206 Lift Modernisation - Group 4: Sheltered Blocks: 45-63 Palace Gates (Braemar Ave), 1-34 Sophia House, 1-27 The Lindales, 1-34 Bedale House, 1-34 & 37-44 Cranley Dene, 1-32 Hilldene Court
PDF 303 KB
(Report of the Director of Adult and Housing
Services to be introduced by the Cabinet Member for Housing). The
report seeks approval to award the contract in principal for the
lift modernisation work at addresses set out above.
Additional documents:
Minutes:
Cabinet were asked to agree to
award a contract in principle for required lift modernisation works
at the above listed council owned housing blocks.
RESOLVED
- That
the award of contract for the above project, as allowed under
Contract Standing Order (CSO) 9.07.1(d) (a) based on the lowest
priced tender received.
- That
the total cost including fees as detailed in Para3.1 of Appendix A
be noted.