18 Corporate Performance Update PDF 382 KB
Report of the Director of Culture, Strategy and Engagement. To be introduced by the Leader of the Council.
Additional documents:
Minutes:
The Leader introduced the report which set out the progress made against the delivery of the commitments as set out in the Corporate Delivery Plan as at the end of June 2023.
In response to questions from Councillor da Costa, the following was noted:
- In regard to the District Energy Network, this was red rated due to the increased risk profile which was the same for all major capital schemes, due to the increase in inflationary costs around construction and the impact of interest rates in terms of borrowing.
- There were two lines on air quality because there were two sets of actions – one on the installation of pollution barriers at schools and the implementation of air quality audits, and the other in relation to School Streets.
- The Council were working closely with Fusion and third-party contractors to re-open Tottenham Green leisure centre.
RESOLVED to
1. Note the high-level progress made against the delivery of the commitments as set out in the Corporate Delivery Plan as at the end of June 2023.