114 Award of Contracts for Planned Investment Programme (Lifts) PDF 337 KB
Report of the Director for Placemaking and Housing. To be introduced by the Cabinet Member for Housing and Planning (Deputy Leader).
To seek approval for the appointment of the successful contractors to undertake lift improvements.
Minutes:
The Cabinet Member for Housing and Planning, and Deputy Leader of the Council introduced the report. It was explained that the current lifts had reached the end of their useful life and that replacement parts were becoming obsolete. It was explained that the modernisation of the lifts would ensure compliance with current lift standards and will provide residents and visitors with a reliable and efficient service when travelling the building.
In response to comments and questions from Cllr
Emery, the following information was shared:
RESOLVED:
That Cabinet:
1.
Approved the award of the Lift Modernisation Works
to 1-40 Bounds Green Court, N11 and 1-24 Woodmead, N17 contract to the company identified in
the exempt part of this report for the maximum sum of
£544,684 for a period of 33 weeks.
2.
Approved the issuance of a letter of intent for an
amount up to 10% of the winning bid value (£544,684)
totalling £54,468.
3.
Approved the professional fees and project
management costs of £44,714 that represents 7.91839% of the
contract sum.
4.
Agreed the total project costs.
REASONS FOR DECISION
The four lifts within this scheme were last
modernised in 2004 and are at the age where major improvements are
required. The project will allow works
to modernise the facilities whilst also alleviating the risk of
breakdowns and delays waiting for replacement
parts.
The recommendation is based on a
robust evaluation process following a competitive procurement
process conducted on Adam Procure Dynamic Purchasing System
(DPS).
The evaluation process was carried out in accordance with the Invitation to Tender requirements and was based on 60% price and 40% quality. The outcome of the evaluation was as follows:
Contractor |
Price 60% |
Quality 40% |
Total % |
Rank |
A |
60% |
32% |
92% |
1 |
B |
56% |
32% |
88% |
2 |
Further details of the tender and evaluation process are outlined in Appendix A, the exempt part of this report.
The recommended contractor A’s submitted tender was comprehensive and included well-chosen comparable examples, a good understanding of the contract’s risks and challenges and a good understanding how to add social value for residents.
ALTERNATIVE
OPTIONS CONSIDERED
An alternative option would be the use
of the London Construction Programme Major Works framework.
However, Haringey Council’s Strategic Procurement advised
that the DPS Framework would offer greater competition and would be
the optimum route to market. This considered aspects such as the
speed of access to pre-approved contractors ...