16. Contract Extension - Tyco CCTV Maintenance Contract
PDF 224 KB
Report of the Corporate Director of Environment and Resident Experience. To be presented by the Cabinet Member for Climate Action and Transport
Decision:
DECLARATIONS OF INTEREST MADE FOR THIS ITEM:
None
RESOLVED:
That Cabinet:
1. Pursuant to Contract Standing Order (CSO) 18.02.2 and CSO 2.01(d), approved the extension of the contract for the maintenance of CCTV equipment with Tyco Fire & Integrated Solutions (UK) Ltd for a period of one year, from 1 December 2026 to 30 November 2027, at a value of £809,233.02. The original contract had been awarded in November 2021 for a four-year term commencing on 1 December 2021, with a value of £1,836,668. The contract had subsequently been extended in November 2025 for a period of one year, from 1 December 2025 to 30 November 2026, at a value of up to £900,000. The proposed extension would have increased the total contract value to £3,545,901.02.
2.
Approved an extension of the contract term only, at no additional
cost, for the provision of CCTV equipment and services with Tyco
Fire & Integrated Solutions (UK) Ltd. The contract had
originally been awarded in November 2021 and commenced on 1 March
2022, with an expiry date of 28 February 2027. The proposed
extension would have moved the expiry date to 30 November 2027. The
purpose of the extension was to align the expiry dates of the
equipment and maintenance contracts, thereby enabling the Council
to undertake a future integrated procurement exercise and realise
efficiencies associated with a single contractual
arrangement.
3. Pursuant to Contract Standing Order 2.01(b), approved the commencement of a procurement exercise for a future integrated CCTV service covering maintenance, equipment, and infrastructure requirements.
Reasons for the Decision
The existing CCTV Maintenance Contract was due to expire on 30 November 2026. Continued maintenance support was required to ensure the ongoing operation of the Council's CCTV infrastructure, including community safety CCTV systems, traffic enforcement cameras, School Streets infrastructure, low-traffic neighbourhood enforcement systems, and associated control room equipment.
CCTV infrastructure formed an important part of the Council's operational arrangements for community safety, incident investigation, evidence gathering, and statutory traffic enforcement functions across the borough. Any interruption to maintenance arrangements could have resulted in system failures, reduced operational effectiveness, service disruption, and wider organisational risks.
The Council maintained a separate contract for CCTV Equipment and Services, with that contract due to expire in February 2027. Aligning the expiry dates of the infrastructure and maintenance contracts would have enabled the Council to undertake a single procurement exercise covering CCTV maintenance, cameras, equipment, and supporting infrastructure. This approach was expected to provide a more integrated service model by bringing responsibility for maintenance, equipment, and infrastructure together within a single contractual arrangement. It was also anticipated to support contract consolidation and improve value for money through future procurement activity.
Future procurement arrangements for CCTV services needed to take account of the planned relocation of the CCTV control room and associated server infrastructure from Alexandra House and River Park House. Entering into a longer-term maintenance and equipment contract before the technical requirements for the future control room had been established could have limited flexibility and created a risk that ... view the full decision text for item 16.