45 Disposal of the proposed shell and core facility at the Welbourne site in Tottenham Hale for use as a new health centre pdf icon PDF 3 MB

Additional documents:

Minutes:

The report sought approval to enter into an agreement for lease with Healthlink Investments Ltd for a unit at the prospective Welbourne development at Tottenham Hale in order to realise the Welbourne Health Centre.

 

The Leader noted that the agreement with Argent Related contained an obligation for them to deliver a health care facility to shell and core specification, of 1,500 square metres, with the Council taking a long lease back for this health care unit, subject to a further key decision on the financial and operational arrangements for the health centre. 

 

The report now sought this key decision in order to secure the health centre.  Because the financial and operational details of the Health Centre had now been resolved, it was proposed that the Council dispose of a long lease to HealthLink, the third party developer appointed by the GP practice.  HealthLink would fit out the health centre once Argent Related had completed the building and have leased the unit back to the Council.  The terms of the disposal to HealthLink would be as set out in the agreed Heads of Terms, as referred to in Annex C of this report.

 

The CCG required a commitment from the Council to support the preliminary approval in order to secure the funding of the proposed health centre. Full business approval would be needed after planning consent was granted for the development scheme to be put forward by Argent Related, which was estimated for later in 2018.  It was proposed that the Council agree now to dispose of the property based on a long lease to HealthLink Investments Ltd, appointed by the CCG to fit out the health centre, as per the Heads of Terms as referred to in Annex C of this report.

 

In response to questions from Cllr Brabazon and Cllr Connor, the following was noted.

 

·         Argent Related had the responsibility for providing a health centre, regardless of the type of regeneration scheme being taken forward.

 

·         Noted that the disposal of the lease would be for a term of 125 years for the premium set out in and based on the agreed Heads of Terms attached in Annex C of this report. Therefore, the council would be obtaining a premium receipt for the lease and HealthLink Investments Ltd would be funding the fit out of the new health centre.

 

·         It was not yet known what the range of health facilities expected to be provided form the new health centre would be. Agreed that Cllr Connor is provided with an update on when this decision is due to be made by the CCG and Health and Wellbeing board.

 

Further to considering private information at item 8,

 

RESOLVED

 

1.    To approve the disposal to HealthLink Investments Limited of the new health facility unit (outlined in red in the plan in Appendix A2) to be built by TH Ferry Island Limited Partnership under the Development Agreement dated 21 March 2017 on the Welbourne Centre site in Tottenham Hale subject to the Lease back  ...  view the full minutes text for item 45