10 Enterprise Resource Planning Programme - Phase 2
PDF 330 KB
Report of the Corporate Director of Finance and Resources. To be presented by the Cabinet Member for Finance and Corporate
Additional documents:
Decision:
DECLARATIONS OF INTEREST MADE FOR THIS ITEM:
None
RESOLVED:
That Cabinet, after considering the information within the exempt appendices:
1.
Approved the Full Business Case for the replacement of the
Council’s Enterprise Resource Planning (ERP) system,
including the procurement of an integrated ERP solution, its
implementation, and, if required, business integration and support
services.
2. Approved the commencement of two linked procurement activities in accordance with Contract Standing Order (CSO) 2.01(b), comprising:
3.
Delegated authority to decide whether to proceed with the
procurement of Business Integration services to the Corporate
Director of Finance and Resources, in consultation with the Cabinet
Member for Finance and Corporate Services.
· the cost estimates were indicative and had been developed using market engagement, benchmarking, risk allowances and contingency provisions;
· final contract values and the recommended supplier or suppliers would be subject to a future Cabinet decision; and
·
no cashable savings had been assumed at this stage, with potential
benefits to be further assessed during procurement and
implementation.
Reasons for the decision
The existing SAP ECC
platform was approaching the end of mainstream support in December
2027. Following that date, the Council would have become
increasingly dependent on third-party support arrangements and
faced heightened risks relating to security, payroll operations,
legislative compliance, system resilience and audit
assurance.
The current system was
also limiting operational efficiency. Core Finance, Procurement,
Human Resources and Payroll processes relied on manual workarounds,
offline spreadsheets, duplicate data entry and fragmented
workflows. This increased the risk of errors, reduced efficiency
and limited access to timely and reliable management
information.
The recommended option
was supported by a structured assessment process. The Council
undertook market engagement, considered five options, and evaluated
them against agreed criteria. Delivery approaches were tested
through a Request for Information process and supported by a
ten-year total cost of ownership assessment.
The Council was
required to procure the technology, implementation, support and
associated services in accordance with the Procurement Act 2023,
Contract Standing Orders and relevant procurement legislation. The
proposed route to market was a further competition through the
Crown Commercial Service Back Office Software 2 (BOS2)
framework.
The Council confirmed that it was an eligible contracting authority under the ... view the full decision text for item 10
Minutes:
The Cabinet Member for Finance and Corporate introduced the report
It was stressed that the Council is focused on improving core services and organisational effectiveness.
It was explained that the Council was currently relying on manual processes and offline spreadsheets to support some finance, human resources and procurement activities. It is considered essential to modernise these systems to support the efficient delivery of services.
It was stressed that the Council needed a modern Enterprise Resource Planning (ERP)system. The risks associated with operating a system approaching obsolescence were recognised, and it was noted that some other local authorities had already implemented replacement solutions. To address this, the administration approved a procurement route and funding envelope, with a final supplier recommendation and confirmed costs to be presented to Cabinet at a later stage.
The Cabinet Member stressed that the procurement of a new system must follow appropriate procurement procedures and demonstrate good value for money. Given the Council’s financial position, expenditure would be subject to close scrutiny. However, replacing critical technology infrastructure was vital to ensure both operational effectiveness and service delivery.
It was explained that the proposed investment is intended to improve internal processes and enhance the experience of residents and staff. The aim is to provide systems that are more reliable, accessible and efficient when residents interacted with Council services, including making payments and submitting applications.
The administration stated its intention to secure greater value for money from the procurement activity and to focus on efficient and effective use of public resources in support of local communities.
Following questions from Councillors Carlin and Cawley-Harrison, the following information was shared: