation will need to be repaid.

 

A scheme for Chestnuts Primary School has been developed, with sectional completion dates in order to achieve the following:

 

·                Salix Public Sector Decarbonisation grant funding works (Window replacement, LED Lighting, Loft Insulation, Building Management System).

·                Boiler and heating works completion prior to the heating season starting in October.

·                Decant classroom spaces completed prior to the start of the September term.

·                Roof replacement, brick repointing, small power and data

 

This construction award report requests a decision on the procurement of a contractor to undertake all of the external envelope and building services infrastructure works identified, designed and approved by the project sponsor.

 

A Cabinet Member decision is required in July 2021 to enable timely mobilisation and facilitate procurement of longer lead in materials as soon as possible which will offer greater likelihood of achieving maximum grant funding available.

 

Alternative Options Considered

Do nothing – a decision not to support this award of construction contract will result in the Councils failure to suitably maintain its education estate  ...  view the full minutes text for item 9.

10.

Lordship Lane Primary School - Building Services Improvement and External Envelope Works - Award of Construction Contract pdf icon PDF 222 KB

Additional documents:

Minutes:

The Cabinet Member for Early Years, Children & Families considered the report which sought approval to award a contract to Mulalley and Company Limited up to the value of £3,416,532.90 to undertake building services improvement and external envelope condition works at Lordship Lane Primary School pursuant to contract standing order 16.02 and, pursuant to Contract Standing Order (CSO) 16.02 to approve the issuance of a letter of intent.

 

It was noted that whilst there was a lot of work to be carried out at the school, there was an extensive project programme in place in order to make best use of the summer holidays.  The contractor had also provided information on their Covid safety plans which were in line with the Council’s approach and Government guidance.  The Cabinet Member requested that the contractor increase the regularity of carrying out their Lateral Flow Tests to help reduce the spread of Covid in schools.

 

RESOLVED that the Cabinet Member

i.          Approve an award to Mulalley and Company Limited of £3,105,939.00;

ii.         Approve a client construction contingency of 10% that equates to £310,593.90 which will be strictly managed under change control governance arrangements;

iii.        Approve the issuance of a letter of intent for up to 10% of the contract value totalling £310,593.90.

 

Reasons for decision

 

A major review of the condition and suitability of the Children’s Services estate has been undertaken which has informed the Children’s Service’s asset management plan (CSAMP).  This identified condition and suitability deficiencies in the primary, secondary, and wider Children’s Service estate that need addressing in the short, medium, and long-term.  Lordship Lane Primary School is high priority for major works due to issues relating to health and safety or school closure risks.

 

In 2018 an initial brief was given to undertake the most immediate (short term) health and safety, compliance, and resilience work. These findings included fire compartmentation, fire doors and heating resilience and were subject to a separate award under delegated powers.

 

In 2019 a further commission was given to further investigate and address urgent works relating to the condition of building services (ie heating, electrics and plumbing), external envelope (ie roofs, windows) and boundary security.

 

The scheme at Lordship Lane Primary School has been granted an allocation of funding (£539,000) from the public sector decarbonisation programme, a government initiative sponsored by the Department for Business, Energy & Industrial Strategy and administered by Salix (Salix works). The grant will be used to part fund the scheme thus reducing the amount of borrowing that the Council will need to undertake. The terms of the grant are that the relevant works need to be completed by the 30th September 2021. If this date is missed, then there is a risk that the grant allocation will need to be repaid. 

 

The works at Lordship Lane Primary School has been developed into 2 phases in order to minimise disruption to the school (referenced in 5.2) and achieve the criteria for Salix Public Sector Decarbonisation grant funding.  This construction award report  ...  view the full minutes text for item 10.

11.

West Green Primary School - Building Services Improvement and External Envelope Works - Award of Construction Contract pdf icon PDF 222 KB

Additional documents:

Minutes:

The Cabinet Member for Early Years, Children & Families considered the report which sought approval to award a contract toMulalley and Company Limited up to the value of £2,270,002.90 to undertake building services improvement and external envelope condition works at West Green Primary School pursuant to contract standing order 16.02 and, pursuant to Contract Standing Order (CSO) 16.02 to approve the issuance of a letter of intent.

1 

2 

 

RESOLVED that the Cabinet Member

i.          Approve an award to Mulalley and Company Limited of £2,063,639

ii.         Approve a client construction contingency of 10% that equates to £206,363.90, which will be strictly managed under change control governance arrangements

iii.        Approve the issuance of a letter of intent for up to 10% of the contract value totalling £206,363.90.

 

Reasons for decision

 

A major review of the condition and suitability of the Children’s Services estate has been undertaken which has informed the Children’s Service’s asset management plan (CSAMP).  This identified condition and suitability deficiencies in the primary, secondary, and wider Children’s Service estate that need addressing in the short, medium, and long-term.  West Green Primary School is high priority for major works due to issues relating to health and safety or school closure risks.

 

In 2018 an initial brief was given to undertake the most immediate (short term) health and safety, compliance, and resilience work. These findings included fire compartmentation, fire doors and heating resilience and were subject to a separate award under delegated powers.

 

In 2019 a further commission was given to further investigate and address urgent works relating to the condition of building services (ie heating, electrics and plumbing), external envelope (ie roofs, windows) and boundary security.

 

The scheme at West Green Primary School has been granted an allocation of funding (£325,000) from the public sector decarbonisation programme, a government initiative sponsored by the Department for Business, Energy & Industrial Strategy and administered by Salix (Salix works). The grant will be used to part fund the scheme thus reducing the amount of borrowing that the Council will need to undertake. The terms of the grant are that the relevant works need to be completed by the 30th September 2021. If this date is missed, then there is a risk that the grant allocation will need to be repaid. 

 

The works at West Green Primary School has been developed into 2 phases in order to minimise disruption to the school (referenced in 5.2) and achieve the criteria for Salix Public Sector Decarbonisation grant funding.  This construction award report requests a decision on the procurement of a contractor to undertake Phase 2 – building services improvement and external envelope condition works. Phase 1, which consists of the demolition of a redundant/end of life modular unit, has been tendered and awarded under delegated approval at c£17,400, as it is intended to complete Phase 1 during mid-July before the main works commence. This decision is for Phase 2 only. The scheme of works developed is to achieve the following:

 

·           Salix Public Sector Decarbonisation  ...  view the full minutes text for item 11.

12.

EXCLUSION OF PRESS AND PUBLIC

Items 7-9 are likely to be subject to a motion to exclude the press and public from the meeting as it contains exempt information as defined in Section 100a of the Local Government Act 1972 (as amended by Section 12A of the Local Government Act 1985); paragraph 3, information relating to the financial or business affairs of any particular person (including the authority holding that information)

Additional documents:

Minutes:

RESOLVED

 

That the press and public be excluded from the reminder of the meeting as Item 5 contained exempt information, as defined under paragraph 3 of Part 1 of Schedule 12A of the Local Government Act 1972.

 

13.

EXEMPT - Chestnuts Primary School - External Envelope and Building Services Improvement - Award of Construction Contract

Additional documents:

Minutes:

The Cabinet Member considered exempt information pertaining to agenda item 9.

14.

EXEMPT - Lordship Lane Primary School - Building Services Improvement and External Envelope Works - Award of Construction Contract

Additional documents:

Minutes:

The Cabinet Member considered exempt information pertaining to agenda item 10.

15.

EXEMPT - West Green Primary School - Building Services Improvement and External Envelope Works - Award of Construction Contract

Additional documents:

Minutes:

The Cabinet Member considered exempt information pertaining to agenda item 11.