To advise of major proposals in the pipeline including those awaiting the issue of the decision notice following a committee resolution and subsequent signature of the section 106 agreement; applications submitted and awaiting determination; and proposals being discussed at the pre-application stage.
Additional documents:
Minutes:
The Committee considered an update on major planning proposals in the pipeline.
In response to a question, confirmation was provided that there were two alternative proposals at pre-application stage currently for 163 Tottenham Lane.
RESOLVED
· That the report be noted.
17 UPDATE ON MAJOR PROPOSALS
PDF 116 KB
To advise of major proposals in the pipeline including those awaiting the issue of the decision notice following a committee resolution and subsequent signature of the section 106 agreement; applications submitted and awaiting determination; and proposals being discussed at the pre-application stage.
Additional documents:
Minutes:
The Committee considered an update on major planning proposals in the pipeline and raised the following questions:
270-274 West Green Road
Officers updated that this application had now been refused on the basis of the absence of an affordable housing contribution.
Lee Valley technopark
Confirmation was provided that part of the scheme would extend through the Ashley Road depot site.
Hale Village Tower
A revised proposal had been put forward for the tower to be designated residential instead of a hotel. A variation would be required to the s106 agreement and recalculation of the affordable housing contribution. The proposal would come before the Committee at pre application stage.
St Lukes
An application had been submitted to remove the age related limitation for the co-housing units, a small element of the scheme.
2 Canning Crescent
Concerns were raised over the potential loss of employment land. Officers noted these concerns and agreed to circulate to the Committee details of how much employment land would be reprovided.
GLS depot
This was the original application for the Hale Village site and which was still under construction.
Dyne House, Highgate School
Officers agreed to seek an update on progress with this application from the planning policy team for circulation to the Committee.