Venue: Alexandra House, Station Road, N22 7TY
Contact: Ayshe Simsek, Democratic Services and Scrutiny Manager 2929, Email: ayshe.simsek@@haringey.gov.uk
No. | Item |
---|---|
Apologies for absence To receive any apologies for absence. Minutes: There were none. |
|
Declarations of interest A member with a disclosable pecuniary interest or a prejudicial interest in a matter who attends a meeting of the authority at which the matter is considered:
(i) must disclose the interest at the start of the meeting or when the interest becomes apparent, and (ii) may not participate in any discussion or vote on the matter and must withdraw from the meeting room.
A member who discloses at a meeting a disclosable pecuniary interest which is not registered in the Register of Members’ Interests or the subject of a pending notification must notify the Monitoring Officer of the interest within 28 days of the disclosure.
Disclosable pecuniary interests, personal interests and prejudicial interests are defined at Paragraphs 5-7 and Appendix A of the Members’ Code of Conduct Minutes: There were none. |
|
URGENT BUSINESS Minutes: There was none. |
|
DEPUTATIONS / PETITIONS / QUESTIONS Minutes: There were none. |
|
Minutes: The Major Projects Delivery Manager introduced the report. The rationale for the report was outlined.
Officers outlined the reasoning for the proposed budget uplift of £498,689. It was additionally noted that work was expected, following approval of the uplift, to be completed by end-July 2025.
Officers noted that they were disappointed that the uplift was required, as it was expected that the project would have been completed in February 2025.
RESOLVED:
That the Cabinet Member for Housing and
Planning, and Deputy Leader of the Council: 1.
Approved an increase of funding for the project of £498,689
from £5,918,805 to £6,417,494. 2.
Approved a variation of the construction works contract to Kind
Diamond Consortium (KDC) up to £461,640, varying the contract
value from £1,904,529 to £2,366,169, pursuant to
contract standing orders 18.03.3, 2.01(d), and 0.08. 3. Approved a client contingency of £44,485. Reasons for Decision As approved by the Cabinet Member for Health, Social Care, and Wellbeing via a Cabinet Member signing on the 6th of June 2024, the Council had entered a JCT Standard Building Contract without Quantities 2016 (SBC/XQ 2016) with Kind Diamond Consortium to complete works at Canning Crescent with a start date of 4th July 2024 and completion on 15th January 2025.
An extension of time had been granted on the 29th of January 2025, reflecting additional fire compartmentalisation works that were required during the initial stages of the work, with a revised completion date of 21st February 2025. Following failure to hand over the building by this date, a non-completion certificate had been issued on the 25th of February 2025.
The handover that had been expected to be achieved on the 21st of February 2025 was not possible due to several items, notably: · Upon commissioning of the Air Source Heat Pumps (ASHP), completed on the 14th of February 2025, it had been found that the flow rate of the pumps serving the hot water and heating was below the designed parameters of the system, which in cold weather could have led to the heating temperatures not reaching required levels. This had been identified as a design fault, and three new pumps had been ordered, which were due to be replaced in May 2025. · Issues had also been identified with the fire dampers across the scheme (fitted by a previous contractor), which provided the integrity of the fire compartments where pipes entered floors and walls in protected corridors. This had only been established by the design team on Monday, 25th February 2025. Due to the requirement to maintain warranties, there was now a requirement to replace all dampers across the building.
The Client had also requested additional works to the building, including providing hand driers and hot and cold ZIP taps, which had not formed part of the contract but were included within the scope of works forming this approval.
Alternative options considered
Do nothing – The refurbishment works at Canning Crescent remained incomplete. A decision not to support this award of construction contract would have resulted ... view the full minutes text for item 10. |
|
Exclusion of the Press and Public Item 7 is likely to be subject to a motion to exclude the press and public be from the meeting as it contains exempt information as defined in Section 12A of the Local Government Act 1985; paras 3, namely information relating to the financial or business affairs of any particular person (including the authority holding that information) Minutes: RESOLVED: That the press and public be excluded from the remainder of the meeting as item 7 contains exempt information as defined under paragraph 3, Part 1, Schedule 12A of the Local Government Act 1972: Information relating to the financial or business affairs of any particular person (including the authority holding that information).
|
|
Canning Crescent 176 High Road, Wood Green, N22 8JT Refurbishment Works - Increase of project budget and variation of construction works contract - EXEMPT REPORT Minutes: The information contained within the exempt appendix was discussed.
RESOLVED:
The information within the exempt appendix was noted. The recommendations contained within item 4 were agreed. |