West Green Primary School - Building Services Improvement and External Envelope Works - Award of Construction Contract

Meeting: 02/07/2021 - Cabinet Member Signing (Item 11)

11 West Green Primary School - Building Services Improvement and External Envelope Works - Award of Construction Contract pdf icon PDF 222 KB

Additional documents:

Minutes:

The Cabinet Member for Early Years, Children & Families considered the report which sought approval to award a contract toMulalley and Company Limited up to the value of £2,270,002.90 to undertake building services improvement and external envelope condition works at West Green Primary School pursuant to contract standing order 16.02 and, pursuant to Contract Standing Order (CSO) 16.02 to approve the issuance of a letter of intent.

1 

2 

 

RESOLVED that the Cabinet Member

i.          Approve an award to Mulalley and Company Limited of £2,063,639

ii.         Approve a client construction contingency of 10% that equates to £206,363.90, which will be strictly managed under change control governance arrangements

iii.        Approve the issuance of a letter of intent for up to 10% of the contract value totalling £206,363.90.

 

Reasons for decision

 

A major review of the condition and suitability of the Children’s Services estate has been undertaken which has informed the Children’s Service’s asset management plan (CSAMP).  This identified condition and suitability deficiencies in the primary, secondary, and wider Children’s Service estate that need addressing in the short, medium, and long-term.  West Green Primary School is high priority for major works due to issues relating to health and safety or school closure risks.

 

In 2018 an initial brief was given to undertake the most immediate (short term) health and safety, compliance, and resilience work. These findings included fire compartmentation, fire doors and heating resilience and were subject to a separate award under delegated powers.

 

In 2019 a further commission was given to further investigate and address urgent works relating to the condition of building services (ie heating, electrics and plumbing), external envelope (ie roofs, windows) and boundary security.

 

The scheme at West Green Primary School has been granted an allocation of funding (£325,000) from the public sector decarbonisation programme, a government initiative sponsored by the Department for Business, Energy & Industrial Strategy and administered by Salix (Salix works). The grant will be used to part fund the scheme thus reducing the amount of borrowing that the Council will need to undertake. The terms of the grant are that the relevant works need to be completed by the 30th September 2021. If this date is missed, then there is a risk that the grant allocation will need to be repaid. 

 

The works at West Green Primary School has been developed into 2 phases in order to minimise disruption to the school (referenced in 5.2) and achieve the criteria for Salix Public Sector Decarbonisation grant funding.  This construction award report requests a decision on the procurement of a contractor to undertake Phase 2 – building services improvement and external envelope condition works. Phase 1, which consists of the demolition of a redundant/end of life modular unit, has been tendered and awarded under delegated approval at c£17,400, as it is intended to complete Phase 1 during mid-July before the main works commence. This decision is for Phase 2 only. The scheme of works developed is to achieve the following:

 

·           Salix Public Sector Decarbonisation  ...  view the full minutes text for item 11