Approval of construction contract for St Mary’s Close and Nightingale Lane

Meeting: 15/09/2020 - Cabinet (Item 294)

294 Approval of construction contract for St Mary’s Close and Nightingale Lane pdf icon PDF 335 KB

[Report of the Director for Housing, Planning and Regeneration. To be introduced by the  Cabinet Member for Housing and Estate Renewal.]

 

This report will seek approval to award one construction contract for housing development at both St Mary's Close and Nightingale Lane and to appropriate the land for planning purposes.

Additional documents:

Minutes:

The Cabinet Member for Housing and Estate Renewal introduced the report which sought approval to appoint the recommended contractor to complete a new build development of five Council rented homes; two at St Mary’s Close N17 and three at Nightingale Lane N8, and to appropriate the land for planning purposes to facilitate the development process.

It was noted that on approval, these developments would be the seventh and eighth scheme to move to a start on site, of the 58 schemes in the Council housing delivery programme that the Council intends to directly deliver itself. It will be the twelfth and thirteenth schemes to move to a start on site in the overall programme.

Five new Council homes in two wards – two three-bedroom homes and three two-bedroom homes – meant that five households who are not currently adequately housed would be living in homes that met their needs.

 

Further to considering exempt information at item 27,

RESOLVED

  1. To approve the appointment of Cosmur Construction Limited to undertake the new build works to provide a total of five Council rented homes at St Mary’s Close and Nightingale Lane for a total contract sum of £1,348,437.49 and to approve the client contingency sum set out in the exempt part of the report.

 

  1. To approve the appropriation of the land at St Mary’s Close and Nightingale Lane (edged red in the plans attached at Appendix 1) from housing purposes to planning purposes under Section 122 of the Local Government Act 1972 as they are no longer required for the purpose which they are currently held, and for the purpose of carrying out development as set out in paragraphs 6.1 to 6.27 of this report.

 

  1. To approve the use of the Council’s powers under Section 203 of the Housing and Planning Act 2016 to override easements and other rights of neighbouring properties infringed upon by the St Mary’s development, under planning permission Ref: HGY/2020/0136 and by Nightingale Lane development, under planning permission Ref: HGY/2020/0159.

 

 

  1. To delegate to the Director of Housing, Regeneration and Planning, after consultation with the Director of Finance and the Cabinet Member for Housing and Estate Renewal, authority to make payments of compensation as a result of any infringement arising from the development and the recommendation 3.1.3, within the existing scheme of delegation.

 

  1. To approve the appropriation of the land at St Mary’s Close and Nightingale Lane (edged red in the plans attached at Appendix 1) from planning purposes back to housing purposes under Section 19 of the Housing Act 1985, after practical completion of the development on 31 December 2021.

Reasons for decisions

St Mary’s Close and Nightingale Lane was approved by Cabinet on 9 July 2019 to be included in the Council housing delivery programme. This scheme has subsequently been granted planning consent and is ready to progress to construction. This report therefore marks the third, and final, Member led decision to develop these two sites.

Following a formal tender process, a contractor has been identified  ...  view the full minutes text for item 294