61 Woodside House Refurbishment PDF 206 KB
[Report of the interim Director for Housing, Planning and Regeneration. To be introduced by the Cabinet Member for Strategic Regeneration.]
Budget report for the Woodside House Refurbishment Project.
Additional documents:
Minutes:
The Cabinet Member for Strategic Regeneration introduced this report which sought Cabinet approval to vary the original contract with T&B (Contractors) Limited by allowing the increase of the original value by up to £750,000.
The Cabinet Member had raised concern regarding overspend on the project, which had been approved by the previous administration. However, the Cabinet Member was satisfied the refurbishment of Woodside House would provide the Council with better facilities in the future. The Mayor’s parlour had relocated to Woodside House and there was an registry office for weddings to take place.
The Cabinet Member recognised it was unfortunate that previously unknown issues had arose during construction which meant the project would have to overspend to fix those issues, such as drainage problems that delayed had construction efforts. Cabinet were advised that the Council could face additional charges if it did not resolve the extra costs.
Following a question from Cllr Barnes, the following was noted:
Officers advised it was difficult to crossover lessons learned from the Woodside House Refurbishment project to new build projects, as the latter would likely not have pre-existing conditions
RESOLVED
Reasons for decision
To ensure Haringey Council can adhere to its contractual obligations and make payment of contract valuations.
Alternative options considered
In order to make invoiced interim valuation payments that are required in December and January, approval is required now, while final negotiations are completed (construction contracts allow six months for the presentation of the Final Account by the main contractor after Practical Completion of the works). If not approved, the council would be unable to make payment of the bi-monthly interim valuations, as well as Final Account payment and would mean it would be in breach of its contractual payment obligations and be at risk of incurring additional interest costs on unpaid amounts.