125 19 Clarendon Road, N8 PDF 31 KB
Erection of part single story/part two storey/part three storey side and front extensions, and use of the building including rear shed as a cultural community centre.
RECOMMENDATION: Grant permission subject to conditions.
Additional documents:
Minutes:
This item had been deferred from the previous meeting of the Committee on 11 January 2010. The Committee considered a report, previously circulated, which gave details of the application, the applicant’s case, the site and its environment, planning history and all of the relevant planning factors and policies.
The Planning Officer gave a summary of the report submitted and took questions from the Committee. It was reported the plans had been revised to address the issues raised at the site visit by Committee Members in respect of fenestration.
In response to concerns raised by the Committee that there was a need for increased signage for the new spine road, it was agreed that Cllr Dodds would contact Transport regarding this issue directly, outside the meeting.
In response to a question from the Committee regarding the suggestion for a green roof, it was confirmed that Condition 4 could be varied to include the requirement for a green roof, and this was agreed by the Committee. It was agreed that an additional Condition 4 be placed on the consent seeking sustainable measures be incorporated into the design.
In response to a concern raised by the Committee that the proposed structure was too close to existing flats, it was reported that, further to a requirement for the applicant to move the three-storey element further from the block, the gap between the structures was felt to be acceptable.
It was further agreed that an informative be added that the community centre should work with other cultural centres and industrial units in the area to maximise parking in industrial areas during evening hours to reduce the impact of parking in the local area.
RESOLVED
That, subject to the conditions set out below, planning application reference HGY/2009/1892 be granted.
Location: 19 Clarendon Road N8
Proposal: Erection of part single storey / part two storey / part three storey side and front extensions, and use of the building including rear shed as a cultural community centre.
Recommendation: Grant subject to conditions
Decision: Grant subject to conditions
Drawing No’s: 2-5, 6a, 7-13 incl.
Conditions:
IMPLEMENTATION/ OF THE CONSENT
1. The development hereby authorised must be begun not later than the expiration of 3 years from the date of this permission, failing which the permission shall be of no effect.
Reason: This condition is imposed by virtue of the provisions of the Planning & Compulsory Purchase Act 2004 and to prevent the accumulation of unimplemented planning permissions.
2. The development hereby authorised shall be carried out in complete accordance with the plans and specifications submitted to, and approved in writing by the Local Planning Authority.
Reason: In order to ensure the development is carried out in accordance with the approved details and in the interests of amenity.
EXTERNAL APPEARANCE
3. Notwithstanding the description of the materials in the application, no development shall be commenced until precise details of the materials to be used in connection with the development hereby permitted have been submitted to, approved in writing by and implemented ... view the full minutes text for item 125